IN THE HIGH COURT OF DELHI AT NEW DELHI
Rajiv Shakdher, Amit Bansal, JJ.
Idbi Bank Limited On Behalf of Senior Lenders - Appellant
Versus
National Highways Authority of India - Respondent
LPA 681 of 2022 & CM Nos. 50927-28 of 2022
Decided On : 21-02-2024
Concession Agreement - Extension of Concession Period - CA, SA, EA, FA, SPA - Articles 29, 34, 35
Fact of the Case:
The appellant sought relief for extension of the concession period under the concession agreement (CA) dated 06.06.2008. Disputes arose between the appellant, NHAI, and Pink City Expressway Private Limited. The Single Judge declined relief for prayers (a) to (e) and (g) and directed further instructions for prayer clause (f).
Finding of the Court:
The Court held that the appellant cannot seek a writ for extension of the concession period as it is not a party to the CA. The interim extension granted by NHAI expired, and the Court suggested the appellant to seek remedy under the agreements with all defences available to NHAI.
Issues: Interpretation of rights under the concession agreement and related agreements, authority to seek extension of concession period, and the availability of remedies for the appellant.
Ratio Decidendi: The Court emphasized that the appellant cannot seek a writ for extension of the concession period as it is not a party to the CA. The Court suggested the appellant to seek remedy under the agreements with all defences available to NHAI.
Final Decision: The appeal was disposed of, and the pending applications were closed.
JUDGMENT
[Physical Hearing/Hybrid Hearing (as per request)]
Rajiv Shakdher, J. (Oral)
1. This appeal is directed against the interim order dated 01.06.2022 passed by the learned Single Judge in W.P.(C) No. 7806/2022.
1.1. In sum, the appellant had approached the writ court with several pleas which are replicated in the impugned order.
2. Via the impugned order, the learned Single Judge declined to grant relief with regard to prayers made in clause (a) to (e) and (g). Insofar as prayer clause (f) is concerned, the learned Judge had directed counsel for the respondent/NHAI to take further instructions.
2.1. It is not in dispute that the prayers declined by the learned Single Judge concerned issuance of a direction to the respondent/National Highways Authority of India (NHAI) to extend the concession period under concession agreement [CA] dated 06.06.2008.
3. Mr Sandeep Sethi, learned senior counsel, who appears on behalf of the appellant, says that even while the learned Single Judge held that the concession agreement was a "cohesive, composite and interlinked repository of the bargain between the disputants", he has ended up compromising the rights of the appellant as is evident upon perusal of the observations made in paragraphs 13 to 17 of the impugned judgment.
4. According to Mr Sethi, there are several rights which flow in favour of the appellant by virtue of substitution agreement [SA] dated 12.02.2009, escrow agreement [EA] dated 12.02.2009, restated facility agreement [FA] dated 18.06.2009 and the supplementary agreement [SPA] dated 20.12.2013.
5. Only the respondent/NHAI and the concessionaire, i.e., Pink City Expressway Private Limited [in short, "Pink City"] are parties to the CA and SPA.
6. Insofar as the SA is concerned, it is executed amongst Pink City, respondent/NHAI and the appellant (acting for and on behalf of the Senior lenders). The EA was executed amongst Pink City, the appellant, the escrow bank and respondent/NHAI. The restated facility agreement has been entered into between Pink City, the senior lenders and India Infrastructure Finance Company Limited.
7. Mr Sethi has taken us through various clauses of the agreements, referred to hereinabove including the CA, in an attempt to establish that the appellant had, in fact, a right to call upon the respondent no. 1/NHAI to extend the concession agreement.
7.1. It is also Mr Sethi's contention that the appellant had a right to substitute the concessionaire.
8. On the other hand, Mr Parag Tripathi, learned senior counsel, who appears on behalf of the respondent, says that no such right vested in the appellant.
8.1. Mr Tripathi has brought to the fore an aspect, which is not in dispute, that respondent/NHAI has infused Rs. 352 crores into the subject project via the One Time Fund Infusion Scheme [Scheme].
8.2. It is Mr Tripathi's contention that the principal sum alone is Rs. 321 crores and nothing has been repaid to respondent/NHAI.
9. We may note that the original total project cost was estimated at Rs. 3,009/- crores.
9.1. It is the appellant's claim that it provided approximately Rs.1876.37 crores for the project of which Rs.1297 crores remains outstanding as on 02.06.2022, exclusive of penal interest, charges, and costs, etc.
10. The record shows that the project involved augmentation of the existing four lane road spanning between km 42.70 to km 273 (approximately 225.60 km), on the Gurgaon - Kotputli - Jaipur section of National Highway No. 8, in the State of Haryana and Rajasthan ["carriageway"].
11. The concessionaire was required to widen the carriageway to six (6) lanes, albeit, on a built, operate and transfer model.
12. As things stand today, disputes have erupted not only between the appellant and the respondent/NHAI but also between the respondent/NHAI and Pink City.
13. What we are required to rule upon is whether the learned Single Judge's conclusion that the reliefs (a) to (e) and (g) are not tenable in law or on facts, call for interference.
14. Mr Sethi submits
The appellant cannot seek a writ for extension of the concession period as it is not a party to the concession agreement, and suggested to seek remedy under the agreements with all defences available....
Lenders cannot independently seek extension of concession period under Concession Agreement, their rights do not confer standing in this matter according to the agreements in place.
The main legal point established in the judgment is that the right to seek extension of the concession period was vested in the concessionaire alone, and the senior lenders did not have the independe....
A concession period extension under a contract requires compliance with specific procedural conditions, and is not automatic despite recommendations from an independent engineer.
The Court emphasized the limited scope of interference in appeals under Section 37 of the Arbitration Act and upheld the findings of the Arbitral Tribunal and the Single Judge based on plausibility a....
The court clarified that the powers under Section 9 of the Arbitration and Conciliation Act cannot extend to granting specific performance of a contract or automatic extensions beyond terms explicitl....
The court affirmed that the Tribunal's rejection of the appellant's request for interim measures was valid due to established insufficient funding and non-compliance, affirming limited grounds for in....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.