DELHI HIGH COURT
SANJIV KHANNA, CHANDER SHEKHAR
Delhi Metro Rail Corporation Ltd. – Appellant
Versus
Delhi Airport Metro Express Private Limited – Respondent
Based on the provided legal document, here are the key points extracted with their respective references:
Case Details and Parties * The case is an intra-Court appeal filed by Delhi Metro Rail Corporation Ltd. (DMRC) against Delhi Airport Metro Express Private Limited (DAMEPL). (!) * DMRC is a state-owned company with equal participation from the Government of India and the Government of National Capital Territory of Delhi. (!) * DAMEPL is a special purpose vehicle incorporated by a consortium of M/s Reliance Infrastructure Limited and M/s Construcciones Y Auxiliar de Ferrocarriles SA. (!) * The dispute relates to the Concession Agreement (CA) signed on 25th August, 2008, for the construction, operation, and maintenance of the Delhi Airport Metro Express Line (AMEL). (!)
Background and Timeline of Events * DMRC undertook land acquisition and civil structures, while DAMEPL was responsible for railway systems, rolling stock, and signaling. (!) * DAMEPL was entitled to collect fares and non-fare revenue, and was required to pay an annual concessionaire fee of Rs.51 crores. (!) * DAMEPL paid the concessionaire fee for the first year but stopped subsequent payments, requesting deferment due to financial constraints and lack of retail revenue. (!) * On 8th July, 2012, DAMEPL stopped operations citing unsafe conditions regarding viaduct bearings and girders. (!) * DAMEPL issued a cure notice on 9th July, 2012, and subsequently a termination notice on 8th October, 2012, under Article 29.5.1 of the CA. (!) * Repairs were undertaken, and on 18th January, 2013, the Commissioner of Metro Road Safety (CMRS) granted sanction to restart operations with speed restrictions. (!) * DAMEPL resumed operations on 22nd January, 2013, and handed over the project to DMRC on 30th June, 2013. (!) * An Arbitral Tribunal was constituted on 8th August, 2013, and pronounced its award on 11th May, 2017. (!)
Arbitral Award Findings * The Arbitral Tribunal held that there were defects in the civil structure (cracks, twists, gaps) which were not cured within the 90-day period specified in the cure notice. (!) * The Tribunal found that these defects had a "Material Adverse Effect" on DAMEPL's ability to perform obligations, validating the termination notice under Article 29.5.1. (!) * The Tribunal held that DAMEPL's participation in meetings and operations after the termination notice was "without prejudice" to their rights and did not amount to a waiver. (!) * The Award directed DMRC to pay DAMEPL a termination payment of Rs.2782.33 crores, comprising debt due and 130% of adjusted equity. (!) * The Tribunal included Rs.611.95 crores as part of the "adjusted equity" despite DAMEPL's balance sheets categorizing it as subordinate debt. (!)
High Court Judgment (Appeal) * The High Court set aside the findings regarding the validity of the termination notice due to confusion and contradiction in the Award regarding the date of termination (8th October, 2012 vs. 7th January, 2013). (!) * The Court held that the Award suffered from perversity and patent illegality for ignoring the statutory sanction granted by CMRS on 18th January, 2013, which certified the safety of the line. (!) * The Court set aside the finding that Rs.611.95 crores should be treated as equity, ruling it perverse to ignore the Board resolution converting share application money into subordinate debt. (!) * Consequently, the direction to pay interest under Article 29.8 on the termination payment was held infructuous. (!) * The Court set aside the Award in its entirety regarding the termination payment and consequential reliefs, leaving the matter for fresh adjudication via arbitration. (!) * The Court upheld the finding that DAMEPL did not waive the termination notice by election or conduct. (!)
JUDGMENT
Sanjiv Khanna, J. Delhi Metro Rail Corporation Ltd. ('DMRC', for short) in this intra-Court appeal under Section 37 of the Arbitration and Conciliation Act, 1996 (`A & C' Act, for short) read with Section 13 of the Commercial Courts, Commercial Division and Commercial Appellate Division of the High Courts Act, 2015 has impugned judgment and order dated 6th March, 2018, whereby the learned single Judge has dismissed objections under Section 34 of the A & C Act upholding the award dated 11th May, 2017 passed by the Arbitral Tribunal.
2. DMRC is a state-owned company with equal participation from the Government of India and the Government of National Capital Territory of Delhi.
3. The respondent, Delhi Airport Metro Express Private Limited ('DAMEPL', for short), is a company incorporated as a special purpose vehicle by the consortium of M/s Reliance Infrastructure Limited and M/s Construcciones Y Auxiliar de Ferrocarriles SA, Spain (`consortium', for short).
4. The consortium were successful bidders in the international competitive bidding process for construction, operation and maintenance of the Delhi Airport Metro Express Line (`AMEL', for short) based on Public-Priv
The main legal point established in the judgment is the binding effect of the settlement between the parties, the waiver of the right to seek re-employment by the workmen, and the entitlement of the ....
A lockout is justified if it is declared in response to an illegal strike or a strike that is in breach of a settlement or award.
The combination of eyewitness testimonies, recovery of the weapon used, and forensic examination results can establish guilt in criminal cases, even based on circumstantial evidence.
The conviction of an accused person under Section 27(3) of the Arms Act is not permissible in law if the accused is also charged with committing murder under Section 302 of the Indian Penal Code.
The court can enhance compensation based on the deceased's income and family dependency, and adjust the multiplier used by the Tribunal if found unjustified.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.