SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img



IN THE HIGH COURT OF DELHI
Vibhu Bakhru, J.
National Highways Authority of India - Appellant
Versus
C.P. Rama Rao (Proprietor) - Respondent
O.M.P. (COMM) 127 of 2021 and IA Nos. 4107 of 2021 & 4106 of 2021
Decided On : 23-03-2021




The introduction of GST is a change in law that materially affects contractual obligations, enabling claims for force majeure under the Contract Agreement.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - Disputes over Contract Agreement for toll collection - The petition was filed challenging an Arbitral Award on the grounds of misunderstanding 'force majeure' under Clause 25(b) due to GST implementation.


(B) Change in Law - Introduction of GST is considered a 'change in law' having material adverse effects, allowing relief under force majeure.


(C) Performance Security - Respondent entitled to the release of performance security and waiver of certain payments as per Tribunal's determination.



Facts of the case:
NHAI entered into a Contract Agreement with the respondent for toll collection. Following the GST rollout, the respondent claimed significant losses due to reduced traffic. NHAI rejected a claim for force majeure.


Findings of Court:
The Arbitral Tribunal found the GST introduction as a change in law, allowing the respondent's claims for losses due to a force majeure event.


Issues: The court addressed if the GST implementation constituted a force majeure event and the implications on contractual obligations.


Ratio Decidendi: The Tribunal concluded that the GST's impact led to a material adverse effect, thereby qualifying as force majeure under the Contract Agreement.


Result: Petition dismissed; the Arbitral Award upheld.

Table of Content
1. basics of the contract and gst implementation. (Para 1 , 2 , 3 , 4 , 5 , 6)
2. claim of force majeure due to gst impact. (Para 7 , 8 , 9 , 10 , 11 , 12)
3. arbitral verification of claimed losses. (Para 13 , 14 , 16)
4. nhai challenges claim based on contract terms. (Para 15 , 20 , 21)
5. interpretation of law change regarding gst. (Para 22 , 23 , 24 , 25 , 26 , 27)
6. finding on material adverse effect on obligations. (Para 28 , 29 , 30 , 31)
7. jurisdiction of the arbitral tribunal's interpretation. (Para 32 , 33 , 34 , 35)
8. final decision of the court regarding award. (Para 36 , 38)

JUDGMENT

Vibhu Bakhru, J. (Oral)--The petitioner (hereinafter `NHAI) has filed the present petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter the `A&C Act'), inter alia, impugning the Arbitral Award dated 12.12.2020 (hereinafter the `impugned award') passed by the Arbitral Tribunal comprising of a Sole Arbitrator.

2. The impugned award was rendered in respect of disputes that had arisen between the parties in relation to an agreement dated 30.07.2016 (hereinafter the `Contract Agreement') entered into between the parties for "Collection of user fee of Vemapadu Fee Plaza at Km. 795.498 for Ankaapalli to Tuni Section from Km. 358.00 to Km. 272.00 (New Chainage from Km. 830.525 to Km. 741.255) of NH-5 in the State of Andhra Pradesh" (hereinafter the `project').

3. On 17.06.2016, NHAI invited tenders by issuing a Request for Proposal (RFP) in respect of work relating to collection of User Fee at Vempadu Toll Plaza located at Km. 795.498 on the stretch extending from Km. 830.525 to Km. 741.255 on National Highway No.5 (now renamed as National Highway No.16) in the State of Andhra Pradesh.

4. On 21.07.2016, the respondent submitted the financial bid for the aforesaid work. He was declared the highest bidder and NHAI issued a Letter of Acceptance. Thereafter, on 30.07.2016, the parties entered into a Contract Agreement, whereby the respondent was granted the concession for collecting User Fee at Vempadu Toll Plaza for a period of one year with effect from 08:00:00 hours on 01.08.2016 to 07:59:59 hours on 01.08.2017. In terms of the Contract Agreement, the respondent was required to pay Rs.2,24,40,274/- per week to NHAI. The said payment was exclusive of any TCS or any taxes or service charges as applicable.

5. In terms of Clause 19 of the Contract Agreement, the respondent was liable to pay penalty at the rate of 0.2% per day for initial one month delay and at the rate of 0.5% per day for further delay beyond one month in remittance of the agreed amount. In terms of Clause 17(b)(i) of the Contract Agreement, the respondent also furnished the following performance security: (i) cross DD, Pay order in the sum of Rs.9,75,09,000/- and (ii) bank guarantee being BG No. 24/2016 dated 30.07.2016 in the sum of Rs.9,75,09,000/- issued by Indian Bank.

6. The Government of India rolled out the Goods of Services Tax (GST) with effect from 01.07.2017. The said levy subsumed all indirect taxes.

7. The respondent claimed that in view of the uncertainty surrounding the implementation of GST, there was a rapid decline in the movement of traffic and it adversely affected the collection of tolls. The respondent brought this to the notice of NHAI by its letter dated 05.07.2017.

8. The respondent informed NHAI that he had incurred a loss of Rs.52,62,228/- on account of reduction in collection of tolls for the period 28.06.2017 to 05.07.2017. According to the respondent, the said communication was received by the Project Director (PD) and was submitted to the Regional Office (RO) for assessment. Thereafter, the respondent sent another letter dated 08.07.2017, tabulating the loss incurred by him for the period from 28.06.2017 to 07.07.2017 at Rs.62,89,975/-. This was also followed by another letter dated 12.07.2017 whereby the respondent quantified the loss for the period from 28.06.2017 to 11.07.2017 at Rs.85,21,

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top