IN THE HIGH COURT OF DELHI
Vibhu Bakhru, J.
National Highways Authority of India - Appellant
Versus
C.P. Rama Rao (Proprietor) - Respondent
O.M.P. (COMM) 127 of 2021 and IA Nos. 4107 of 2021 & 4106 of 2021
Decided On : 23-03-2021
| Table of Content |
|---|
| 1. basics of the contract and gst implementation. (Para 1 , 2 , 3 , 4 , 5 , 6) |
| 2. claim of force majeure due to gst impact. (Para 7 , 8 , 9 , 10 , 11 , 12) |
| 3. arbitral verification of claimed losses. (Para 13 , 14 , 16) |
| 4. nhai challenges claim based on contract terms. (Para 15 , 20 , 21) |
| 5. interpretation of law change regarding gst. (Para 22 , 23 , 24 , 25 , 26 , 27) |
| 6. finding on material adverse effect on obligations. (Para 28 , 29 , 30 , 31) |
| 7. jurisdiction of the arbitral tribunal's interpretation. (Para 32 , 33 , 34 , 35) |
| 8. final decision of the court regarding award. (Para 36 , 38) |
JUDGMENT
Vibhu Bakhru, J. (Oral)--The petitioner (hereinafter `NHAI) has filed the present petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter the `A&C Act'), inter alia, impugning the Arbitral Award dated 12.12.2020 (hereinafter the `impugned award') passed by the Arbitral Tribunal comprising of a Sole Arbitrator.
2. The impugned award was rendered in respect of disputes that had arisen between the parties in relation to an agreement dated 30.07.2016 (hereinafter the `Contract Agreement') entered into between the parties for "Collection of user fee of Vemapadu Fee Plaza at Km. 795.498 for Ankaapalli to Tuni Section from Km. 358.00 to Km. 272.00 (New Chainage from Km. 830.525 to Km. 741.255) of NH-5 in the State of Andhra Pradesh" (hereinafter the `project').
3. On 17.06.2016, NHAI invited tenders by issuing a Request for Proposal (RFP) in respect of work relating to collection of User Fee at Vempadu Toll Plaza located at Km. 795.498 on the stretch extending from Km. 830.525 to Km. 741.255 on National Highway No.5 (now renamed as National Highway No.16) in the State of Andhra Pradesh.
4. On 21.07.2016, the respondent submitted the financial bid for the aforesaid work. He was declared the highest bidder and NHAI issued a Letter of Acceptance. Thereafter, on 30.07.2016, the parties entered into a Contract Agreement, whereby the respondent was granted the concession for collecting User Fee at Vempadu Toll Plaza for a period of one year with effect from 08:00:00 hours on 01.08.2016 to 07:59:59 hours on 01.08.2017. In terms of the Contract Agreement, the respondent was required to pay Rs.2,24,40,274/- per week to NHAI. The said payment was exclusive of any TCS or any taxes or service charges as applicable.
5. In terms of Clause 19 of the Contract Agreement, the respondent was liable to pay penalty at the rate of 0.2% per day for initial one month delay and at the rate of 0.5% per day for further delay beyond one month in remittance of the agreed amount. In terms of Clause 17(b)(i) of the Contract Agreement, the respondent also furnished the following performance security: (i) cross DD, Pay order in the sum of Rs.9,75,09,000/- and (ii) bank guarantee being BG No. 24/2016 dated 30.07.2016 in the sum of Rs.9,75,09,000/- issued by Indian Bank.
6. The Government of India rolled out the Goods of Services Tax (GST) with effect from 01.07.2017. The said levy subsumed all indirect taxes.
7. The respondent claimed that in view of the uncertainty surrounding the implementation of GST, there was a rapid decline in the movement of traffic and it adversely affected the collection of tolls. The respondent brought this to the notice of NHAI by its letter dated 05.07.2017.
8. The respondent informed NHAI that he had incurred a loss of Rs.52,62,228/- on account of reduction in collection of tolls for the period 28.06.2017 to 05.07.2017. According to the respondent, the said communication was received by the Project Director (PD) and was submitted to the Regional Office (RO) for assessment. Thereafter, the respondent sent another letter dated 08.07.2017, tabulating the loss incurred by him for the period from 28.06.2017 to 07.07.2017 at Rs.62,89,975/-. This was also followed by another letter dated 12.07.2017 whereby the respondent quantified the loss for the period from 28.06.2017 to 11.07.2017 at Rs.85,21,
The introduction of GST constituted a 'change in law' and had a material adverse effect on the obligations of the parties under the Contract Agreement, entitling the respondent to remission of paymen....
The main legal point established in the judgment is the importance of interpreting contractual provisions in accordance with their plain language and the grounds for challenging an award under Sectio....
Demonetisation constituted a force majeure event under the contract, materially affecting obligations, thus allowing waiver of payment claims.
An expulsion under a contract must have legitimate causes, and unjustified actions by one party render such expulsion illegal, reaffirming constraints under arbitration frameworks.
The main legal point established in the judgment is the interpretation of the force majeure clause, the arbitrability of certain claims, and the application of legal principles established in previou....
The arbitral Tribunal found NHaI's actions to expel the respondent from the site was unjustified and illegal based on various grounds, including the delay in granting Extension of Time (EOT) and the ....
Parties are entitled to interest on payments due under contracts; if no timeframe is specified, payments are due within 15 days of demand. The distinction between interest payments and debt repayment....
The main legal point established in the judgment is the interpretation and application of Section 34 of the arbitration and Conciliation act, 1996 to an international commercial arbitration, and the ....
The inapplicability of the ground of patent illegality to international commercial arbitration and the importance of interpreting specific contractual clauses in determining the validity of claims an....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.