SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img



IN THE HIGH COURT OF DELHI
Vibhu Bakhru, J.
National Highways Authority of India - Appellant
Versus
PCL-STICCO (JV) - Respondent
O.M.P. (COMM) 77 of 2016 & I.A No. 2511 of 2021
Decided On : 23-03-2022




An expulsion under a contract must have legitimate causes, and unjustified actions by one party render such expulsion illegal, reaffirming constraints under arbitration frameworks.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - Disputes arising from a contract for construction between National Highways Authority of India and a contractor - The court reviewed the legality of the Arbitral Tribunal's award which included findings on the wrongful expulsion of the contractor and the circumstances surrounding extensions of time (Paras 1-39).

(B) Arbitral Tribunal's Findings - The Tribunal concluded NHAI's expulsion of the contractor was unjustified and highlighted NHAI's delays and non-compliance with contractual obligations as factors in the disputes (Paras 13, 23).

Facts of the case:
NHAI awarded a contract to the respondent for highway works, which faced significant delays leading to disputes and arbitration. NHAI alleged slow progress from the contractor and subsequently expelled them from the site (Paras 3-9).

Findings of Court:
The Tribunal found NHAI bound by contractual obligations and the delays attributable to it. Hence, the expulsion of the contractor was declared illegal (Paras 22-39).

Issues: The legality of NHAI’s actions in expelling the contractor and their justified grounds for delaying extensions of time (Paras 12, 22).

Ratio Decidendi: The court upheld that an expulsion under a contract must be justified by legitimate causes, and unjustified actions by one party do not permit such an expulsion (Paras 33-34).

Result: The petition dismissed.

Table of Content
1. background of arbitration and contractual obligations. (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8 , 9 , 10)
2. claims made by the respondent in arbitration. (Para 11 , 12)
3. observations on the legality of nhai’s actions. (Para 13 , 14 , 22 , 23 , 24 , 25 , 26 , 30 , 31)
4. grounds for dismissing claims of patent illegality. (Para 33 , 34 , 35 , 36)
5. conclusion and order dismissing the petition. (Para 38 , 39)

JUDGMENT

Vibhu Bakhru, J. The National Highways Authority of India (hereinafter `NHAI') has filed the present petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter `the A&C Act') impugning an Arbitral Award dated 15.12.2015 (hereinafter `the impugned award') delivered by an Arbitral Tribunal comprising of three members - Justice (Retd.) Shri E. Padmanabhan, Shri T.C. Bhagoria and Shri Surjeet Singh as the Presiding Arbitrator (hereinafter `the Arbitral Tribunal').

2. The impugned award was rendered by the Arbitral Tribunal in respect of disputes that had arisen between the parties in connection with the Agreement for "Widening to 4/6 lanes and strengthening of existing 2-Lane Carriageway of NH-5 in the State of Orissa from Km 284.00 to Km 338.00 (Ganjam-Sunkhala) Contract Package OR-VII".

3. NHAI had invited bids for the aforesaid works in the year 2001. On 30.03.2001, the respondent submitted its bid pursuant to the said invitation to tender. The respondent's bid was accepted by a Letter of Acceptance (LoA) dated 09.07.2001, and the contract was awarded to the respondent.

4. Thereafter, on 20.08.2001, the parties entered into a formal contract (hereinafter `the Contract'). The date for commencement of the works was stipulated as 22.09.2001, and the works were to be completed within a period of thirty-two months, that is, by 21.04.2004.

5. The execution of the works was delayed and by a letter dated 31.07.2003, the respondent sought extension of time (EOT) till 30.06.2005. NHAI granted the same by a letter dated 01.08.2003. Thereafter, the respondent again sought EOT till 31.12.2005, which was granted by NHAI by its letter dated 20.09.2004. Thereafter, the respondent sought EOT till 30.06.2006 which was also granted by NHAI by its letter dated 05.08.2005.

6. Since the works were further delayed, the respondent applied for EOT till 31.12.2007 by a letter dated 13.06.2006. The respondent's request for EOT was recommended by the Engineer by its letter dated 08.07.2006. However, NHAI did not confirm the same.

7. NHAI alleged that the progress of the works was slow and the respondent had practically abandoned the site. On 12.05.2007, the Team Leader recommended that the Contract be repudiated in case of non-completion of the works by 31.12.2007. Thereafter, by a letter dated 05.06.2007, the respondent once again sought EOT till 31.12.2008. However, by a letter dated 14.06.2007, the Engineer declined the request for EOT and stated that it had recommended repudiation of the Contract.

8. The parties conducted mutual discussions and the respondent also proposed by its letter dated 23.10.2007 that the Contract be amicably foreclosed. On 31.03.2008, the respondent once again sent a letter reminding NHAI to consider its request for grant of EOT and/or foreclosure of the Contract.

9. By a letter dated 03.04.2008, NHAI rejected the respondent's request for foreclosure of the Contract. It issued a separate letter dated 03.04.2008 initiating action under Sub-clause 63.1 of the General Conditions of Contract (hereinafter `GCC') and expelled the respondent from the Contract.

10. The resultant disputes between the parties were referred to arbitration.

11. Before the Arbitral Tribunal, the respondent filed a Statement of Claims and raised the following claims:

Claim No.Particulars of ClaimAmount of claim
1.Unpaid amount of balance work executed including claim of escalation for which Bank Guarantee was given and the same had been encashed by the respondent.Rs.20,71,14,460/-
2.Claim

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top