IN THE HIGH COURT OF DELHI
Vibhu Bakhru, J.
Janta Associates - Appellant
Versus
Indian Oil Foundation - Respondent
O.M.P.(I) (COMM.) 74 of 2020
Decided On : 11-05-2021
| Table of Content |
|---|
| 1. background of the arbitration and contract issues. (Para 1 , 2 , 3 , 4 , 5) |
| 2. respondent's reasons for termination and dispute. (Para 6 , 7) |
| 3. petitioner's claims and court's reasoning on staying actions. (Para 9 , 10 , 11 , 12 , 13) |
| 4. application of legal principles from case law. (Para 14 , 15 , 16) |
| 5. final dismissal of the petition. (Para 18 , 19) |
JUDGMENT
[Hearing held through videoconferencing]
Vibhu Bakhru, J. (Oral)--The petitioner has filed the present petition under Section 9 of the Arbitration and Conciliation Act, 1996 (hereafter A&C Act), inter alia, praying as under:
"a. Ex-parte stay and set aside the Show Cause Notice dated 24.02.2020 issued by the Respondents;
b. Direct the Respondents to pay the due amount of Rs.1,89,91,737/- (Rupees One Crore Eighty Nine Lakh Ninety One Thousand Seven Hundred and Thirty Seven Only) to the Petitioner and allow the Petitioner to continue to complete the work by providing modified dam drawings;
OR, in the alternative
Direct the Respondents to secure the due amount of Rs.1,89,91,737/- (Rupees One Crore Eighty Nine Lakh Ninety One Thousand Seven Hundred and Thirty Seven Only) by way of a bank guarantee or by deposit with the Court during the pendency of the present petition and the arbitration proceedings;
c. Direct the Respondents to withdraw the Termination Notices dated 06.01.2020, 13.01.2020 and 28.01.2020, and restrain the Respondents from taking any such adverse/coercive actions against the Petitioner during the pendency of the present petition;"
2. The respondent no.2 (hereafter `EIL') had invited e-bids for "Composite Works for Development of Infrastructure Facilities at Khajekhalan Ghat, Patna Sahib, Patna" on behalf of respondent no.1 (hereafter `IOF'). The petitioner had submitted its bid which was accepted by the respondents and a Letter of Acceptance was issued by EIL on 13.09.2018. Thereafter, the petitioner entered into a contract with IOF (through EIL) on 10.10.2018. The petitioner states that the work front was handed over to the petitioner on 09.02.2019, after much delay.
3. It is the petitioner's case that since the work site was on a river front, the petitioner was required to construct a cofferdam to protect the site from inflow of water. The petitioner did so as per the design provided by EIL. However, on 12.04.2019, there was heavy rainfall resulting in breach of the cofferdam. Consequently, the entire site was inundated and the petitioner had to incur substantial expenditure for clearing the site. It is the petitioner's case that it had suggested that a dam be constructed by sheet piling method. However, EIL did not accept the same and the destruction was caused due to faulty design of the cofferdam. The petitioner claims that despite the above, EIL insisted that a cofferdam be reconstructed by the petitioner. The petitioner did so but the said cofferdam was again destroyed on 04.05.2019.
4. The petitioner claims that it had submitted it Fifth RA Bill, which was revised on 27.08.2019, for a sum of Rs.1,15,31,770/-. However, the same remains unpaid. The petitioner also claims that the delay in construction was caused due to various reasons attributable to the respondents. The petitioner also claims that despite the petitioner's request for a comprehensive insurance policy, the respondents had failed to accept its suggestion. In addition, the petitioner claims that there was substantial delay in handing over the above front. This also adversely affected the progress of the works and caused a major setback to the project. Further, the petitioner claims that the respondents had persistently delayed in making payments towards the work done and this resulted in the petitioner facing a severe liquidity crunch, which resulted in further delay in executing the works. The petitioner also claims that the pace of decision making with the respondents was extremely slow. This also made it difficult to maintain the progress of works. The petit
The court affirmed that interim relief under Section 9 of the Arbitration Act requires clear evidence of potential non-payment, which was lacking, supporting the validity of the show cause notice aga....
Interim measures, etc. by courts - Ex-parte stay and Show Cause Notice - No valid ground to interdict respondents from considering show cause notice and taking an informed decision with regard to con....
The court held that disputes can only be referred to arbitration if they arise from Notified Claims included in the Final Bill, which must first be finalized.
Disputes arising from Notified Claims in the Final Bill are required to be referred to arbitration, and the determination of Notified Claims must be made before invoking arbitration.
Interim measures under the Arbitration and Conciliation Act allow arbitration tribunals to secure claims, especially under concerns of insolvency, as long as the actions align with just and convenien....
The contract between the parties was terminable and not specifically enforceable under the Specific Relief Act, 1963.
Statutory limitation under Section 34 of the Arbitration Act is strict and cannot be relaxed without sufficient justification; defective petitions lead to being treated as non-est.
Claims can still be made post-final bill if made under coercion; the final arbiter's decisions should not contravene public policy.
A petitioner requesting interim relief under Section 9 must establish a strong prima facie case and demonstrate that the respondent is likely to frustrate the enforcement of a future decree.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.