IN THE HIGH COURT OF DELHI
Vibhu Bakhru, J.
Beigh Construction Company Private Limited - Appellant
Versus
Varaha Infra Limited - Respondent
O.M.P.(I) (COMM.) 372 of 2020 & I.A. 207 of 2021
Decided On : 07-01-2021
JUDGMENT
[Hearing held through video conferencing]
Vibhu Bakhru, J. (Oral)--The petitioner has filed the present petition under Section 9 of the Arbitration and Conciliation Act, 1996 (hereafter the Act), inter alia, praying as under:
"a) Restrain the Respondent from taking any coercive steps against the Petitioner, including terminating the Memorandum of Understanding dated 09.01.2019, till the final adjudication of the disputes by the Arbitral Tribunal.
b) Restrain the Respondent from appropriating monies from the Project in any manner other than in the manner prescribed in Memorandum of Understanding dated 09.01.2019, till the final adjudication of the disputes by the Arbitral Tribunal.
c) Restrain the Respondent from taking any coercive steps against the Petitioner which would adversely affect the Petitioner in undertaking its obligations and enjoying its rights under the Memorandum of Understanding dated 09.01.2019, till the final adjudication of the disputes by the Arbitral Tribunal.
d) grant ad-interim ex-parte reliefs in terms of Prayers (a) to (c) above"
2. The respondent was awarded the contract for executing an Engineering, Procurement and Construction Contract for "Rehabilitation & Up-gradation to 2 Lane with Paved shoulder/4 laning configuration of Wakan Pali Khopoli Road NH-548A(SH93) connecting New NH (SH88), MPEW, AH47 (NH4) and NH66 (NH17) from KM.0/000 to 40/600 in the state of Maharashtra on Engineering, Procurement & Construction (EPC) mode" by the Maharashtra State Road Development Corporation (MSRDC). And, the said parties (respondent no.1 and MSRDC) entered into the "Engineering, Procurment and Construction Agreement" (hereafter `the EPC Contract') on 07.04.2017.
3. The present petition arises out of disputes that have arisen between the parties in connection with a Memorandum of Understanding dated 09.01.2019 (hereafter `the Agreement'), whereby the respondent had agreed to sub-contract the execution of the EPC Contract to the petitioner.
4. In terms of the Agreement, it was agreed that the petitioner would execute the EPC Contract and the entire amount received from the employer (MSRDC) would be deposited in an escrow account. The petitioner would be entitled to 99% of the said amounts and the respondent would be entitled to the balance 1%.
5. It is the petitioner's grievance that the terms of the Agreement are not being complied with. The petitioner claims that it has executed works for an amount of Rs.39,29,44,384.07 against which a payment of Rs.32,00,60,345.20 has been released by MSRDC after retaining a sum of Rs.1,93,52,129.72. However, the petitioner has not received 99% of the said amounts disbursed by MSRDC. The petitioner alleges that the respondent has illegally and in breach of its obligations retained substantial portion of the same.
6. Mr Kathpalia, learned senior counsel appearing for the petitioner submitted that MSRDC is now in the process of releasing the retention money in proportion to the work completed in terms of a policy circular (Atmanirbhar Bharat: Relief for Contractors/Developers of Road Section no. Ro/MUM/GEN-Corrs/2020- 21/210 dated 08.06.2020) issued by the Ministry of Road Transport and Highways, Government of India. He submits that since the said amounts are directly relatable to the works executed by the petitioner, directions ought to be issued to the respondent to ensure that it does not receive the said sums and makes over the said sums directly to the petitioner. He earnestly contends that the amounts received or to be received by the respondent from MSRDC are in the nature of amounts received in trust and therefore, cannot be appropriated by the respondent.
7. Mr Rajeev Sharma, learned counsel appearing for the respondent has countered the aforesaid submission. He points out that the Agreement dated 09.01.2019 was terminated on 04.10.2020 and this was also communicated to MSRDC on 06.10.2020. He referred to a letter dated 19.10.2020 sent by MSRDC
A petitioner requesting interim relief under Section 9 must establish a strong prima facie case and demonstrate that the respondent is likely to frustrate the enforcement of a future decree.
The main legal point established in the judgment is the requirement to establish a strong prima facie case and the defendant's actions to defeat the realization of a potential decree when seeking int....
Interim measures under the Arbitration and Conciliation Act allow arbitration tribunals to secure claims, especially under concerns of insolvency, as long as the actions align with just and convenien....
A court cannot grant permanent relief under Section 9 of the Arbitration and Conciliation Act, as its provisions are limited to interim measures to support arbitration, not for final outcomes.
The relief sought under Section 9 of the Arbitration Act is interim in nature and cannot be a permanent measure.
The court affirmed that interim relief under Section 9 of the Arbitration Act requires clear evidence of potential non-payment, which was lacking, supporting the validity of the show cause notice aga....
Arbitration - Constitution of the tribunal – Interim relief - court under Order 39 Rule 1 of the Code of Civil Procedure has the power to pass an order of injunction in respect of the property in dis....
An arbitration agreement remains valid and enforceable despite procedural limitations on arbitrator appointment, ensuring disputes are addressed effectively.
Interim measures, etc. by courts - Ex-parte stay and Show Cause Notice - No valid ground to interdict respondents from considering show cause notice and taking an informed decision with regard to con....
The main legal point established in the judgment is that the decision of the Arbitral Tribunal must be based on evidence and material on record, and the Court will not interfere with the award unless....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.