SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img



IN THE HIGH COURT OF DELHI
Vibhu Bakhru, J.
Beigh Construction Company Private Limited - Appellant
Versus
Varaha Infra Limited - Respondent
O.M.P.(I) (COMM.) 372 of 2020 & I.A. 207 of 2021
Decided On : 07-01-2021




A petitioner requesting interim relief under Section 9 must establish a strong prima facie case and demonstrate that the respondent is likely to frustrate the enforcement of a future decree.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 9 - Petition for interim relief - The petitioner sought to restrain the respondent from taking coercive steps and sought payments related to a Memorandum of Understanding till arbitration - Petitioner claimed breaches by the respondent on the Agreement terms. (Paras 1, 5, 20)

(B) Interim Relief - Court’s power to grant interim measures under Section 9 - The court may not grant relief unless a strong prima facie case is established and there is evidence that the defendant is likely to frustrate any decree passed in favor of the plaintiff. (Paras 15, 17, 19)

Facts of the case:
The petitioner entered into a sub-contract with the respondent for executing an EPC contract, alleging non-compliance with payment terms, thus seeking restraining orders. (Paras 2, 4)

Findings of Court:
The petition was dismissed as there was no evidence the respondent intended to frustrate the agreement or that the claims were sufficiently substantiated. (Paras 19, 20)

Issues: Whether the respondent was acting in a manner to defeat the petitioner’s claims and the legal standing of interim relief after contract termination. (Paras 18, 20)

Ratio Decidendi: The court emphasized the need for a prima facie case in granting interim measures and noted that the Agreement was terminated, rendering restraining orders irrelevant. (Paras 18, 20)

Result: Petition dismissed.

JUDGMENT

[Hearing held through video conferencing]

Vibhu Bakhru, J. (Oral)--The petitioner has filed the present petition under Section 9 of the Arbitration and Conciliation Act, 1996 (hereafter the Act), inter alia, praying as under:

    "a) Restrain the Respondent from taking any coercive steps against the Petitioner, including terminating the Memorandum of Understanding dated 09.01.2019, till the final adjudication of the disputes by the Arbitral Tribunal.

    b) Restrain the Respondent from appropriating monies from the Project in any manner other than in the manner prescribed in Memorandum of Understanding dated 09.01.2019, till the final adjudication of the disputes by the Arbitral Tribunal.

    c) Restrain the Respondent from taking any coercive steps against the Petitioner which would adversely affect the Petitioner in undertaking its obligations and enjoying its rights under the Memorandum of Understanding dated 09.01.2019, till the final adjudication of the disputes by the Arbitral Tribunal.

    d) grant ad-interim ex-parte reliefs in terms of Prayers (a) to (c) above"

2. The respondent was awarded the contract for executing an Engineering, Procurement and Construction Contract for "Rehabilitation & Up-gradation to 2 Lane with Paved shoulder/4 laning configuration of Wakan Pali Khopoli Road NH-548A(SH93) connecting New NH (SH88), MPEW, AH47 (NH4) and NH66 (NH17) from KM.0/000 to 40/600 in the state of Maharashtra on Engineering, Procurement & Construction (EPC) mode" by the Maharashtra State Road Development Corporation (MSRDC). And, the said parties (respondent no.1 and MSRDC) entered into the "Engineering, Procurment and Construction Agreement" (hereafter `the EPC Contract') on 07.04.2017.

3. The present petition arises out of disputes that have arisen between the parties in connection with a Memorandum of Understanding dated 09.01.2019 (hereafter `the Agreement'), whereby the respondent had agreed to sub-contract the execution of the EPC Contract to the petitioner.

4. In terms of the Agreement, it was agreed that the petitioner would execute the EPC Contract and the entire amount received from the employer (MSRDC) would be deposited in an escrow account. The petitioner would be entitled to 99% of the said amounts and the respondent would be entitled to the balance 1%.

5. It is the petitioner's grievance that the terms of the Agreement are not being complied with. The petitioner claims that it has executed works for an amount of Rs.39,29,44,384.07 against which a payment of Rs.32,00,60,345.20 has been released by MSRDC after retaining a sum of Rs.1,93,52,129.72. However, the petitioner has not received 99% of the said amounts disbursed by MSRDC. The petitioner alleges that the respondent has illegally and in breach of its obligations retained substantial portion of the same.

6. Mr Kathpalia, learned senior counsel appearing for the petitioner submitted that MSRDC is now in the process of releasing the retention money in proportion to the work completed in terms of a policy circular (Atmanirbhar Bharat: Relief for Contractors/Developers of Road Section no. Ro/MUM/GEN-Corrs/2020- 21/210 dated 08.06.2020) issued by the Ministry of Road Transport and Highways, Government of India. He submits that since the said amounts are directly relatable to the works executed by the petitioner, directions ought to be issued to the respondent to ensure that it does not receive the said sums and makes over the said sums directly to the petitioner. He earnestly contends that the amounts received or to be received by the respondent from MSRDC are in the nature of amounts received in trust and therefore, cannot be appropriated by the respondent.

7. Mr Rajeev Sharma, learned counsel appearing for the respondent has countered the aforesaid submission. He points out that the Agreement dated 09.01.2019 was terminated on 04.10.2020 and this was also communicated to MSRDC on 06.10.2020. He referred to a letter dated 19.10.2020 sent by MSRDC

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top