SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img



IN THE HIGH COURT OF DELHI
Vibhu Bakhru, J.
Steel Authority of India Limited - Appellant
Versus
Jaldhi Overseas Pte Ltd. - Respondent
O.M.P. (COMM.) 168 of 2021 & IA Nos. 6068 of 2021 & 6070 of 2021
Decided On : 28-05-2021




The court upheld that separate contracts cannot justify claims for set-off, affirming that the awarded interest is not contrary to Indian law principles.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - International commercial arbitration - Appellant filed petition against arbitral award regarding payments under Charter Party - Tribunal found no right of set-off for the Respondent regarding pending claims from another contract - Award of USD 515,739.88 plus 12% interest upheld; it was unsubstantiated that SAIL was entitled to a set-off or withheld payments based on a non-existent connection between contracts - The award cannot be challenged as per public policy. (Paras 18, 21, 30, 32)

(B) Grounds of challenge to arbitral awards - Limited scope of interference; courts cannot revisit merits unless patent illegality evident. (Para 21)

Facts of the case:
The Appellant (Steel Authority of India Limited) contested an arbitration award concerning payments due to the Respondent (Jaldhi Overseas Pte Ltd.) under a Charter Party, alleging a right to set-off based on an unrelated contract claim. The Tribunal found no basis for such set-off.

Findings of Court:
The Tribunal awarded the full amount claimed with applicable interest, affirming the independence of the contracts and the lack of justification for withholding payment.

Issues: The core issue was whether SAIL was entitled to set off amounts due against claims arising from a separate contract.

Ratio Decidendi: The court confirmed that the contracts were independent and SAIL could not claim set-off since there was no connected claim. The fundamental policy of Indian law does not preclude the award of compound interest.

Result: Petition dismissed.

Table of Content
1. background of arbitration and charter party details. (Para 1 , 2 , 3 , 4 , 5 , 6)
2. dispute over payment under charter party. (Para 7 , 8 , 9 , 10)
3. tribunal's determination in favor of claimant. (Para 11 , 12)
4. arguments against the arbitral award by sail. (Para 13 , 14 , 15 , 16)
5. court's view on entitlement for equitable set-off. (Para 17 , 18 , 19)
6. court's analysis on evidence and interest claims. (Para 20 , 21 , 22 , 23 , 24 , 25 , 26)
7. court's interpretation of interest claims and public policy. (Para 27 , 28 , 29 , 30 , 31)
8. final ruling on dismissal and costs. (Para 36 , 37 , 38)

JUDGMENT

Vibhu Bakhru, J. Steel Authority of India Limited (hereinafter `SAIL`) has filed the present petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter the `A&C Act`) impugning an Arbitral Award dated 02.11.2020 (hereafter `the impugned award`) delivered by the Arbitral Tribunal comprising of three Arbitrators [Justice (Retd.) V.K. Gupta, former Chief Justice of Uttarakhand High Court, Sh. R.P. Singh, Director (HR & Legal), IIFCO and Justice (Retd.) Madan B. Lokur, former Judge of the Supreme Court of India as the Presiding Arbitrator].

2. The respondent (hereafter `JOPL`) is a company incorporated in Singapore and was the claimant before Arbitral Tribunal. SAIL is a Public Sector Enterprise, inter alia, engaged in manufacture of steel. The arbitration between the parties was an international commercial arbitration within the meaning of Section 2 (1)(f) of the A&C Act. It was conducted under the aegis of Delhi International Arbitration Centre and in accordance with its Rules.

3. JOPL is engaged in the business of maritime logistics including vessel operations and chartering. The parties (SAIL and JOPL) had executed a Charter Party on 21.02.2018 (hereafter `the Charter Party`) whereby JOPL agreed to load, carry and discharge cargo of 75,000 metric tons (5% more or less at the owners` option) of Bulk Coking Coal to ports in India. In terms of the Charter Party, 78,798.860 metric tons of Coking Coal was shipped on board the vessel MV "Ionic Kizuna" at the load port of Norfolk, Virginia on 21.02.2018.

4. The vessel arrived at the discharge port of Vishakhapatnam on 21.05.2018 and 45,564 metric tons of the cargo was discharged at the said port. Thereafter, the vessel proceeded to the port of Haldia and discharged the balance cargo of 33,234,86 metric tons at the said port.

5. In terms of the Charter Party, SAIL also paid 90% of the agreed consideration.

6. On 05.09.2018, JOPL issued an invoice for an amount of USD 528,634.64 being the balance freight plus demurrages incurred at the load port and the discharge ports, payable by SAIL, in terms of the Charter Party.

7. On 03.10.2018, SAIL responded to the said invoice enclosing its calculations of lay time. It agreed to the demurrages in the sum of USD 278,924.49 incurred at the load port and USD 6,205.68 at the discharge ports. It accepted that a balance of USD 515,739.88 was payable to JOPL. In view of the communications exchanged between the parties, on 13.12.2018, JOPL issued a revised invoice for a sum of USD 515,739.88 as agreed by SAIL.

8. There is no dispute between the parties as to the amount payable by SAIL under the Charter Party. There is also no dispute that JOPL had duly performed its obligations under the Charter Party. However, SAIL withheld the admitted balance amount payable to JOPL for the reason that it had raised a claim of damages against JOPL in respect of another contract - Contract of Affreightment dated 28.06.2017 for shipping cargos of limestones (hereafter `the Contract of Affreightment).

9. JOPL had not provided a vessel under the Contract of Affreightment for the 20th shipment and SAIL was compelled to make alternate arrangements for the same. SAIL claimed that JOPL had breached its obligations under the Contract of Affreightment and raised the claim for damages quantified at the additional exp

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top