SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2024 Supreme(Del) 797

IN THE HIGH COURT OF DELHI AT NEW DELHI
VIBHU BAKHRU, SACHIN DATTA, JJ.
Gillanders arbuthnot and co. Limited - Appellant
Versus
Steel Authority Of India Limited & Ors. - Respondents
FAO (OS) (COMM) 13 of 2024
Decided on : 20-11-2024

Advocate Appeared:
For the Appellant :Mr Raj Shekhar Rao, Senior Advocate with Mr Gaurav Juneja, Mr Arjit Oswal, Mr Soorya B. and Mr Rajarshi Roy, Advocates.
For the Respondents:Mr Shaiwal Srivastava, Advocate.

IMPORTANT POINT
The court affirmed that claims for breach of contract are subject to statutory limitation periods, which cannot be extended by claims of continuing breaches.

Headnote:

(A) Arbitration and Conciliation Act, 1996 - Section 34 - Limitation Act, 1963 - The appellant challenged the arbitral award on grounds of limitation, asserting that the claims were not time-barred due to a continuing breach. The Arbitral Tribunal ruled the claims were barred, leading to the appeal. The court found that the cause of action arose upon termination of the contract, and the claims were indeed time-barred. (Paras 11, 14, 78, 100)

(B) Public Policy - The court clarified that the grounds of patent illegality do not apply to international commercial arbitration, and the merits of the arbitral award cannot be re-evaluated under the guise of public policy. (Paras 25, 90, 100)

Facts of the case:

The appeal arose from an arbitration dispute regarding a contract for construction work, where the appellant claimed damages after the contract was terminated due to alleged breaches by the consortium of contractors.

Findings of Court:

The court upheld the Arbitral Tribunal's decision that the claims were barred by limitation, emphasizing the importance of adhering to statutory time limits in contractual disputes.

Issues: The primary issue was whether the claims were barred by limitation, considering the nature of the breaches and the timing of the arbitration request.

Ratio Decidendi: The court ruled that the cause of action for breach of contract arose at the time of termination, and the claims were not timely filed, thus affirming the Arbitral Tribunal's decision.

Result: The appeal was allowed, and the impugned judgment was set aside.

JUDGMENT :

VIBHU BAKHRU, J.

1. M/s Gillanders Arbuthnot and Co. Limited (hereafter GACL), a company incorporated under the Company Act, 1956 has filed the present appeal under Section 37(1)(c) of the Arbitration and Conciliation Act, 1996 (hereafter the A&C Act) impugning a judgment dated 06.12.2023 (hereafter the impugned judgment) delivered by the learned Single Judge in O.M.P.(COMM) 269/2023 captioned Steel Authority of India Limited v. Beijing Sino Steel Industry and Trade Group Corporation, China and Ors., Respondent no.1 (hereafter SAIL) had preferred the said application [O.M.P.(COMM) 269/2023] under Section 34 of the A&C Act for setting aside an arbitral award dated 11.04.2023 (hereafter the impugned award) rendered by an Arbitral Tribunal (hereafter the Arbitral Tribunal) comprising of three members. The learned Single Judge allowed the said petition and has set aside the impugned award. Aggrieved by the same, GACL has filed the present appeal.

2. The arbitral proceedings were conducted under the Rules of Arbitration of the International Chamber of Commerce (hereafter the ICC Rules). The parties had agreed to the place of arbitration as New Delhi. There is no dispute that the A&C Act is applicable in this case and the challenge to the impugned award was maintainable under Section 34 of the A&C Act.

3. The disputes between the parties arise out of an agreement dated 13.10.2007 entered into between SAIL and a consortium of contractors comprising of M/s Beijing Sino Steel Industry and Trade Group Corporation (hereafter respondent no.2 – SSIT in short), M/s Tangshan Iron and Steel Design & Research Institute Company Limited, China (respondent no.3 – TISD in short) and GACL. The said consortium of contractors is collectively referred to as the Consortium. The agreement in question was for executing the work of installation of a Top Pressure Recovery Turbine (TRT) (PKG-18) under 2.5 MT New Stream Expansion at SAIL’s IISCO Steel Plant, Burnpur, India. The said agreement is hereafter referred to as the Contract.

4. Whilst, SSIT and TISD are companies existing and organized under the laws of China, GACL is an Indian company incorporated under the Companies Act, 1956. SAIL is a Government company incorporated under Section 617A of the Companies Act, 1956.

5. The Contract was for execution of work on a divisible turnkey basis for an aggregate consideration (Contract Price) of USD 6,051,350.00 and Rs.14,92,69,000/-.

6. The works under the Contract were to be completed within a period of twenty-four months from the effective date of the Contract, that is, within two years from 13.10.2007. Thus, the Contract was required to be completed on or before 12.10.2009. However, the term of the Contract was extended to 30.11.2012. Undisputedly, the execution of the works under the Contract was delayed. According to SAIL, the Contract was delayed on account of reasons attributable to the Consortium. SAIL claimed that the drawings were finalized as late as 25.08.2008 and there were unilateral changes in the design by SSIT and TISD.

7. SAIL terminated the Contract by a letter dated 29.11.2012, alleging breach of the Contract on the part of the Consortium. SAIL further informed the consortium members (SSIT, TISD and GACL) that the balance works would be completed at their risk and cost by engaging another contractor. Thereafter, on 07.10.2011, SAIL invited tenders for completion of the balance work (referred to as the Risk Purchase Contract).

8. SAIL raised a claim for damages. Additionally, it also claimed interest and costs. The parties were unable to resolve their disputes amicably. SAIL made a request for arbitration to the Secretariat of the International Chambers of Commerce (ICC) on 03.12.2018 but the same was abandoned as SAIL did not deposit the necessary costs. On 07.01.2020, SAIL initiated the arbitration proceedings by sending a fresh request to the ICC Secretariat. Thereafter, the Arbitral Tribunal was constituted in accordance with the ICC

                              Click Here to Read the rest of this document
                              1
                              2
                              3
                              4
                              5
                              6
                              7
                              8
                              9
                              10
                              11
                              SupremeToday Portrait Ad
                              supreme today icon
                              logo-black

                              An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

                              Please visit our Training & Support
                              Center or Contact Us for assistance

                              qr

                              Scan Me!

                              India’s Legal research and Law Firm App, Download now!

                              For Daily Legal Updates, Join us on :

                              whatsapp-icon Back to top