IN THE HIGH COURT OF DELHI AT NEW DELHI
VIBHU BAKHRU, SACHIN DATTA, JJ.
Gillanders arbuthnot and co. Limited - Appellant
Versus
Steel Authority Of India Limited & Ors. - Respondents
FAO (OS) (COMM) 13 of 2024
Decided on : 20-11-2024
(A) Arbitration and Conciliation Act, 1996 - Section 34 - Limitation Act, 1963 - The appellant challenged the arbitral award on grounds of limitation, asserting that the claims were not time-barred due to a continuing breach. The Arbitral Tribunal ruled the claims were barred, leading to the appeal. The court found that the cause of action arose upon termination of the contract, and the claims were indeed time-barred. (Paras 11, 14, 78, 100)
(B) Public Policy - The court clarified that the grounds of patent illegality do not apply to international commercial arbitration, and the merits of the arbitral award cannot be re-evaluated under the guise of public policy. (Paras 25, 90, 100)
Facts of the case:
The appeal arose from an arbitration dispute regarding a contract for construction work, where the appellant claimed damages after the contract was terminated due to alleged breaches by the consortium of contractors.
Findings of Court:
The court upheld the Arbitral Tribunal's decision that the claims were barred by limitation, emphasizing the importance of adhering to statutory time limits in contractual disputes.
Issues: The primary issue was whether the claims were barred by limitation, considering the nature of the breaches and the timing of the arbitration request.
Ratio Decidendi: The court ruled that the cause of action for breach of contract arose at the time of termination, and the claims were not timely filed, thus affirming the Arbitral Tribunal's decision.
Result: The appeal was allowed, and the impugned judgment was set aside.
JUDGMENT :
VIBHU BAKHRU, J.
1. M/s Gillanders Arbuthnot and Co. Limited (hereafter GACL), a company incorporated under the Company Act, 1956 has filed the present appeal under Section 37(1)(c) of the Arbitration and Conciliation Act, 1996 (hereafter the A&C Act) impugning a judgment dated 06.12.2023 (hereafter the impugned judgment) delivered by the learned Single Judge in O.M.P.(COMM) 269/2023 captioned Steel Authority of India Limited v. Beijing Sino Steel Industry and Trade Group Corporation, China and Ors., Respondent no.1 (hereafter SAIL) had preferred the said application [O.M.P.(COMM) 269/2023] under Section 34 of the A&C Act for setting aside an arbitral award dated 11.04.2023 (hereafter the impugned award) rendered by an Arbitral Tribunal (hereafter the Arbitral Tribunal) comprising of three members. The learned Single Judge allowed the said petition and has set aside the impugned award. Aggrieved by the same, GACL has filed the present appeal.
2. The arbitral proceedings were conducted under the Rules of Arbitration of the International Chamber of Commerce (hereafter the ICC Rules). The parties had agreed to the place of arbitration as New Delhi. There is no dispute that the A&C Act is applicable in this case and the challenge to the impugned award was maintainable under Section 34 of the A&C Act.
3. The disputes between the parties arise out of an agreement dated 13.10.2007 entered into between SAIL and a consortium of contractors comprising of M/s Beijing Sino Steel Industry and Trade Group Corporation (hereafter respondent no.2 – SSIT in short), M/s Tangshan Iron and Steel Design & Research Institute Company Limited, China (respondent no.3 – TISD in short) and GACL. The said consortium of contractors is collectively referred to as the Consortium. The agreement in question was for executing the work of installation of a Top Pressure Recovery Turbine (TRT) (PKG-18) under 2.5 MT New Stream Expansion at SAIL’s IISCO Steel Plant, Burnpur, India. The said agreement is hereafter referred to as the Contract.
4. Whilst, SSIT and TISD are companies existing and organized under the laws of China, GACL is an Indian company incorporated under the Companies Act, 1956. SAIL is a Government company incorporated under Section 617A of the Companies Act, 1956.
5. The Contract was for execution of work on a divisible turnkey basis for an aggregate consideration (Contract Price) of USD 6,051,350.00 and Rs.14,92,69,000/-.
6. The works under the Contract were to be completed within a period of twenty-four months from the effective date of the Contract, that is, within two years from 13.10.2007. Thus, the Contract was required to be completed on or before 12.10.2009. However, the term of the Contract was extended to 30.11.2012. Undisputedly, the execution of the works under the Contract was delayed. According to SAIL, the Contract was delayed on account of reasons attributable to the Consortium. SAIL claimed that the drawings were finalized as late as 25.08.2008 and there were unilateral changes in the design by SSIT and TISD.
7. SAIL terminated the Contract by a letter dated 29.11.2012, alleging breach of the Contract on the part of the Consortium. SAIL further informed the consortium members (SSIT, TISD and GACL) that the balance works would be completed at their risk and cost by engaging another contractor. Thereafter, on 07.10.2011, SAIL invited tenders for completion of the balance work (referred to as the Risk Purchase Contract).
8. SAIL raised a claim for damages. Additionally, it also claimed interest and costs. The parties were unable to resolve their disputes amicably. SAIL made a request for arbitration to the Secretariat of the International Chambers of Commerce (ICC) on 03.12.2018 but the same was abandoned as SAIL did not deposit the necessary costs. On 07.01.2020, SAIL initiated the arbitration proceedings by sending a fresh request to the ICC Secretariat. Thereafter, the Arbitral Tribunal was constituted in accordance with the ICC
Associate Builders v. Delhi Development Authority
Pundlik Jalam Patil (dead) by LRs v. Executive Engineer, Jalgaon Medium Project and Anr.
Renusagar Power Co. Ltd. v. General Electric Co.
Indian Oil Corporation Limited v. SPS Engineering Limited
Geo Miller & Co. Pvt. Ltd. v. Chairman, Rajasthan Vidyut Utpadan Nigam Ltd.
Hari Shankar Singhania & Ors. v. Gaur Hari Singhania & Ors.
Shri Ram Mills Ltd. v. Utility Premises (P) Ltd.
Vijay Karia & Ors. v. Prysmian Cavi E Sistemi SRL & Others
State of Punjab & Ors. v. Bhatinda District Cooperative Milk Producers Union Ltd.: (2007) 11 SCC 363
ONGC Ltd. v. Western Geco International Ltd
HRD Corporation (Marcus Oil and Chemical Division) v. GAIL (India) Limited
Ssangyong Engineering and Construction Co. Ltd. v. National Highways Authority of India
Gemini Bay Transcription (P) Ltd. v. Integrated Sales Service Ltd.
The court affirmed that claims for breach of contract are subject to statutory limitation periods, which cannot be extended by claims of continuing breaches.
The court can set aside an arbitral award under Section 34 if it violates substantive law, contract terms, or public policy, especially when procedural requirements aren't met or if the award is pate....
The limited scope of intervention by Courts in arbitral awards under Section 34 of the Arbitration and Conciliation Act, emphasizing the need to satisfy specific grounds for setting aside an arbitral....
Claim of damages against JOPL in respect of another contract - There was no requirement for JOPL to lead any evidence. Its claim was founded on an admission on part of SAIL that sums as claimed were ....
The judgment emphasizes the limited scope of interference with arbitral awards and the principle that courts should not interfere with arbitral awards unless there is a patent illegality or violation....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.