IN THE HIGH COURT OF DELHI AT NEW DELHI
Vibhu Bakhru, J.
Steel Authority Of India Ltd - Appellant
Versus
Larsen & Toubro Ltd - Respondent
O.M.P. (Comm) No. 506 of 2020; I.A. No. 9395 of 2020
Decided On : 17-08-2021
Arbitration - Contract Agreement - Arbitration and Conciliation Act, 1996 - Interest Act, 1978 - Building and Other Conditions of Contract Act, 1996 - CENVAT and VAT - Price Adjustment - [Steel Authority of India Limited] - [Contract Agreement Dispute] - [Arbitration and Conciliation Act, 1996, Section 34; Interest Act, 1978; Building and Other Conditions of Contract Act, 1996] - The court addressed the controversy arising from disputes between Steel Authority of India Limited (SAIL) and L&T in relation to a Contract Agreement dated 16.03.2009. The court discussed the applicability of the Arbitration and Conciliation Act, 1996, the Interest Act, 1978, and the Building and Other Conditions of Contract Act, 1996, in reaching its decision. Key legal provisions such as the Contract Agreement, CENVAT and VAT, and price adjustment were interpreted and influenced the court's decision.
Fact of the Case:
Disputes arose between Steel Authority of India Limited (SAIL) and L&T in relation to a Contract Agreement dated 16.03.2009. The Arbitral Tribunal accepted L&T's claims in part and entered an award in its favor. SAIL filed a petition challenging the impugned award, raising three grounds of appeal.
Finding of the Court:
The court found that the Arbitral Tribunal did not commit a patent error in denying SAIL's claim for shortfall in credit on account of CENVAT and VAT. The court also held that SAIL was not entitled to withhold any amount on account of any liability under the Building and Other Conditions of Contract Act, 1996. Additionally, the court concluded that the impugned award was not patently erroneous in accepting L&T's claim for price adjustment (escalation). The court dismissed the petition and disposed of the pending application.
Issues: The issues involved in the case included the denial of SAIL's claim for shortfall in credit on account of CENVAT and VAT, the entitlement of SAIL to withhold amounts under the Building and Other Conditions of Contract Act, 1996, and the acceptance of L&T's claim for price adjustment.
Ratio Decidendi: The court's decision was based on the interpretation of the Contract Agreement, the applicability of CENVAT and VAT, and the terms of price adjustment under the Agreement. The court found that SAIL's claims were not supported by the legal provisions and terms of the Agreement.
Final Decision: The court dismissed the petition and disposed of the pending application, upholding the impugned award in favor of L&T.
JUDGMENT
Vibhu Bakhru, J. - Steel Authority of India Limited (hereinafter 'SAIL'), a company incorporated under the Companies Act, 1956, has filed the present petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter the 'A&C Act') impugning an arbitral award dated 01.05.2020 (hereinafter 'the impugned award') delivered by the Arbitral Tribunal comprising of three arbitrators.
2. The impugned award has been rendered in the context of disputes that have arisen between the parties in relation to a Contract Agreement dated 16.03.2009 (hereinafter 'the Agreement').
3. By the impugned award, the Arbitral Tribunal accepted the claims preferred by the respondent in part and entered an award of Rs.15,90,14,025/- in its favour. The Tribunal allowed interest at the current rate of interest in accordance of the Interest Act, 1978 on the amount due to the respondent and; post award interest at the current rate of interest (as per the Interest Act, 1978) plus 2%, with effect from ninety days after 01.05.2010, on the amount payable to the respondent.
4. Briefly stated, the relevant facts that are necessary to address the controversy are as under:- 4.1 By a notice dated 13.01.2009, SAIL invited bids from various contractors for "Additional Civil Works of Rolling Mills, BOF, CCP Complex including Lime and Dolomite Plant (Package No.: 48 C-1)" under 2.5 MT New Stream Expansion at IISCO Steel Plant (hereinafter 'the Project').
4.2 The respondent (hereinafter 'L&T') submitted its bid of Rs.245,33,43.297/- on 02.02.2009. Thereafter, SAIL issued a Letter of Acceptance (LoA) dated 27.02.2009 to L&T, accepting a total price Rs.189,52,29,602 for the execution of the Project on Item Rate basis. In terms of Clause 8.2.1 of the General Conditions of the Contract (GCC), L&T was required to submit a security deposit equivalent to 5% of the total contract value.
4.3 On 16.03.2009, pursuant to the issuance of the LoA, SAIL and L&T entered into the Contract Agreement (the Agreement) for execution of the works at a contract price of Rs.189,52,29,602. In terms of Article 5 of the Agreement, the time of completion of the Project was stipulated as twelve months from the date of the contract. Subsequently, two change orders were issued on 29.09.2009 and 02.07.2010 for extra items amounting to Rs.26,48,90,255/- and Rs.56,43,69,208.31/- respectively and the contract price was adjusted accordingly.
4.4 In terms of Article 6 of the Agreement, Mecon Ltd. (hereinafter 'Mecon') was appointed as the Consultant to undertake the functions delegated by SAIL.
4.5 On 30.09.2011, L&T completed the work awarded to it by SAIL and, on 04.01.2013, SAIL issued the Preliminary Acceptance Certificate (PAC) effective from 30.09.2011.
4.6 Thereafter, on 21.09.2015, SAIL issued the Final Acceptance Certificate (FAC) with effect from 21.06.2014.
4.7 SAIL withheld certain payments due to L&T on various grounds. Disputes arose between the parties, inter alia, with respect to processing the invoices and release of payments and processing of payments for price adjustment. L&T issued a notice dated 11.07.2016 claiming a sum of Rs.29.20 crores and inviting SAIL for resolution of the said claims through conciliation.
4.8 The conciliation proceedings were not successful and Mr. S.S. Agarwal, Conciliator, issued a letter dated 29.03.2018 confirming that the conciliation had failed.
4.9 Thereafter, on 06.05.2019, L&T invoked the Arbitration Clause, as contained in the Agreement. The Arbitral Tribunal comprising of Mr. Rajeev Kher, as the Presiding Arbitrator, Justice (Retd.) D.R. Deshmukh and Dr. Vishwapati Trivedi was constituted to adjudicate the disputes between the parties.
5. The claims made by L&T in its Statement of Claims are summarized as under:-
| Claim No. 1 | Towards outstanding/withheld payments on account of PAC- ?10.28 crores. |
| Claim No. 2 | Towards ou |
The main legal point established in the judgment is the interpretation and application of the Contract Agreement, CENVAT and VAT provisions, and the terms of price adjustment under the Agreement.
The interpretation of the contract as given by the Arbitral Tribunal is to be accepted if plausible, and the court should be slow in interfering with concurrent findings unless there is apparent perv....
Arbitration rulings require justifiable reasons for contract termination, affirming that unilateral actions without attributed fault violate contractual obligations.
The court upheld that separate contracts cannot justify claims for set-off, affirming that the awarded interest is not contrary to Indian law principles.
Claim of damages against JOPL in respect of another contract - There was no requirement for JOPL to lead any evidence. Its claim was founded on an admission on part of SAIL that sums as claimed were ....
The court affirmed that claims for breach of contract are subject to statutory limitation periods, which cannot be extended by claims of continuing breaches.
The main legal point established in the judgment is that the decision of the arbitral Tribunal is entitled to substantial discretion in awarding interest, and the court does not sit as the first appe....
The main legal point established in the judgment is that the decision of the Arbitral Tribunal must be based on evidence and material on record, and the Court will not interfere with the award unless....
The Arbitral Tribunal's decision to award refunds related to price reductions and bank charges was upheld, demonstrating the limited grounds for court interference under the Arbitration and Conciliat....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.