SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img



IN THE HIGH COURT OF DELHI
C. Hari Shankar, J.
World Window Infrastructure Pvt. Ltd. - Appellant
Versus
Central Warehousing Corporation - Respondent
Arb. A. (COMM.) 16 of 2020
Decided On : 24-11-2021




The appeal confirmed that unless fraud or special circumstances exist, arbitrary orders regarding payments or force majeure claims will not suspend contractual obligations, particularly when prior payments and actions indicate acceptance of terms.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 37(2)(b) - Appeal against orders by arbitrator concerning payment obligations and force majeure - Appellant sought injunction against invocation of bank guarantees citing force majeure due to COVID-19 pandemic - Arbitrator found operations at facility were not disrupted, thus refused relief - No basis for injunctive relief unless fraud or irreparable injustice shown. (Paras 21.2 and 67)

(B) Contracts - Interpretation - Arbitral proceedings uphold obligation to pay fixed and variable fees with annual escalation - Continued acceptance of terms and payments till February 2020 implied recognition of obligations - Dispute over terms of interpretation left for final determination, but interim measures denied as unfounded on disruptive circumstances. (Paras 17, 27.3, and 51)

Facts of the case:
The appellant, a logistics company, contracted with Central Warehousing Corporation for operational management involving fixed and variable fee structures. Payment disputes arose concerning escalations, particularly during the COVID-19 pandemic when the appellant sought exemption citing contractual force majeure. Previous payments with escalation had been consistently made until disputes led to a cessation in payments. (Paras 9-10, 19, and 33)

Findings of Court:
The court upheld the arbitrator's rulings that the appellant failed to prove funds' invocation justified under the force majeure principle, confirming that regular business operations continued. The bank guarantees were validly encashed due to the appellant's payment defaults. (Paras 31 and 66)

Issues: The primary issues included whether the pandemic situation warranted force majeure application to expunge appellant liabilities, the appropriate interpretation of contract clauses pertaining to raised fees, and the legitimacy of invoking bank guarantees secured by escrow. (Paras 21.1, 31, and 38)

Ratio Decidendi: The court reinforced the non-interference principle with arbitrator orders unless evident fraud was present, additionally emphasizing that continuity in payments undermined claims of duress or coercive agreements. (Paras 33, 42, and 46)

Result: Appeal dismissed.

Table of Content
1. details of rfp and contractual obligations (Para 3 , 4 , 5 , 6 , 7)
2. payment history and escalation clause impact (Para 8 , 9 , 10 , 11 , 12 , 13)
3. invocation of force majeure and contractual performance (Para 17 , 18 , 19 , 20)
4. court's assessment of injustice and fraud in bank guarantee invocation (Para 21)
5. judgment reasoning on contractual obligations and force majeure (Para 27 , 28 , 30 , 32 , 33)

JUDGMENT

1. This appeal, under Section 37 (2)(b) of the Arbitration and Conciliation Act, 1996 ("the 1996 Act") challenges orders dated 17th June, 2020 and 15th August, 2020, passed by the learned arbitrator on applications preferred by the appellant M/s World Window Infrastructure and Logistics Pvt. Ltd. under Section 17 of the 1996 Act.

2. The appellant had, in fact, filed three applications before the learned arbitrator under Section 17 , on 21st May, 2020, 18th June, 2020 and 26th June, 2020. The application dated 18th June, 2020 was, later, withdrawn. The orders impugned adjudicate the applications dated 21st May, 2020 and 26th June, 2020.

Facts

3. On 26th April, 2004, the respondent, Central Warehousing Corporation (CWC) issued a Request for Proposal (RFP), inviting tenders for providing Strategic Alliance Management and Operations and Commercial Services at six Inland Container Deports (ICDs)/Container Freight Stations (CFSs). Clause 4.6.5 of the RFP required the operator, to whom the tender was awarded, to submit a minimum yearly return and to commit for a minimum guarantee of business in terms of traffic (referred to, alternatively, as "Minimum Guaranteed Throughput"/"MGT"). In respect of ICD, Loni, the MGT was 18000 TEUs per annum. One TEU represented one (120 foot) container.

4. The appellant was the sole bidder. The financial bid of the appellant was opened on 5th July, 2004. There were various exhibits to the financial bid. Exhibit 10, titled "Format for Commercial Bid", read thus:

"FORMAT FOR COMMERCIAL BID

NAME OF THE CFS/ICD: LONI

AFixed Fee (lumpsum) per annum
B(I)Variable fee per TEU for loaded container entering or leaving the facility
B(II)Variable fee per TEU being transported between gateway ports and Inland CFSs/ICDs

    C. The fixed fee as well as variable fee as quoted by the bidder or as negotiated, shall be subject to a yearly escalation of 5% on compoundable basis. The first escalation will take place after one year from the date of commencement of operations."

Exhibit 11 to the Financial Bid was a "Format for Agreement". Clause 17.0 of the said Exhibit 11 set out the format for payments to be made by the "operator" to the CWC, and read thus:

    "17.0 Payment to CWC

    (i) Fixed Fee

    In return for the rights granted to the Operator (Name of the Operator) under the Strategic Alliance Management Contract, the Operator shall pay CWC a fixed fee of Rs. for CFS, per annum.

    (ii) Variable Fee

    In addition to the above, the Operator (Name of the Operator) shall pay CWC a per TEU fee for each loaded container entering and leaving the Facility @ Rs. for B (i) and Rs. for B(ii). The variable fee shall be payable to the Corporation for the actual number of containers or for the minimum guaranteed throughput (calculated on monthly basis), whichever is higher.

    (iii) Payment shall be exempt on:

  • Empty containers leaving the Facility provided they entered the facility in loaded status and per TEU variable fee has already been paid
  • Empty containers entering the facility provided the containers leave the Facility in loaded Status and pay the per TEU variable fee

    (iv) The Fixed fee and the variable fees, even for the minimum guaranteed throughput, as mentioned above shall be subject to a yearly escalation of 5% P.A. on compoundable basis effective from the date of commencement of the operations."

Thus, Clause C of Exhibit 10 as well as Clause 17.0 (iv) of Exhibit 11 to the Financial Bid, which set out the Formats for the Commercial Bids and for the Agreement to be executed between the successful operato

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top