IN THE HIGH COURT OF DELHI
Vibhu Bakhru, J.
SPML Infra Limited - Appellant
Versus
NTPC Limited - Respondent
O.M.P. (COMM) 318 of 2020 and IA No. 16126 of 2021
Decided On : 16-12-2021
| Table of Content |
|---|
| 1. nature of the parties and contract formation. (Para 1 , 2 , 3 , 4) |
| 2. details of sil's claims against ntpc. (Para 8 , 9) |
| 3. sil's arguments against the arbitral tribunal's decisions. (Para 10 , 11 , 12 , 13 , 14) |
| 4. court's analysis of claims 3 and 3a. (Para 16 , 17 , 18 , 19) |
| 5. court's analysis of claim 2 regarding excessive steel usage. (Para 21 , 22 , 23 , 24 , 25) |
| 6. assessment of sil's additional claims regarding dewatering. (Para 26 , 27 , 28 , 29 , 30 , 31 , 32 , 33 , 34 , 35 , 36) |
| 7. set aside aspects of the arbitral tribunal's decision. (Para 37) |
| 8. final disposal and liberty to seek arbitration. (Para 38 , 39) |
JUDGMENT
Vibhu Bakhru, J.
1. The petitioner (hereafter `SIL') has filed the present petition under Section 34 of the Arbitration and Conciliation Act, 1996 impugning an arbitral award dated 02.03.2014 (hereafter the `impugned award') delivered by the Arbitral Tribunal comprising of Justice (Retired) M.C. Agarwal as the Sole Arbitrator (hereafter the `Arbitral Tribunal').
2. SIL claims that it is a leading infrastructure company and has executed several projects. The respondent (hereafter `NTPC') is a Government of India enterprise and is, inter alia, engaged in the activity of generating electricity and managing the sale. NTPC had issued a Notice Inviting Tenders (NIT) on 02.05.2006 for inviting bids for the work of `Construction of the Main Plant Civil Works Package for Korba Super Thermal Power Project, Stage III (I x 500 MW)' (hereafter the `Project').
3. On 12.06.2006, SIL submitted its bid pursuant to the aforesaid NIT. The same was found to be the lowest and after negotiation, NTPC issued a Letter of Award (hereafter `LOA') dated 08.09.2006 whereby, the aforesaid contract was awarded to SIL. Thereafter, the parties entered into a contract bearing no. CS-2140-322-9-CS-COA-4740, in respect of the aforesaid Project on 28.02.2007 (hereafter `the Contract').
4. The works were to be completed within a period of thirty-seven months from the date of the LOA (that is, on or before 07.10.2009). The value of the Contract was agreed at Rs.67,59,66,972/-, which was amended to Rs.76,92,73,538.78/- (up to Amendment No.6). SIL claimed that it had mobilised its resources immediately after issuance of the LOA. However, it claims that execution of the works was delayed on account of several reasons (hindrances) attributable to NTPC. SIL claimed that it had incurred huge losses on account of failure on the part of NTPC to perform its obligations under the Contract. It claimed that some of the delays were also occasioned on account of repeated change in the methodology of execution of the works as demanded by NTPC. SIL claimed that NTPC had issued the NIT, without the necessary ground work and without being fully ready for the execution of a contract of such nature.
5. In view of the above, SIL raised certain claims, which were denied by NTPC.
6. The LOA was amended on several occasions. The last amendment, prior to reference, being the sixth amendment was made on 01.09.2010.
7. In terms of Clause 10 of the Contract, it was open for the parties to seek recourse to arbitration in terms of Clause 56 and 57 of the General Conditions of Contract (hereafter `GCC'), as applicable to the Contract. In view of the disputes between the parties, SIL invoked the Arbitration Clause (Clause 56 of the GCC) by a notice dated 11.06.2010. Pursuant to the said request, the Arbitral Tribunal was constituted and the Sole Arbitrator was appointed to adjudicate the disputes between the parties.
8. On 10.11.2010, SIL filed its Statement of Claims before the Arbitral Tribunal claiming an aggregate amount of Rs.44,52,90,985/-, in addition to interest and costs. The summary of SIL's claims is set out below:
Claim No.1. Claim on account of extra works executed at the site amounting to Rs.5,56,78,755/-.
A) Additional expenses incurred for carrying continuous dewatering with specialized techniques - Rs. 2,49,82,825.00
B) Additi
Arbitral tribunals must not reject claims on non-arbitrability if disputes are sufficiently raised, and recovery rates must reflect reasonable estimates based on contractual terms and evidence.
Arbitral Tribunal found that agreed price (item rate) for excavation also included work of “dewatering and lowering ground water table to maintain dry working condition.” It is clear from terms of Co....
Arbitral tribunals have discretion over fact-finding, and courts should not re-evaluate evidence unless decisions violate public policy or involve patent illegality.
The Arbitral Tribunal's interpretation of reimbursement based on actual costs incurred due to statutory changes is valid, despite disputes over contract terms, reinforcing the principle of contractua....
Arbitration - Application for setting aside of arbitral Award - Award of interest at rate of 18% per annum from date of award is not in consonance with observations made by Arbitral Tribunal, which r....
The Court's decision emphasizes the limited scope of interference under Section 34 and 37 of the A&C Act, and the Arbitrator's authority to award interest and costs in the absence of an agreement bet....
The entitlement to compensation for overheads incurred during the extended period of the agreement and the calculation of rates for extra items were central legal points established in the judgment.
The scope of interim relief under Section 17 of the Arbitration and Conciliation Act is strictly limited to matters directly aiding the final relief sought in arbitration.
The Arbitral Tribunal has considerable discretion in evaluating evidence and interpreting contract clauses, and its decision cannot be interfered with unless found to be patently illegal or in confli....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.