IN THE HIGH COURT OF DELHI
Vibhu Bakhru, J.
Satluj Jal Vidyut Nigam Ltd. - Appellant
Versus
Jaiprakash Hyundai Consortium - Respondent
O.M.P. (COMM.) 95 of 2020 and IA No. 11175 of 2020
Decided On : 24-12-2021
| Table of Content |
|---|
| 1. formation and specifics of the contract. (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8 , 9 , 10 , 11 , 12) |
| 2. dispute and arbitration proposals by jhc. (Para 13 , 14 , 15 , 16 , 17 , 18 , 19) |
| 3. arguments presented against the arbitral award. (Para 20 , 21 , 22 , 23 , 24) |
| 4. analysis on the validity of claims and the arbitral tribunal's findings. (Para 26 , 27 , 28 , 29 , 30 , 31 , 32 , 33 , 34 , 35) |
| 5. final determination and resolution of issues raised. (Para 36 , 37 , 38 , 39 , 40 , 41 , 42 , 43 , 44 , 45 , 46 , 47) |
JUDGMENT
Vibhu Bakhru, J.
1. The petitioner has filed the present petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereafter `the A&C Act') impugning an arbitral award dated 07.11.2007 (hereafter `the impugned award') passed by an Arbitral Tribunal comprising of Shri H.C. Bharadvaj, Shri V.K. Tyagi and Shri R.S. Prasad as the Presiding Arbitrator (hereafter `the Arbitral Tribunal').
2. The impugned award has been rendered in the context of Contract No.3 under Agreement No. 04/93 dated 24.06.1993 for execution of Civil Works of Pressure Shaft and Power House Complex of Naptha Jhakri Hydroelectric Project (hereafter `the Agreement').
Factual Context:
3. The respondent, Jaiprakash Hyundai Consortium (hereafter `JHC'), is a consortium between M/s Jaiprakash Associates Limited, a company registered under the Companies Act, 1956 and M/s Hyundai Engineering & Construction Co. Ltd, a company registered under the laws of South Korea. The consortium came into existence by an agreement dated 30.07.1992.
4. In 1992, the petitioner, (hereafter `SJVNL') invited bids for various works including civil works of pressure shafts and power house complex relating to the Naptha Jhakri Hydroelectric Project (hereafter the `Project'). JHC submitted its bid and SJVNL awarded the contract for executing the Project to JHC by a Letter of Award (hereafter `LOA') dated 26.05.1993. Thereafter, the Agreement was signed between the parties on 24.06.1993 for a total value of Rs.475.01 crores. In terms of the Agreement, the date of commencement of the Project was 01.07.1993 and JHC was expected to complete the pressure shafts within a period of fifty-seven months, and the power complex within a period of sixty-three months from the date of commencement of the Project. Resultantly, the scheduled date of completion of the pressure shafts and power complex was 31.03.1998 and 30.09.1998, respectively.
5. Admittedly, disputes arose between the parties regarding SJVNL's failure to perform its obligations under the Agreement. JHC claims that in terms of Sub-clause 4.5(i) of Chapter IV of the Additional Conditions of Contract (ACC) included as an integral part of the Agreement, SJVNL was obligated to provide JHC with AC 3 phase 50 cycle, 440/400 V construction power at various work sites, colonies and offices. However, SJVNL had failed to provide the requisite construction power at 440/400 V, as contracted; therefore, JHC had to incur additional expenses for stepping down and stepping up the power for distribution and consumption at the site.
6. In view of the dispute between the parties, a meeting was held on 09.07.1993 between SJVNL and JHC wherein, SJVNL stated that it would provide 22 KV construction power at various sites while power supply at JHC's camp would be provided on Low Tension supply (LT Supply), that is, at 440/400 V. By its letter dated 03.09.1993, JHC disputed that the same was in conformity with their contract and it claimed that the relevant clauses of the Agreement imposed an obligation on SJVNL to provide construction power at 440/400 V instead of 22 KV. Subsequently, various meetings were held between the parties between the period 09.10.1993 to 12.10.1993 wherein SJVNL reiterated its stand that the construction power would be provided to JHC at 22 KV only.
7. JHC, by its letter dated 23.12.1993, communicated to SJVNL that it required construction power at 440/400 V at five points - (i) the
The court upheld the arbitral tribunal's decision that the contract mandated construction power be supplied at 400/440 V, recognizing the claimant's entitlement to additional expenses due to unmet co....
SJVNL had contended before the Arbitral Tribunal that disputes had arisen once JHC had accepted power supply - Said contention was rejected and, in view of this Court, rightly so.
The main legal point established in the judgment is the determination of the date of commissioning of the Power Project and the liability for liquidated damages. The court interpreted the relevant pr....
The court upheld the Arbitral Tribunal's finding that a contractor is not liable for damages unless the claimant proves actual loss, emphasizing limited scope for judicial review of arbitral awards.
The scope of interim relief under Section 17 of the Arbitration and Conciliation Act is strictly limited to matters directly aiding the final relief sought in arbitration.
The main legal point established in the judgment is that the decision of the Arbitral Tribunal must be based on evidence and material on record, and the Court will not interfere with the award unless....
The scope of judicial review under Section 34 of the Arbitration Act is limited to reasons of law and pertains to the arbitral tribunal's adherence to the contract terms and evidence presented.
Without adequate notice, a unilateral change in contract terms is impermissible, especially concerning supply obligations.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.