IN THE HIGH COURT OF DELHI
Vibhu Bakhru, J.
NTPC Vidyut Vyapar Nigam Limited - Appellant
Versus
Symphony Vyapar Private Limited - Respondent
O.M.P. (COMM.) 164 of 2021 & IA No. 5828 of 2021
Decided On : 09-08-2021
| Table of Content |
|---|
| 1. dispute involves entitlement to liquidated damages. (Para 1 , 2 , 3 , 4 , 5 , 6) |
| 2. challenge to arbitral award's validity based on ppa terms. (Para 7) |
| 3. background of solar power project compliance. (Para 8 , 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16) |
| 4. commissioning timeline and relevant observations. (Para 17 , 18 , 19 , 20 , 21 , 22) |
| 5. injunction against invoking bank guarantees. (Para 23 , 24 , 25 , 26 , 27 , 28 , 29 , 30) |
| 6. counsel arguments challenging arbitral decisions. (Para 31 , 32 , 33 , 34) |
| 7. court's analysis on arbitral findings and award. (Para 35 , 36 , 37 , 38 , 39 , 40 , 41 , 42 , 43 , 44 , 45 , 46 , 47 , 48) |
JUDGMENT
Vibhu Bakhru, J. NTPC Vidyut Vyapar Nigam Limited (hereinafter "NVVNL") has filed the present petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter the "A&C Act") impugning an arbitral award dated 20.11.2020 (hereinafter "the impugned award") rendered by an Arbitral Tribunal comprising of Justice (Retired) V.N. Khare, former Chief Justice of India, Mr Ambarish Dave and Justice (Retired) D.P. Wadhwa, former Judge of the Supreme Court of India as the Presiding Arbitrator.
2. The impugned award was rendered in the context of disputes that had arisen between NVVNL and respondent no.1 (hereinafter "Symphony") in connection with a Power Purchase Agreement (hereinafter the "PPA") entered into between NVVNL and Symphony.
3. Essentially, the dispute between NVVNL and Symphony are centered around the question whether NVVNL is entitled to recover liquidated damages from Symphony in terms of clause 4.6 of the PPA. NVVNL claims that it is entitled to recover Rs.2,87,77,000/- (Rupees Two Crores, Eighty-Seven Lakhs, Seventy-Seven Thousand only) as liquidated damages being 10% of the Performance Bank Guarantee furnished by Symphony, as according to NVVNL, Symphony had failed to commission the solar power plant for generating 10 MW capacity on or before the Scheduled Commissioning Date.
4. According to NVVNL, Symphony had commissioned 5 MW capacity on or before 26.02.2013 (the Scheduled Commissioning Date) and commissioned the balance 5 MW on 27.02.2013. NVVNL claimed that it was thus, entitled to recover half of 20% of the Performance Bank Guarantee in terms of Clause 4.6 of the PPA. Symphony disputed the aforesaid claim as according to Symphony, it had commissioned the Solar Power Generating project before the Scheduled Commissioning Date. It claimed that it had completed and installed 10 MW of solar power generating capacity on 21.02.2013.
5. The Arbitral Tribunal held in favour of Symphony and accepted its contention that it had completed and installed the solar power plant with 10 MW capacity on or before the Scheduled Commissioning Date of 26.02.2013. Accordingly, the Tribunal held that NVVNL was not entitled to recover any liquidated damages. The Arbitral Tribunal further held, in any event, NVVNL could not recover damages under clause 4.6 of the PPA without establishing that it had suffered any loss.
6. Accordingly, the Arbitral Tribunal directed that the Performance Bank Guarantee furnished by Symphony be discharged. It also awarded costs of Rs.1,08,66,000/- (Rupees One Crore Eight Lacs and Sixty-Six Thousand only) in favour of Symphony.
7. It is contended on behalf of NVVNL that the impugned award is patently erroneous as it is contrary to the terms of the PPA. It is contended on behalf of NVVNL that the impugned award disregards the Minutes of the Meeting of Commissioning Committee of 25.02.2013/26.02.2013 - which recorded that Symphony had electrically connected only 7.04 MW capacity as on 25.02.2013 - and therefore, the impugned award is patently illegal and is liable to be set aside.
Factual Background
8. The Government of India launched the Jawaharlal Nehru National Solar Mission (hereinafter "JNNSM") with the objective to establish India as a global leader in solar energy. The Government of India through the Ministry of New and Renewable En
Point of Law : Arbitration - Application for setting aside of Arbitral Award - Courts would not interfere “unless Court comes to a conclusion that perversity of award goes to root of matter without t....
The main legal point established in the judgment is the determination of the date of commissioning of the Power Project and the liability for liquidated damages. The court interpreted the relevant pr....
Arbitral tribunals have discretion over fact-finding, and courts should not re-evaluate evidence unless decisions violate public policy or involve patent illegality.
The court clarified that in public utility projects, liquidated damages may be claimed without proof of actual loss, reinforcing the importance of agreed contractual terms.
The court affirmed that deductions for non-performance are valid when based on contract conditions and substantiated by timely verification reports, emphasizing the importance of evidentiary reasonin....
The court upheld the arbitral tribunal's decision that the contract mandated construction power be supplied at 400/440 V, recognizing the claimant's entitlement to additional expenses due to unmet co....
The arbitral tribunal's decision to deny claims for damages due to lack of supporting evidence is valid under Section 34 of the Arbitration and Conciliation Act, emphasizing minimal judicial interfer....
SJVNL had contended before the Arbitral Tribunal that disputes had arisen once JHC had accepted power supply - Said contention was rejected and, in view of this Court, rightly so.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.