IN THE HIGH COURT OF DELHI AT NEW DELHI
VIBHU BAKHRU, J.
National Highways Authority Of India – Appellant
Versus
M/s UEM – Essar Joint Venture - Respondent
O.M.P. (Comm) 18 of 2021, & I.A. Nos. 655, 659 of 2021
Decided on : 22-03-2022
Arbitration and Conciliation Act, 1996 - Section 34 and 34(2A) - Execution of the work relating to “Western Transport Corridor - Contract for executing Project works - Defect Liability Certificate - Respondent’s claim for payment works executed by it and certified by Engineer appointed by NHAI - Majority of Arbitrators allowed aforesaid claim, in favour of respondent - Ground that it is vitiated by patent illegality on face of award - Claims raised by respondent were barred by limitation - Principal claim for payment of work done nor claim for interest on said amount, could be entertained - Respondent had submitted its bid and contract for executing Project works for a consideration was awarded to respondent in terms of Letter of Acceptance - Execution of the works was to commence on and completed within a period of thirty months.
Finding of the Court :
Jurisdiction of Arbitral Tribunal and this Court finds no infirmity with manner in which said communications have been interpreted - letters respondent invoked the Disputes Resolution Mechanism and by a letter - Disputes to DAB was in conformity with Disputes Resolution Mechanism, as agreed between the parties in terms of Clause 67 of COPA - Respondent’s claim for amount certified NHAI issued a ‘Notice of Dissatisfaction’ and expressed its intention to refer disputes to arbitration in terms of Clause 67.4 of COPA - Respondent invoked Arbitration Clause. In the given facts, decision of Arbitral Tribunal holding that respondent’s claim was not barred by limitation cannot, by any stretch, be stated to be patently illegal or one that vitiates impugned award under Section 34(2A) of A&C Act.
Result: Petition is dismissed
JUDGMENT :
VIBHU BAKHRU, J
1. The National Highway Authority of India (hereinafter ‘NHAI’) has filed the present petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter ‘the A&C Act’) impugning an arbitral award dated 01.09.2020 (hereinafter ‘the impugned award’) passed by an Arbitral Tribunal comprising of three members [Justice (Retd.) Iqbal Ahmed Ansari, Shri A.B. Desai, Chief Engineer and Justice (Retd.) C.K. Thakkar as the Presiding Arbitrator].
2. The impugned award was rendered in the context of disputes that had arisen between the parties in connection with the Agreement dated 16.01.2002. The principal dispute between the parties was regarding the respondent’s claim for payment of a sum of Rs.4,95,02,980/- for the works executed by it and certified by the Engineer appointed by NHAI. The majority of the Arbitrators [Shri A.B. Desai and Justice (Retd.) C.K. Thakkar] allowed the aforesaid claim, in favour of the respondent. The said learned Arbitrators also awarded interest in favour of the petitioner; however, there is a difference of opinion as to the date from which the said interest would run. Justice (Retd.) Iqbal Ahmed Ansari entered a dissenting opinion.
3. NHAI has assailed the impugned award (by majority) on the ground that it is vitiated by patent illegality on the face of the award. According to NHAI, the claims raised by the respondent were barred by limitation. Thus, neither the principal claim for payment of the work done nor the claim for interest on the said amount, could be entertained.
4. Briefly stated, the facts necessary to address the aforesaid controversy, are as under:-
4.1 On 18.09.2001, NHAI had invited tenders for execution of the work relating to “Western Transport Corridor, Tumkur- Haveri Section of NH4 - Rehabilitation and upgrading of Sira-Chitrdurga Section (Km. 122.3 to Km. 189) in the State of Karnataka – Package 2” (hereinafter ‘the Project’), on the terms and conditions stipulated thereon.
4.2 The respondent had submitted its bid and the contract for executing the Project works for a consideration of Rs.253,24,41,361/- was awarded to the respondent in terms of the Letter of Acceptance dated 28.11.2001 (hereinafter the ‘LoA’). Thereafter, on 16.01.2002, the parties entered into a formal agreement (hereinafter ‘the Contract’).
4.3 In terms of the Contract, the execution of the works was to commence on or before 01.03.2002 and completed within a period of thirty months from the commencement date. Thus, the entire works were required to be completed on or before 31.08.2004. The execution of the works was delayed and the respondent sought Extension of Time (hereinafter ‘EOT’) for completion of the works on successive occasions, which were approved by NHAI.
4.4 There is some controversy regarding the approvals of the EOT. According to NHAI, it had agreed to EOT on four occasions (that is, till the 4th EOT) but had not approved the subsequent three requests for EOT (that are, requests for the 5th, 6th and 7th EOT).
4.5 NHAI claims that the said works could not be completed within the stipulated period of time due to delay on the part of the respondent; the said works were completed by 26.03.2008. Thereafter, the Engineer (appointed by NHAI) issued the Taking Over Certificate (hereinafter ‘TOC’). And, on 11.01.2011, the Engineer issued the Defect Liability Certificate (hereinafter ‘DLC’) with effect from 31.01.2010.
4.6 Pursuant to the issuance of the DLC, on 22.04.2011, the respondent submitted a Draft Final Statement, in accordance with Clause 60.11 of the Conditions of Particular Application (hereinafter the ‘COPA’). The Engineer certified an aggregate payment of Rs.4,95,02,980/- for the work done against certain items but rejected the Draft Final Statement in regard to the other payments. The respondent submitted further information to the Engineer in support of its cl
Execution of the works was delayed and the respondent sought Extension of Time for completion of the works on successive occasions, which were approved by NHAI.
The inapplicability of the ground of patent illegality to international commercial arbitration and the importance of interpreting specific contractual clauses in determining the validity of claims an....
An expulsion under a contract must have legitimate causes, and unjustified actions by one party render such expulsion illegal, reaffirming constraints under arbitration frameworks.
The main legal point established in the judgment is the interpretation and application of Section 34 of the arbitration and Conciliation act, 1996 to an international commercial arbitration, and the ....
The arbitral Tribunal found NHaI's actions to expel the respondent from the site was unjustified and illegal based on various grounds, including the delay in granting Extension of Time (EOT) and the ....
The main legal point established in the judgment is that the decision of the Arbitral Tribunal must be based on evidence and material on record, and the Court will not interfere with the award unless....
Statutory limitation under Section 34 of the Arbitration Act is strict and cannot be relaxed without sufficient justification; defective petitions lead to being treated as non-est.
The Arbitral Tribunal's decision falls within its jurisdiction and does not amount to patent illegality, as it was based on a plausible interpretation of the exclusionary clause in the contracts and ....
Failure to raise claims for escalation in a timely manner and acceptance of payments in full and final settlement preclude further claims.
The Arbitral Tribunal has considerable discretion in evaluating evidence and interpreting contract clauses, and its decision cannot be interfered with unless found to be patently illegal or in confli....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.