IN THE HIGH COURT OF DELHI AT NEW DELHI
JYOTI SINGH, J.
Kotak Mahindra Bank Limited - Petitioner
Versus
Union Of India & Ors. - Respondesnts
CS(COMM) 497 of 2019
Decided on : 24-07-2025
| Table of Content |
|---|
| 1. seeking discharge from bank guarantees (Para 1 , 2 , 3) |
| 2. unilateral alteration of payment methodology (Para 18 , 19 , 20 , 21) |
| 3. discharge of surety under sections 133 and 139 of the contract act (Para 22 , 23 , 24) |
| 4. analysis of the bank guarantees and their terms (Para 36 , 37 , 47) |
| 5. legal principles governing unconditional bank guarantees (Para 50 , 51 , 63) |
JUDGMENT :
JYOTI SINGH, J.
1. This suit is filed on behalf of the Plaintiff seeking a decree for declaration that Plaintiff is discharged from its obligations under Bank Guarantees (‘BGs’) being: (i) Bank Guarantee No. 0691OBG16010553 dated 23.08.2016; (ii) Bank Guarantee No. 0691OBG16010800 dated 26.08.2016; (iii) Bank Guarantee No. 0691OBG16011649 dated 14.09.2016; (iv) Bank Guarantee No. 0691OBG16012653 dated 30.09.2016; and (v) Bank Guarantee No. 0691OBG16014183 dated 26.10.2016 as also declaring that invocation of the said Bank Guarantees vide notices/letters dated 05.01.2019, 15.01.2019 and 29.01.2019 is invalid, illegal and void. Plaintiff also seeks a decree in the sum of Rs.48,77,13,600/- along with interest from the date of payment against Defendant No.1.
BRIEF FACTS
2. It is averred that Plaintiff is a Banking Company registered under the Companies Act, 1956 engaged in the business of banking. Defendant No.1/Ministry of Road, Transport and Highways (‘MoRTH’) is an Organization under the Government of India entrusted with task of formulating and administering, in consultation with other Central Ministries/Departments, State Governments etc., policies for Road Transport, National Highways and Transport Research, with a view to increasing the mobility and efficiency of road transport system in the country. Defendant No.3 is a Company against which NCLT, Mumbai has admitted insolvency proceedings and appointed Resolution Professional. During the pendency of Corporate Insolvency Resolution Process (‘CIRP’), no legally compliant resolution plan was received by the Committee of Creditors till 269th day and hence by efflux of time, on 270th day, Defendant No.3 went into liquidation and NCLT thereafter appointed a Liquidator.
3. It is averred that MoRTH had entrusted the Government of Bihar the work of development, maintenance and management of NH-104 and had resolved to take up the work of rehabilitation and upgradation of 2 lanes with paved shoulders configuration and strengthening of Sitamarhi- Jaynagar-Narahai Section in the State of Bihar under Phase-I of the National Highways Inter-Connectivity Improvement Projects. By and under two separate bidding documents, both dated 01.04.2015, MoRTH invited bids for undertaking work in Lot-I and Lot-II of the Project.
4. It is stated that on 30.05.2015, Defendant No.3 and RCM Infrastructure Limited entered into two Joint Bidding Agreements for incorporation of a Joint Venture viz., SHEL-RCM JV (‘Joint Venture’) forbidding for Lot-I and Lot-II of the Project and on 02.06.2015, bids were submitted through the Joint Venture. As per Clause 6 of the Joint Bidding Agreements, it was agreed between Defendant No.3 and RCM Infrastructure Limited that their share of the work in terms of proportion of construction and equity share in the project would be 51% and 49%, respectively.
5. It is averred that on 15.10.2015, bid of consortium of Rs.154,62,00,000/- was accepted by MoRTH, being the lowest bid and two separate Letters of Acceptance were issued. On 23.11.2015, Joint Bidding Agreements were superseded by two Supplementary Agreements and it was agreed that Defendant No.3 would now have participation of 100% and RCM Infrastructure Limited would be responsible only to the extent of providing Project Management Services and Technical Consultations. It was also agreed under Clause 5 that it shall be the responsibility of Defendant No.3 to furnish any bond, Performance BG or Counter BG required by MoRTH.
6. It is averred that on 18.02.2016, two Engineering Procurement and Construction Agreements (‘EPC Agreements’) were exec
Hindustan Steelworks Construction Ltd. v. Tarapore & Co. and Another
State Bank of Saurashtra v. Chitranjan Rangnath Raja and Another
Kumari Shrilekha Vidyarthi and Others v. State of U.P. and Others
ABL International Ltd. and Another v. Export Credit Guarantee Corporation of India Ltd. and Others
Himadri Chemicals Industries Ltd. v. Coal Tar Refining Co
The main legal point established in the judgment is the binding effect of the settlement between the parties, the waiver of the right to seek re-employment by the workmen, and the entitlement of the ....
A lockout is justified if it is declared in response to an illegal strike or a strike that is in breach of a settlement or award.
The combination of eyewitness testimonies, recovery of the weapon used, and forensic examination results can establish guilt in criminal cases, even based on circumstantial evidence.
The conviction of an accused person under Section 27(3) of the Arms Act is not permissible in law if the accused is also charged with committing murder under Section 302 of the Indian Penal Code.
The court can enhance compensation based on the deceased's income and family dependency, and adjust the multiplier used by the Tribunal if found unjustified.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.