SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Del) 890

2025 DHC 302
IN THE HIGH COURT OF DELHI AT NEW DELHI
VIBHU BAKHRU, ACJ, TARA VITASTA GANJU, J.
Next Generation Business Powers Systems Ltd. – Appellant
Versus
Telecommunication Consultants India Ltd. – Respondent
FAO (OS) (COMM) No. 61 of 2019
Decided On : 21-01-2025
Advocates Appeared : 
For the Appellants : T.S. Ahuja, Varun S. Ahuja, Ridhi Kapoor
For the Respondents : Ratan K. Singh, Nikhlesh Krishnan, Ritika Priya, Abhishek Bhushan Singh

The court affirmed that guaranteed payments in an arbitration agreement are not contingent on payments from a principal contractor, ensuring obligations are fulfilled regardless of external contractual performance.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 37(1)(c) - Appeal against the judgement of the Single Judge upholding part of the Arbitral Award - The claims contested included amounts withheld by the respondent for various quarters, including a deduction related to Annual Technical Support (ATS) for software. (Paras 3, 10, 11, 18)

(B) Interpretation of Contractual Obligations - Court emphasized that 'guaranteed revenue payment' in the agreement was unconditional and not reliant on payments from the principal contractor. (Paras 17, 27, 36)

(C) Scope of Work - Differentiated roles between contractor and sub-contractor were crucial in determining financial obligations. (Paras 20, 21)

(D) Non-performance claims - Deductions made by the respondent were ruled unjustified due to absence of contractual obligations mandating ATS. (Paras 30, 31) (E) Court findings - The Arbitrator's interpretation was aligned with contract terms, restricting the respondent's right to withhold payments based on principal non-payment. (Paras 41, 47) (F)

Result: Appeal allowed, and the Impugned Judgment was set aside.

Table of Content
1. challenge to prior judgment under arbitration law (Para 1 , 2 , 3)
2. context of agreements related to gswan contract (Para 4 , 5 , 6 , 7 , 8 , 9)
3. findings of the sole arbitrator on claims (Para 10 , 11)
4. appellant's arguments on scope of obligation (Para 12)
5. respondent's defense regarding withheld payments (Para 13)
6. rejoinder claims of the appellant (Para 14)
7. interpretation of clauses related to payments and obligations (Para 19 , 20 , 21 , 22)
8. court's interpretation against sole arbitrator's findings (Para 23 , 24 , 25)
9. ats obligations and contractual limits of the appellant (Para 30 , 31 , 32 , 33 , 34 , 35 , 36)
10. final findings on payment obligations and deductions (Para 38 , 39 , 40 , 41 , 43)

JUDGMENT :

TARA VITASTA GANJU, J.

PREFACE

1. The present Appeal has been filed by the Appellant under Section 37(1)(c) of the Arbitration and Conciliation Act, 1996 [hereinafter referred to as “A&C Act”] against the judgement dated 22.01.2019 passed by the learned Single Judge of this Court in OMP (COMM) No. 17/2017 captioned Telecommunication Consultants India Ltd. v. Next Generation Business Power Systems Ltd. [hereinafter referred to as “Impugned Judgment”]. By the Impugned Judgment, the learned Single Judge has partly upheld an award dated 23.08.2014 [hereinafter referred to as “Arbitral Award”] passed by the learned Sole Arbitrator.

2. An Appeal was also filed by the Respondent before this Court being FAO (OS) (COMM) No. 171/2019 captioned Telecommunication Consultants India Ltd. (TCIL) v. NGBPS Ltd. By an order dated 28.05.2024, the Appeal filed by the Respondent was dismissed by this Court with directions for the release of the amounts deposited by the Respondent before the Court in favour of the Appellant.

3. At the outset and as is recorded in the order dated 16.05.2019 passed by the Coordinate Bench of this Court, the challenge in the present Appeal was confined by the Appellant to only three findings:

(i) The claim for deducted/withheld amount of Rs. 60,01,890/- with interest thereon;

(ii) The claim for amounts deducted in the 31st quarter in respect of Annual Technical Support (ATS) for Rs. 14,64,203/-

(iii) The claim for an amount deducted in the sum of Rs. 35,00,000/- in respect of 32nd quarter.

4. The Government of Gujarat [hereinafter referred to as “GOG”] awarded to the Respondent a contract for Third Party Inspection of the Gujarat State Wide Area Network Project including performance level monitoring and reporting by an agreement dated 15.03.2002 [hereinafter referred to as “GSWAN Project”]. Subsequently, the Respondent entered into an agreement with the Appellant dated 18.04.2002 for providing sub-consultancy for the GSWAN Project of GOG [hereinafter referred to as “Agreement”]. The dispute between the parties arose in respect of this Agreement for sub-consultancy services to the Respondent.

5. The salient terms of the Agreement were that the Agreement would remain in operation for a period up to 14.04.2010 (almost 8 years) with a provision for extension of the Agreement. In terms of Clause 11 of Schedule IV of the Agreement, the Appellant was entitled to collect quarterly guaranteed revenue payments in the sum of Rs. 35,00,000/- for a period of 8 years or 32 quarters against invoices raised from time to time.

6. Upon termination/expiry of the Agreement on 14.04.2010, a third- party agency called M/s PCS Technology Ltd. [hereinafter referred to as “PCS”] was appointed by GOG to take over the GSWAN Project.

7. It is the case of the Appellant that the disputes arose after the 20th quarter as up to then, the Respondent was making timely payments to the Appellant. However, between 21st to 31st quarter, the Respondent illegally retained an amount of Rs. 60,01,890/- from the payments due.

8. A demand notice was served upon the Respondent on 12.07.2010 demanding an amount of Rs. 1,30,01,890/-. Subsequently, on 29.07.2010, the Respondent invoked the bank guarantee which was available as security in th

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top