SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Del) 98

IN THE HIGH COURT OF DELHI AT NEW DELHI
HARISH VAIDYANATHAN SHANKAR, J.
Vijay Jain & Ors. – Petitioners
Versus
Laxmi Foils Pvt. Ltd. – Respondent
ARB.P. 1125 of 2025 & I.A. 1796 of 2026 (Delay of 3 Days in filing the rejoinder)
Decided On : 17-02-2026

Advocates Appeared:
For the Petitioners:Mr. Jayant Mehta, Senior Advocate with Mr. Ashish Verma, Mr. Saksham Thareja, Mr. Akhil Ranganathan and Mr. Pallav Arora, Advocates.
For the Respondent:Ms. Malvika Trivedi, Senior Advocate along with Mr. Sanyam Khetarpal and Ms. Lisa Sankrit, Advocates.

Judicial scrutiny under Section 11 of the Arbitration Act is limited to the prima facie existence of an arbitration agreement, with substantive issues reserved for the arbitral tribunal.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 11(6) - Appointment of Arbitrator - Petitioners seek the appointment of a sole arbitrator due to failure of the respondent to repay a significant debt under a Facilities Agreement involving an arbitration clause. The court emphasizes the limited judicial scrutiny to the existence of an arbitration agreement. (Paras 1, 24, 26)

(B) Civil Procedure - Judicial Intervention - The court's role under Section 11 is to facilitate arbitration and not to adjudicate disputes, ensuring adherence to the original intention of the parties while limiting interference. (Paras 25-28)

Facts of the case:
This petition arose due to the respondent's failure to repay Rs. 1,41,64,903/- owed under a Facilities Agreement entered with the petitioners, who have previously engaged in unsecured loans and have pursued arbitration. Court findings: The court recognizes the existence of a prima facie arbitration agreement based on the signature of a director of the respondent company and appoints an arbitrator to resolve the disputes.

Issues: The primary question was whether a valid arbitration agreement exists despite the respondent's claims of non-payable debts and procedural issues.

Ratio Decidendi: The court concluded that it must restrict scrutiny to the existence of the arbitration agreement, allowing the arbitral tribunal to handle substantive issues, thereby upholding arbitration's integrity.

Result: Petition granted; an arbitrator is appointed.

Table of Content
1. disputes arising from facilities agreement (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8 , 9 , 10 , 11 , 12)
2. arguments regarding validity of arbitration clause (Para 13 , 14 , 15 , 16 , 17 , 18 , 19 , 20 , 21)
3. court's analytical approach to arbitration agreements (Para 22 , 23 , 24 , 25 , 26 , 27 , 28)
4. appointment of arbitrator based on prima facie existence (Para 29 , 30 , 31 , 32 , 33 , 34 , 35 , 36 , 37 , 38 , 39)

JUDGMENT :

HARISH VAIDYANATHAN SHANKAR, J.

1. The present Petition, under Section 11 (6) of theArbitration and Conciliation Act, 1996, Act, has been filed seeking the appointment of a sole Arbitrator for the purpose of adjudication of disputes stated to have arisen between the parties in relation to theFacilities Agreement dated 21.02.2022, Agreement

2. As stated in the Petition, in or around March 2022, the Respondent Company was engaged in the business of manufacturing and trading aluminium hot rolled products, aluminium cold rolled products and aluminium sheets, foils, etc. under the shareholding of the Petitioners herein. It is further stated in the Petition that the Petitioners had, from time to time, granted credit facilities/unsecured loans for the purpose of the Respondent Company's capital expenditure and general corporate expenses.

3. Thereafter, it is stated in the Petition that one OFB Tech Pvt. Ltd. vide Memorandum of Understanding dated 25.11.2021, MoU agreed to purchase 100% equity of the Respondent Company. The said MoU thereafter fructified into a Tripartite Share Purchase Agreement dated 03.02.2022, Share purchase agreement, which was entered into between the Petitioners, Respondent and one OMAT Business Pvt. Ltd., which is the fully-owned subsidiary of OFB Tech Pvt. Ltd.

4. Consequently, in order to discharge the liabilities of the Respondent Company under the credit facilities/unsecured loans granted by the Petitioners, OFB Tech Pvt. drafted and shared a Facilities Agreement vide email dated 07.02.2022.

5. It is further stated in the Petition that there were other lenders as well that had granted unsecured loans to the Respondent Company, and in view thereof, two Facilities Agreements were drafted by OFB Tech Pvt. Ltd., being “Project Laxmi-USL (Shareholders as Lenders)” and “Project Laxmi-USL (Non-shareholders as Lenders)”.

6. It is stated that the Facilities Agreement in the present case, being Project Laxmi-USL (Shareholders as Lenders), was duly executed by the Petitioners and delivered to the Respondent and to its parent company, OFB Tech Pvt. Ltd., on 21.02.2022.

7. It is stated in the Petition that the Agreement envisaged the Arbitration Clause being Clause 7.7, which reads as under:

7.7 Arbitration

7.7.1. If any dispute arises amongst the Parties in relation to or in connection with this Agreement (including in respect of the validity, interpretation, implementation or alleged breach of any provision of this Agreement) (a “Dispute”), the Parties shall attempt to resolve such Dispute amicably through discussions amongst the senior executives of the Parties.

7.7.2. Arbitration. In the case of failure by the Parties to resolve the Dispute in the manner set out in Clause 7.7.1 above within 30 (thirty) days from the date when the Dispute arise, the Dispute shall be finally settled by arbitration in accordance with the Arbitration and Conciliation Act, 1996. All arbitration proceedings shall be conducted in the English language. The seat and venue of arbitration will be Delhi.

7.7.3. Each Party shall appoint 1 (one) arbitrator each, and the 3rd (third) arbitrator shall be appointed by the 2 (two) arbitrators so appointed (the “Arbitration Tribunal”).

7.7.4. Enforcement. The arbitral award(s) rendered by the Arbitration Tribunal shall be made in writing and shall be final and binding upon the Parties and shall set out the reasons for the Arbitration Tribunal's decision.”

8. It is further stated that upon the culmination of the Facilities Agreement, a total principal amount of Rs. 1,41,64,903

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top