SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Del) 318

IN THE HIGH COURT OF DELHI AT NEW DELHI
ANIL KSHETARPAL, AMIT MAHAJAN, JJ.
 
M/S L and D JV – Appellant
Versus
Container Corporation of India Ltd. – Respondent
FAO(OS)(COMM) 10 of 2026 & CM APPL. 3484 of 2026
Decided On : 03-02-2026
 

Advocates Appeared:
For the Appellant : Mr. Sarthak Sawhney, Adv.
For the Respondent: Mr. R. K. Joshi, Mr. Ojusya Joshi and Mrs. Shabnam Joshi, Advs.

Arbitral awards are upheld where the claims are barred by pre-existing certificates and where the burden of proof lies with the claimant to substantiate additional work claims.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Sections 34 and 37 - Appeal against arbitral award - Appellant's claims dismissed due to issuance of No Claim Certificate - The burden is on the Appellant to substantiate claims of additional work, which was not met - Award upheld as no grounds for interference demonstrated. (Paras 1, 20, 21, 29)

(B) Limitation - Claims for interest on delayed payments raised much later found to be barred by limitation, as the cause of action arose when payments became due - The Arbitral Tribunal's findings affirmed regarding the timeline and claims. (Paras 22, 24)

(C) Scope of Interference - Limited scope of review under Section 37 prevents re-evaluation of factual findings unless shown to be arbitrary or illegal. (Paras 16, 26)

Facts of the case:
The Appellant sought to recover amounts for additional works and delayed payments post completion of a works contract at a Container Freight Station; disputes related to contractual obligations were sent to arbitration, which ultimately dismissed their claims based on a lack of evidence and procedural issues.

Findings of Court:
The award was consistent with contractual obligations and evidence presented, concluding that the Appellant's claims were barred by a No Claim Certificate and insufficient documentation.

Issues: Whether the Appellant could raise claims post-issuance of No Claim Certificate and the validity of claims related to delayed payments.

Ratio Decidendi: The learned Arbitral Tribunal concluded that the execution of the No Claim Certificate precluded further claims, and the Appellant failed to prove claims for additional works.

Result: Appeal dismissed.

Table of Content
1. contractual obligations and execution of works (Para 3 , 4 , 5 , 6 , 7 , 8)
2. arbitral tribunal's findings on claims (Para 9 , 10 , 11 , 12)
3. parties' contentions on the appeal (Para 13 , 14)
4. limited scope of interference in arbitration (Para 16 , 17 , 18 , 19 , 20 , 21 , 22 , 23)
5. no grounds for overturning arbitral award (Para 24 , 25 , 26)
6. dismissal of the appeal and conclusion (Para 28 , 29)

JUDGMENT :

ANIL KSHETARPAL, J.

1. The present Appeal, preferred by the Appellant, assails the correctness of judgment and order dated 05.08.2025 [hereinafter referred to as the ‘Impugned Order’] passed by the learned Single Judge in O.M.P.(COMM) 440/2024, whereby the petition filed by the Appellant under Section 34 of the Arbitration and Conciliation Act, 1996 [hereinafter referred to as the ‘1996 Act’] challenging the arbitral award dated 04.07.2024, passed by the learned Arbitral Tribunal, came to be dismissed.

2. The issue which arises for consideration in the present Appeal is whether, in exercise of appellate jurisdiction under Section 37 of the Arbitration and Conciliation Act, 1996, this Court ought to interfere with the order passed by the learned Single Judge dismissing the Appellant’s petition under Section 34 , particularly when the arbitral award rests on a finding that the Appellant is barred from raising any claim on account of the No Claim Certificate and allied declarations executed by it.

FACTUAL MATRIX:

3. In order to appreciate the controversy involved in the present Appeal, it would be apposite to briefly advert to the material facts giving rise thereto.

4. The Respondent awarded a works contract to the Appellant pursuant to a tender issued during the year 2013 for execution of earthwork and allied civil works relating to development of land at a Container Freight Station at Vallarpadam, Cochin, Kerala. The contract was an item-rate contract governed by the General Conditions of Contract and the Special Conditions of Contract, and the scope of work was defined by the Bill of Quantities [hereinafter referred to as ‘BOQ’] forming part of the tender documents. Under the contractual arrangement, the BOQ specifying items of work and approximate quantities was prepared by the Respondent, and the Appellant was required to execute the works in accordance therewith, under the supervision of the Respondent.

5. The scheduled date of commencement of work was 02.03.2014 and the stipulated date of completion was 01.01.2015. The work, however, came to be completed on 26.06.2017, whereafter completion was certified and the works were put to use by the Respondent. During the course of execution of the contract, disputes arose between the parties in relation to the execution of the works, payments made therefor, and responsibility for alleged defects and rectification.

6. The Appellant asserted that, during execution, it was required to carry out certain additional and rectification works beyond the original scope of the BOQ, allegedly on account of site conditions and directions issued by the Respondent. It was also alleged that payments of running account bills were delayed, that certain deductions were wrongfully made, and that amounts towards earnest money deposit were liable to be refunded. According to the Appellant, the additional works were executed under compulsion and without commensurate payment.

7. The Respondent, on the other hand, disputed the aforesaid assertions and contended that the works executed by the Appellant were governed by the contractual terms, that no extra or variation works were duly established in accordance with the contract, and that any rectification carried out was within the Appellant’s contractual obligations. The Respondent further denied liability towards additional payments and interest.

8. In view of the disputes, the Appellant invoked the arbitration clause contained in the contract and referred the disputes to arbitration. Before the learned Arbitral Tribunal, the Appellant

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top