SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Del) 364

IN THE HIGH COURT OF DELHI AT NEW DELHI
AVNEESH JHINGAN, J.
 
Zreyah Semiconductors Pvt. Ltd. – Petitioner
Versus
Oyo Hotels And Homes Pvt. Ltd. – Respondent
O.M.P. (COMM) 249 of 2023 & I.A. 14284 of 2025
Decided On : 02-02-2026
 

Advocates Appeared:
For the Petitioner: Mr. Ashish Dholakia, Sr. Adv. with Mr. Gautam Bajaj, Mr. Akash Panwar, Ms. Meghna Jandu, Mr. Lakshay Nagpal & Ms. Saumya, Advs.
For the Respondent: Mr. Sumant Nayak, Mr. Ankit Premchandani & Ms. Smriti Shukla, Advs.

The court upheld the arbitrator's decision, affirming that the interpretation of contractual obligations did not warrant judicial interference under Section 34 of the Arbitration Act.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - Petition filed against arbitral award directing delivery of switches and payment of Rs.2,84,00,000/- - Petitioner, engaged in manufacturing/supplying electronic components, argued it was merely an assembler - Court finds the interpretation of contract plausible with no entitlement of payment of hundred percent advance by the respondent. (Paras 3.1, 4, 11, 20)

(B) Scope of interference in arbitration - Reappraisal of evidence falls outside limited scope of judicial review under Section 34 unless conclusion is perverse - Construction of contract terms is primarily for arbitral tribunal without interference from courts unless fundamentally flawed. (Paras 19.1, 19.2)

Facts of the case:
Petitioner and respondent entered a vendor agreement after placing a purchase order for switches, dispute arose over non-delivery and payment terms, leading to arbitration where the arbitrator upheld claims for delivery and payment.

Findings of Court:
The findings of the arbitrator were upheld as plausible and without legal error, indicating that the respondent was not obligated to pay a hundred percent advance and the delays in delivery were not justifiable.

Issues: Whether the respondent was obliged to pay a hundred percent advance to the petitioner for component procurement and the nature of their contractual relationship.

Ratio Decidendi: The arbitrator's interpretation of the contract and findings on advance payments were not open to judicial scrutiny under Section 34, confirming the limited scope for interference with arbitral awards.

Result: Petition dismissed.

Table of Content
1. petitioner's case based on arbitral award. (Para 1 , 2)
2. petitioner's claim of being an assembler. (Para 3)
3. respondent's defense and interpretations. (Para 4)
4. court reviews arguments presented. (Para 5)
5. controversy on advance payment. (Para 6)
6. interpretation of vendor agreement clauses. (Para 7 , 8)
7. acceptance criteria based on contract terms. (Para 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16)
8. standard for judicial review of arbitration awards. (Para 19)
9. conclusion on petition dismissal. (Para 20 , 21)

JUDGMENT :

AVNEESH JHINGAN, J.

1. M/s Zreyah Semiconductors Private Limited has filed the petition under Section 34 of the Arbitration and Conciliation Act, 1996 (for short 'the Act') aggrieved of the arbitral award dated 03.04.2023.

FACTS

2. The brief facts are that the petitioner is engaged in the business of manufacturing and supply of electronic components. The respondent is a Private Limited Company engaged in the business of managing hospitality establishments. The respondent placed a purchase order dated 26.09.2019 upon the petitioner (hereinafter 'the PO') for supply of 52360 switches valuing Rs.10,34,89,540/-, inclusive of taxes. Subsequent to the placement of the PO, the parties entered into a vendor agreement dated 23.12.2019 (hereinafter 'the VA'). The PO though prior in time was governed by the terms and conditions of the VA. After the placement of the PO the respondent paid an advance of fifty percent of the invoice value.

2.1 Prior to the placing of the PO, the parties had business transactions wherein the petitioner was assembling switches for the respondent and the entire material was being supplied by the respondent. The scenario changed and pursuant to the PO the petitioner had to procure the components for the switches and five major components were to be procured from vendors specified by the respondent in Schedule 'A' to the VA.

2.2 A dispute arose between the parties due to non-delivery of the switches and arbitration proceedings as provided under the VA were initiated at the instance of the respondent. The arbitrator framed the following issues:

(i) Whether the respondent has committed the breach of the Vender Agreement dated 23.12.2019? If so, its effect.

(ii) Whether the respondent has committed the breach of the P.O.s dated 26.09.2019 and 22.09.2020? If so, its effect.

(iii) Whether the claimant is entitled to the reliefs as claimed in the SOC?

2.3 The arbitrator after considering the pleadings and appreciating the evidence adduced directed the petitioner to deliver 11000 switches claimed to be ready and to pay Rs.2,84,00,000/- along with interest at the rate of nine percent per annum.

CONTENTIONS

3. Learned counsel for the petitioner relies upon clauses 2.1, 2.3 and 3.1 of the VA to contend that the petitioner was an assembler and not a manufacturer, the arbitrator erred in holding that the petitioner was a manufacturer. Reliance is placed upon the correspondence between the parties to show that the terms and conditions of the Chinese vendors (hereinafter 'the vendors') were provided by the respondent to the petitioner. It is submitted that clause 12.1 of the VA relied upon by the arbitrator deals with liability of petitioner towards employees and not with the nature of relationship between the parties and it was wrongly recorded that there was a principal to principal relationship between the parties.

3.1 It is argued that the arbitrator relying on clause 14.10 concluded that all prior discussions, negotiations and agreements were superseded by the VA, if this is taken to its logical end the PO no longer existed and consequently no liability could be casted upon the petitioner.

3.2 The averment is that some of the components were to be procured from the vendors identified by the respondent and the advance amount was to be paid by the respondent for these procurements. On failure of the respondent to make hundred percent advance payment the components could not be procured and the switch

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

AI

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top