IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
Bela M. Trivedi, J.
M/s SMS Infrastructure Limited – Petitioner
Versus
Gujarat State Road Development Corporation – Respondent
R/Petn. Under Arbitration Act No. 42 of 2020
Decided On : 23-04-2021
Arbitration and Conciliation Act, 1996 - Sections 11 (6), 21 and Clause (i) of Section 2(1)(i) - Companies Act - 2(1)(k) - Arbitration Agreement - Contract - Public notice - Removing or re-executing the work - Whether such disputes arise during the progress of the work or after the completion or abandonment thereof, shall be referred to the Arbitration Tribunal, Gujarat State - whether such works contract contains an arbitration clause or not, refer, within one year from the date when the dispute has raised, such dispute in writing to the Tribunal for arbitration in such form and accompanied by such documents or other evidence and by such fees, as may be prescribed - whether in the absence of a Notification in Official Gazette, the Municipal Corporation can at all be considered as a Public Authority for the purpose of Section 2(1)(k) of Gujarat Tribunal Act, 1992 - present petition are that the respondent Gujarat State Road Development Corporation had invited the tenders by issuing a public notice for the work of widening and strengthening Road - Offer of the petitioner being the lowest one was accepted by the respondent on 29.12.2010 and an Agreement was executed between the parties. Clause30 of the terms and conditions of the contract annexed to the said agreement, pertained to referring the disputes to the Arbitration Tribunal.
Finding of the court : State Government, as contemplated in Clause (iii), would arise only when the respondent is a local authority. In the instant case, the respondent Corporation being a Company wholly owned by the Government, Clause (i) of Section 2(1)(i) would be applicable, and not Clause (iii) thereof - Work in question awarded to the petitioner by the respondent Corporation as a “public undertaking” for widening and strengthening would therefore, certainly fall within the meaning of “works contract - Construction Company (supra) and other decisions relied upon the concerned respondents were the local authorities and were not notified in the official gazette by the State Government, and therefore, it was held in the said cases that such authorities could not be said to be a public undertaking under Section 2(1)(i), and that the contracts entered into by such authorities could not be said to be the “works contract” within the meaning of Section 2(1)(k) of the said Act - Such is not the position in the instant case.
Result :Petition is dismissed
JUDGMENT :
1. The Arbitration Petition has been filed by the petitioner M/s. SMS Infrastructure Limited, a Company incorporated under the Companies Act, through its Power-of-Attorney Holder, seeking to appoint an Arbitrator to resolve the disputes between the parties as per the provisions contained under Section 11 (6) of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as “the said Act”).
2. The short facts giving rise to the present petition are that the respondent Gujarat State Road Development Corporation, Gandhinagar had invited the tenders by issuing a public notice for the work of widening and strengthening the Sarkhej Dholka – Vataman – Pipli – Dholera Bhavnagar Road. The offer of the petitioner being the lowest one was accepted by the respondent on 29.12.2010 and an Agreement No.B2/12 of 201112 was executed between the parties. Clause30 of the terms and conditions of the contract annexed to the said agreement, pertained to referring the disputes to the Arbitration Tribunal, which reads as under:
The disputes relating to this contract, so far as they relate to any of the following matters, Whether such disputes arise during the progress of the work or after the completion or abandonment thereof, shall be referred to the Arbitration Tribunal, Gujarat State.
(i) The rates of payment under clause 5 for any tools, materials and stores, in or upon the works of the site thereof or belonging to the contractor or procured by him an intended to be used for execution of the work or any part thereof possession of which may have been taken by the Engineer-in-charge under the said clause-S.
(ii) The Reduction in rates made by the Engineer-in-Charge under clause 9 from the items of works not accepted as completed fully in accordance with the sanctioned specifications.
(iii) The rate of payment for any class of work which is included in the additional or altered work carried out by the contractor in accordance with the instructions of the Engineer-in-Charge under clause 14 and the rates for which is to be determined under the said clause 14.
(iv) The rates of payment for materials already purchased or agreed to be purchased by the contractor before receipt of notice given by the Engineer-in-Charge under clause 15, and/or the amount of compensation payable to the contractor under the said clause for loss in respect of such materials.
(v) The amount of compensation which the contractor shall be liable to pay under clause 17 in the event of his failure to rectify, remove or reconstruct the work within the period specified in the written intimation or the amount of expenses incurred by the Engineer-in-Charge under the said clause 17 in rectifying, removing or re-executing the work or in removing and replacing the materials or articles complained of.
(vi) The reduction of rates as may be fixed by the Engineer-in-Charge under clause 17 for the inferior work or materials as accepted or made use of.
(vii) The amount of compensation payable by the contractor for damages as estimated and assessed under clause 23.
(viii) The amount payable to the contractor for the work carried out under clause 33 in accordance with the instructions and the requirements of the Engineer-in-Charge in a case where there are no specifications.
(2) The provision of Section21 of the GPWD dispute Arbi. Tribunal Act 92 & order issued by the Govt. in connection with this Act will now apply for Arbitration (As per Government in N, & W.R.D. letter No.SUT/1090/2679/K2 dtd. 9/2/94.
(3) The provision of Arbitration Act, shall in so far as they are inconsistent with the provision of this act cease of to apply to any dispute arising from a works contract and all arbitration proceedings in relation to such dispute before an arbitrator, court of authority shall stand transferred to the Tribunal.
(4) The awards declared by the arbitrator should be speaking award, giving reasons and calculations for every item of claims. Th
Om Construction Company Vs. Ahmedabad Municipal Corporation and Anr.
Point of Law : Arbitration - Respondent Corporation is a “public undertaking” as contemplated in Clause (i) of Section 2(1)(i) and the contract entered into between the parties was a “works contract”....
The Court emphasized the importance of examining the existence and validity of an arbitration agreement at the referral stage and the rejection of manifestly non-arbitrable claims.
The Court's jurisdiction under Section 11(6) of the 1996 Act is limited to examining the existence and validity of an arbitration agreement, and the Court may reject claims that are manifestly non-ar....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.