SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Guj) 2011

IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
SUNITA AGARWAL, CJ. 
 
National Dairy Development Board - Petitioner 
Versus 
Harsh Agrawal – Respondent
R/Petn. Under Arbitration Act No. 100 of 2025 
Decided On : 22-09-2025
 

Advocates Appeared:
For the Petitioner: Udit N. Vyas.
For the Respondent: Party In Person.

An arbitration agreement can be inferred from the parties' conduct, and objections regarding jurisdiction must adhere to the terms outlined in the agreement.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 11(6) - National Dairy Development Board Act, 1987 - Dispute regarding execution and venue of arbitration - Applicant seeks appointment of arbitrator and objection to jurisdiction and venue raised by respondent - Court held that agreement existed despite disputes about execution and venue, appointing an arbitrator in Anand as per agreed terms. (Paras 26-34)

(B) Arbitration Agreement - Existence of an arbitration agreement inferred from conduct and communications despite lack of signature - Provisions of the Arbitration and Conciliation Act govern resolution of disputes arising from agreements. (Paras 30-32)

Facts of the case:
The case arises from a subsidy agreement between two parties for establishing a Breed Multiplication Farm under a government scheme. The respondent failed to progress as per the agreement, leading to cancellation of subsidy by the Ministry. (Paras 2-8)

Findings of Court:
The court found a valid arbitration agreement existed and appointed an arbitrator, determining that objections related to jurisdiction did not negate the enforceability of the agreement. (Paras 28-34)

Issues: Whether the agreement was valid and contained an enforceable arbitration clause; jurisdictional objections raised by the respondent. (Paras 12-13, 26)

Ratio Decidendi: The court clarified that an arbitration agreement can be inferred from conduct and correspondence, and jurisdictional matters are governed by the terms agreed upon by the parties in the arbitration clause. (Paras 27-33)

Result: The petition is allowed and an arbitrator is appointed.

Table of Content
1. background of the arbitration case. (Para 1 , 2 , 3)
2. release and inspection of subsidy tranches. (Para 4 , 5 , 6 , 7)
3. response to cancellation and demand for refund. (Para 8 , 9)
4. respondent's jurisdiction objections and financial burdens. (Para 10 , 11 , 12 , 13)
5. constitutional rights and grant implications. (Para 14 , 15 , 16 , 17)
6. dispute over validity of the agreement and allegations. (Para 18 , 19 , 20 , 21 , 22)
7. petitioner's prayer and objections regarding arbitration. (Para 23 , 24 , 25)
8. analysis of jurisdiction and arbitrator appointment. (Para 26 , 27 , 28 , 29)
9. execution of arbitration agreement affirmed. (Para 30 , 31 , 32 , 33)
10. appointment of arbitrator and conclusion. (Para 34)

ORDER :

SUNITA AGARWAL, CJ.

1. Having heard Mr. Udit N. Vyas, learned counsel for the petitioner and Mr. Harsh Agrawal, respondent appearing as party-in-person and perused the record, pertinent is to note that the present petition has been filed by the National Dairy Development Board, an institute of national importance, constituted by an Act of Parliament namely the National Dairy Development Board Act, 1987. It is stated in the petition that the petitioner – Board can sue and be sued in its own name. The petitioner has been appointed as the Nodal Agency for implementation of a scheme namely Rashtriya Gokul Mission launched by Animal Husbandry and Dairying, Government of India for development and conservation of indigenous bovine breeds. Financial assistance in the nature of subsidy/grant in aid is to be provided to the beneficiaries which are desirous of establishing and operating Breed Multiplication Farms to the extent of 50% of the capital cost subject to a maximum of INR 2 crore per applicant.

2. The respondent namely Mr. Harsh Agrawal had applied for subsidy of INR 200 Lakhs under the Breed Multiplication Farms Scheme (in short referred as “BMF Scheme”), on the designated portal for establishing a Breed Multiplication Farm at Momanthal, Noida, Uttar Pradesh. The subsidy to the tune of INR 200 Lakhs was sanctioned in favour of the respondent by the Ministry vide order dated 01.12.2022.

3. In furtherance of the sanction, an agreement for implementation of Breed Multiplication Farm Programme under the Rashtriya Gokul Mission was entered into between the petitioner and the respondent on 02.02.2023. A copy of the said agreement is appended at Annexure B to the petition.

4. It is contended by the petitioner that as per the terms and conditions of the agreement, the petitioner was to release the subsidy in 4 (four) tranches of INR 50 Lakhs each. The first tranche was to be released on the approval of the project, subject to the release of funds by the lending bank of the respondent. The release of subsequent tranches would depend on the actual physical progress of the project, as certified by the petitioner.

5. Accordingly, an amount of INR 50 Lakhs was released in the account of the respondent on 22.03.2023. On 31.03.2023, the first physical progress inspection of the project site was conducted by the officials deputed by the petitioner. In the said report, the respondent had assured that full infrastructure for the project with the capacity of 200 animals would be ready by September, 2023. A copy of the inspection report drawn on 31.03.2023 is appended at Annexure ‘D’ to this petition.

6. Another physical verification inspection was carried out by the officials deputed by the petitioner on 25.09.2023. However, it was noticed that there was virtually no progress in the project, inasmuch as, even the civil work for construction of shed had not commenced. The respondent had not even procured any livestock required for the project. During the course of visit, the respondent indicated that he would require a further period of 12 months, i.e. till September, 2024 to complete the infrastructure for the project. Subsequent thereto, another inspection of the project site was made on 13.02.2024. During the course of th

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

AI

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top