IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM: NAGALAND: MIZORAM & ARUNACHAL PRADESH) ITANAGAR PERMANENT BENCH (YUPIA)
NANI TAGIA, MITALI THAKURIA, JJ.
Shri Ano Umpe, S/o Late Y. Umpe – Appellant
Versus
The Land Acquisition Collector/Deputy Commissioner
Writ Appeal No.12(AP)2022
Decided on : 22-02-2023
Land Acquisition Act, 1894 - Section 11 - Land Acquisition - Compromise agreement - Compensation - Petitioners’ land was acquired for 2800 MW Dibang Valley Multipurpose Hydro-Electric Project, for which an award in respect of all beneficiaries including petitioners was passed to extent - Writ petition, had contended that State authorities including Deputy Commissioner, together with the NHPC Ltd. had devised a strategy of delaying disbursement of compensation and whoever had approached authorities for compensation were asked to sign a compromise agreement not to claim awarded amount and thereafter, the part-payment of compromise amount was made - It was contended that out of award for an amount of approximately Rs.1601.39 crore, respondent No.2, NHPC Ltd. had deposited only about Rs.640.00 crore - Held, Once award has been passed in accordance with law relating to land acquisition, unless award is modified or rescinded, award is executable and the compensation earmarked therein, is entitled to be received by parties, for whom amount has been determined in the award. Whether it is the Land Acquisition Act, 1894 or the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, after award is passed by competent authority, there is no provision in either of law that there can be any settlement on a compromise basis between/amongst the parties - Appeal stands disposed of
JUDGMENT :
(N.Tagia, J)
1. Heard Mr. R. Saikia, learned counsel for the appellants. Also heard Mr. K. Ete, learned Advocate General(In-charge) for the State of Arunachal Pradesh, representing respondent No.1 and Mr. P. K. Tiwari, learned Senior Counsel for the National Hydro Power Corporation Ltd.(NHPC), representing respondent No.2.
2. This Intra-Court Appeal is directed against the judgment and order dated 11.05.2022, passed by the learned Single Judge in the writ petition being WP(C) No.60(AP)2022.
3. The appellants, altogether 15(fifteen) in numbers, who were part of the 116 writ petitioners, had preferred WP(C) No.60(AP)2022, under Article 226 of the Constitution of India, seeking a direction to the respondent No.1, the Land Acquisition Collector-cum-Deputy Commissioner, Dibang Valley District, Anini, to disburse the compensation amount to the writ petitioners, so deposited by the National Hydro Power Corporation Ltd.(in short “NHPC Ltd.”), by allowing them to withdraw the same under protest, in terms of Section 77 of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013(hereinafter the “Act of 2013” for short).
4. The appellants/writ petitioners’ case before the learned Single Judge was that the petitioners’ land was acquired for 2800 MW Dibang Valley Multipurpose Hydro-Electric Project, for which an award in respect of all beneficiaries including the petitioners was passed to the extent of Rs.1601,39,31,725/-(Rupees One thousand six hundred one crore thirty nine lakh thirty one thousand seven hundred twenty five only), which was approved by the Deputy Commissioner, Dibang Valley District, Anini, vide order dated 07.09.2018. The approval of the award by the State Government was conveyed vide letter dated 18.02.2018. Later on, the State had rescinded and/or cancelled the award vide order dated 20.12.2019. By an order dated 24.03.2020, the State Government, however, had withdrawn the order dated 20.12.2019. While some of the project affected persons had challenged the order dated 20.12.2019, the legality of the award was assailed by the NHPC Ltd., i.e., the respondent No.2.
5. The appellants along with other petitioners in the writ petition, had contended that the State authorities including the Deputy Commissioner, together with the NHPC Ltd. had devised a strategy of delaying disbursement of compensation and whoever had approached the authorities for compensation were asked to sign a compromise agreement not to claim the awarded amount and thereafter, the part-payment of compromise amount was made. It was contended that out of the award for an amount of approximately Rs.1601.39 crore, the respondent No.2, NHPC Ltd. had deposited only about Rs.640.00 crore. It was further contended that the respondent authorities were not making payment of any money to those award holders, who were not submitting themselves to accept the compromise amount. The appellants along with other petitioners further contended that since the NHPC Ltd. had deposited a sum of Rs.640.00 crore, the appellants had an indefeasible right to collect their proportionate share of award under protest. The appellants/writ petitioners, thus, essentially contended before the learned Single Judge that the appellants have been discriminated by the State authorities in not releasing their proportionate share of compensation, while the same has been released to those, who had signed the compromise agreement. Under the aforesaid circumstances, a direction was sought for, to the State authorities to allow the appellants/writ petitioners to receive their proportionate share of compensation under protest, in terms of Section 77 of the Act of 2013.
6. Resisting the prayer of the appellants/writ petitioners, the State in the counter-affidavit filed had, firstly, contended that the State authorities have a right to have
SupremeToday
Compensation for land acquisition must be determined under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, where prior proceedings unde....
The court affirmed the obligation of the state to pay compensation for land acquisition as mandated by law, emphasizing the validity of the award and the constitutional right to property.
Section 3G of National Highways Act, 1956 provided for procedure for determination of amount payable as compensation.
The main legal point established in the judgment is the importance of clarifying disputed questions of fact and doubts on the authenticity of the draft award before seeking any direction for payment ....
The court affirmed the obligation to pay compensation for land acquisition, emphasizing the learned Single Judge's jurisdiction to direct payment when no challenge to the award existed.
Petitioners are not entitled to claim compensation for structures on enhanced rate, on the basis of Standard Schedule Rates of 2005-06.
Compensation in land acquisition must adhere to statutory requirements, including formal awards under section 11 of the Land Acquisition Act, or provisions of the updated Act of 2013 apply.
The award under Section 23-A of the Fair Compensation Act, 2013 is not final and binding if all 'persons interested' did not appear before the Competent Authority and agree in writing on the matters ....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.