2023 Supreme(Gau) 451

IN THE HIGH COURT OF GAUHATI, NAGALAND, MIZORAM AND ARUNACHAL PRADESH AT KOHIMA BENCH
Songkhupchung Serto, Kakheto Sema, JJ.
Chakhesang Public Organisation, Represented By Its President And Ors. – Petitioners
Versus
The Union Of India Represented By The Secretary, Ministry Of Road Transport And Highways, Parivahan Bhavan, 1, Parliament Street, New Delhi And Ors. – Respondents
PIL 9 of 2019
Decided On : 30-01-2023

Advocates:
Advocate Appeared:
For the Petitioner: Angshuman Sarma
For the Respondent: Yanger Wati

Headnote:

Tender process - Roads construction - In order to improve pathetic conditions of roads in State of Nagaland, Ministry of Road Transport & Highways under scheme known as Special Accelerated Road Development Programme – NE allotted a sum of Rs. 1,296/-crores for construction of 2-lane road - Ministry of Road Transport & Highways and Public works Department, Nagaland were notified to be the funding and executing agency; and the implementing agency respectively - After tender process Contractor, namely M/s Maytas Gayatri (joint – venture) was issued the work order and the Contractor started executing work in year 2011 under supervision of State PWD - During process of execution of work, a lot of cut-earths, stones, trees etc., were piled up along roads under construction instead of dumping same at identified dumping sites - When rainy season came they slid down on lands and properties of villagers who are settled along road causing severe damage to their lands and properties - Held, land owners being tribals and marginal land owners, authorities; be it from Central Government or State Government or both, should have been a little more sensitive and considerate, if need be, while undertaking project so that they need not have gone through such loss and suffering - Project started in year 2011; it has been more than 10 (ten) years since owners of lands have suffered loss of their lands, crops and properties - A welfare State, certainly, is not expected to be so apathetic about genuine grievances of its own citizens - It does not behove for a welfare state to deny or defer benefit of such right by giving such excuse as that, land owners may make such claim in pending arbitration process, especially when lands owners are not a party in proceeding. Therefore, to prevent any further suffering of these people, both Central Government and the State Government should act in tandem expeditiously – Order accordingly.

JUDGMENT :

S. Serto, J.

This is a PIL filed by Chakhesang Public Organization, through its functionaries on behalf of persons whose lands/properties including crops, irrigation and fields, drainage etc. were damaged due to the construction of 2-lane road within Phek District under the 2-lane Project: Longleng-Changtongya – Mon -Tamlu – Merangkong, Phek – Pfutsero and Zunheboto – Chakhabama, SARDP (Special Accelerated Road Development Programme) -NE, praying for issuance of appropriate writ/order/direction directing the respondents to pay compensation for the damages caused.

2. Heard Mr. Angshuman Sarma, learned counsel appearing for the petitioners, Mr. L.T. Sangtam, learned Additional AG appearing for the State respondents, Mr. Yangerwati, learned CGC appearing on behalf of the Union of India (respondent No. 1), and Mr. L. Iralu, learned counsel appearing for respondent No. 10.

3. The facts and circumstances leading to the filing of this PIL briefly stated are as follows: In order to improve the pathetic conditions of the roads in the State of Nagaland, the Ministry of Road Transport & Highways under the scheme known as Special Accelerated Road Development Programme – NE allotted a sum of Rs. 1,296/-crores for construction of 2-lane road from Longleng -Changtongya – Mon -Tamlu – Merangkong, Phek – Pfutsero and Zunheboto – Chakhabama. Ministry of Road Transport & Highways and the Public works Department, Nagaland were notified to be the funding and executing agency; and the implementing agency respectively. After the tender process the Contractor, namely M/s Maytas Gayatri (joint – venture) was issued the work order and the Contractor started executing the work in the year 2011 under the supervision of the State PWD. During the process of the execution of the work, a lot of cut-earths, stones, trees etc., were piled up along the roads under construction instead of dumping the same at the identified dumping sites. Therefore, when the rainy season came they slid down on the lands and properties of the villagers who are settled along the road causing severe damage to their lands and properties. Since the land owners are poor farmers and ignorant about their rights and the ways and means to redress their grievances, the petitioner/Organisation took upon itself to help them in approaching the right authorities and forums through legal means so that their grievances are addressed or redressed as per law. So after several meetings were held the petitioner submitted two representations dated 18.10.2019 and 20.10.2019 to the Chief Engineer, PWD (National Highway), Nagaland and to the Deputy Commissioner, Phek respectively, requesting for compensation for the damages caused to the properties of the land owners whose lands and properties have been affected during the construction of the road specifically for the land owners along the stretch of the road viz.Phek -Pfutsero and Zunheboto -Chakhabama under the administrative jurisdiction of EAC, Sakraba, Phek District. Though the representations did not receive immediate response as desired, the office of the PWD (National Highway), Nagaland conducted a joint-survey of the lands and properties damaged/destroyed, for the purpose of ascertaining the extent of the damage caused to each individual’s land and properties and for the purpose of quantifying the compensation to be paid. The same was carried out under the aegis of the Deputy Commissioner under whose jurisdiction the properties are situated. The joint verification was conducted by the officers of the State, aggrieved persons, and members of local administrative bodies after issuance of proper notification by the Deputy Commissioner concerned. As per the joint survey, the compensation amount worked out for the land owners between Phek – Pfutsero road was Rs. 5,81,69,989.70/-and for the land owners between Zunheboto and Chakhabama road it was Rs. 55,12,66,695.34/-. However, the State Government of Nagaland did not disburse the amount to the