IN THE HIGH COURT OF GAUHATI, ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH
MICHAEL ZOTHANKHUMA, J.
A.N.E. INDUSTRIES PVT. LTD. – Petitioner
Versus
UNION OF INDIA – Respondent
Arb. Pet. No. 24 of 2023
Decided On : 30-01-2024
ARBITRATION - APPOINTMENT OF ARBITRATOR - Arbitration and Conciliation Act, 1996, Sections 11, 12 - The court discussed the provisions of the Arbitration and Conciliation Act, 1996, particularly Sections 11 and 12, emphasizing the need for an independent and impartial arbitrator as mandated by the Supreme Court in Perkins Eastman Architects DPC & Anr. Vs. HSCC (India) Ltd. The court highlighted that the Managing Director of the respondent company could not appoint an arbitrator due to statutory ineligibility under the amended Section 12(5) of the Act, which disqualifies individuals with a vested interest in the dispute from serving as arbitrators. This interpretation influenced the court's decision to appoint an independent arbitrator instead.
Fact of the Case:
The petitioners were awarded a work order for coal extraction but were halted by forest officials due to lack of permission from the Forest Department. They sought arbitration for compensation after exhausting in-house dispute resolution procedures.
Finding of the Court:
The court found that the appointment of an arbitrator must comply with the amended provisions of the Arbitration and Conciliation Act, 1996, which require an independent arbitrator, thus ruling against the appointment procedure outlined in the contract that involved an interested party.
Issues: Whether the appointment of an arbitrator should follow the procedure outlined in the arbitration clause of the contract, or whether an independent arbitrator must be appointed as per the amended provisions of the Arbitration and Conciliation Act, 1996.
Ratio Decidendi: The court held that the amended Section 12(5) of the Arbitration and Conciliation Act disqualifies the Managing Director from appointing an arbitrator due to potential bias, necessitating the appointment of an independent arbitrator as per the Supreme Court's interpretation in Perkins Eastman.
Final Decision: The court appointed Hon’ble Mr. Justice H.N. Sarma as the arbitrator to resolve the dispute, emphasizing the need for independence in the arbitration process.
ORDER :
1. Heard Mr. C.P. Sarma, learned Senior Counsel assisted by Mr. A. Lal, learned counsel appearing for the petitioners. Also heard Mr. M.Z. Ahmed, learned Senior Counsel assisted by Mr. A.M. Dutta, learned counsel appearing for the respondent Nos. 2 to 4. Mr. K. Gogoi, learned counsel appears on behalf of the respondent No. 1.
2. The petitioners herein have prayed for appointment of an Arbitrator in terms of Section 11 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the ‘1996 Act’) keeping in view the amended Section 12 of the 1996 Act, as has been interpreted by the Hon’ble Supreme Court in the case of Perkins Eastman Architects DPC & Anr. Vs. HSCC (India) Ltd. (2020) 20 SCC 760, i.e., an independent and disinterested Arbitrator would have to be appointed by the Court and not in terms of the procedure provided in the arbitration clause, wherein the Arbitrator is an interested person.
3. On the other hand, the counsel for the respondent Nos. 2 to 4 submits that the appointment of an Arbitrator would have to be done under Section 11 of the 1996 Act in terms of the decision of the Hon’ble Supreme Court in the case of Union of India Vs. Parmar Construction Company, (2019) 15 SCC 682 and in the case of Union of India Vs. Pradeep Vinod Construction Company, (2020) 2 SCC 464, whereby the Arbitrator would have to be appointed in terms of the procedure laid down in the arbitration clause of the agreement, even if the Arbitrator is an interested person or if not an interested person, appointed by an interested person.
4. The brief facts of the case is that the petitioners were allotted a work order by the respondent No. 3 on 16.10.2019 for extraction of coal seams at Tikak OC, Tikak Colliery by open cast method for 5 years. The petitioners thereafter mobilized/deployed machinery and manpower on the site for extraction of coal seams. However, the forest officials from the Government of Assam stopped all works at the site on 05.11.2019. The petitioners were directed not to resume any mining activity on the ground that no permission had been taken from or given by the Forest Department for the mining activity. Thereafter, an alternative site was provided to the petitioner for their mining activities, in which they are still working. The petitioners are now claiming compensation for the loss incurred in having their mining activities stopped in the original site, due to the respondent No. 3 not having taken the prior permission of the Forest Department, Government of Assam.
5. The petitioners’ counsel submits that in terms of Clause 13(a) of the NIT, there is an in-house procedure for settlement of disputes between the parties. After exhausting the procedure in terms of Clause 13(a), there is a further procedure for settlement of disputes through arbitration under Clause 13(b), if the procedure under Clause 13(a) fails. The learned Senior Counsel submits that though in-house procedure for settlement of disputes under Clause 13(a) of the NIT had been availed of by the parties, no settlement could be arrived at between the parties. As such, the petitioners are now praying for settlement of the disputes through arbitration, in terms of Section 11 of the 1996 Act and the decision of the Hon’ble Supreme Court in Perkins Eastman (supra), wherein the Arbitrator would have to be appointed by this Court and not by the CMD of the respondent Company.
6. On the other hand, the stand of the respondents is that as the arbitration clause provided under 13(b) provides that the Arbitrator should be appointed by the CMD of the respondent Company, the Arbitrator should be appointed in that manner only, in terms of the law laid down by the Hon’ble Supreme Court in the case of Parmar Construction Company (supra) and Pradeep Vinod Construction Company (supra).
7. Clause 13(b) of the NIT which provides the procedure for settlement of disputes through arbitration, states as follows:
If the pa
Perkins Eastman Architects DPC & Anr. Vs. HSCC (India) Ltd. (2020) 20 SCC 760
TRF Ltd. Vs. Energo Engg. Projects Ltd. (2017) 8 SCC 377
The court established that under the amended Arbitration and Conciliation Act, 1996, an arbitrator must be independent and impartial, and parties cannot appoint an arbitrator if the appointing author....
Once person who was required to arbitrate upon disputes arisen under terms and conditions of contract becomes ineligible by operation of law, he would not be eligible to nominate a person as an arbit....
Point of Law : S.13(2) provides that a party who intends to challenge appointment of an arbitrator shall, within fifteen days after becoming aware of the constitution of the arbitral tribunal or afte....
The main legal point established in the judgment is that the appointment of an arbitrator must be in accordance with the law, and if found to be invalid, the court has the jurisdiction to set it asid....
The interpretation of Section 15(2) of the Arbitration and Conciliation Act, 1996 is that where the mandate of an arbitrator terminates, a substitute arbitrator shall be appointed according to the ru....
Appointment of arbitrator by designation is permissible. Arbitration clauses in government contracts providing that an employee of the department will be the sole arbitrator are neither void nor unen....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.