SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2024 Supreme(Gau) 1532

IN THE GAUHATI HIGH COURT (HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH) KOHIMA BENCH
MANISH CHOUDHURY, J.
M/s Genmachines – Appellant
Versus
State Of Nagaland And Ors – Respondents
Review. Pet. 5 of 2024
Decided on : 02-12-2024

Advocates:
Advocate Appeared:
For the Petitioner: N. LONGKUMER, NISUKA CHISHI, KIM PIENYU, REBECCA, LUCY WEO, M SOLO
For the Respondent: GOVT ADV NL

IMPORTANT POINT
The court clarified that review powers are limited to correcting errors, not re-evaluating merits, and dismissed the review petition for lack of merit.

Headnote:

(A) Constitution of India - Article 226 - Review of order - The review petition sought to challenge the order dated 01.10.2024, which directed the State respondents to disburse the admitted outstanding amount of Rs. 617.38 lakhs to the petitioner. The petitioner claimed a higher amount of Rs. 647.57 lakhs, but the State respondents admitted liability only for Rs. 617.38 lakhs. The court emphasized that the review power is not to be confused with appellate powers and is limited to correcting errors apparent on the face of the record. The court found no merit in the review petition and dismissed it. (Paras 1, 7, 12, 15)

JUDGMENT :

The instant review petition is preferred seeking review of an Order dated 01.10.2024, whereby, a writ petition, W.P.[C] no. 10/2024 after hearing, has been disposed of with certain observations and directions. It is relevant to mention that in the writ petition, W.P.[C] no. 10/2024, the present review petitioner was the writ petitioner.

2. I have heard Mr. N. Longkumer, learned counsel for the review petitioner and Mr. Imti Imsong, learned State counsel for all the respondents.

3. Before dilating on the grounds on which the instant review petition is preferred, it appears appropriate to extract the contents of the Order dated 01.10.2024 passed in the writ petition, W.P.[C] no. 10/2024, for better appreciation, :-

    2. The projected case of the petitioner, in brief, is that it is a registered supplier and contractor and has earned its reputation in execution of small hydro electric project, design, supply, erection, commissioning, total building management system, testing, servicing of power plants, etc. and it has the experience of executing a number of hydro project works in various parts of the country.

    2.1. On 09.12.2015, the office of the Chief Engineer [T&G], Department of Power, Nagaland [the respondent no. 4] published a Short Notice Inviting Tender [SNIT] inviting sealed bids from reputed Manufacturers, Authorized Distributors and Engineering Procurement and Construction [EPC] Contractors for construction of ‘Ponglefo Hydro Electric Project’ [‘the Project’, for short] at Salomi village under Kiphire District of Nagaland at an approximate cost of Rs. 16.00 crores. In response to the SNIT which was widely published in the local newspapers, the petitioner along with others submitted its sealed bid. After evaluation, the petitioner was selected and was awarded an Work Order dated 06.02.2016 for construction of the Project, that is, Ponglefo Hydro Electric Project, 2 x 500 kw and the petitioner was directed to execute a Contract Agreement within 15 days from the date of issue of the Work Order. A Contract Agreement was thereafter, executed between the petitioner and the respondent no. 4 on behalf of the Government of Nagaland on 14.03.2016 after complying with all the formalities. The details of the Project was set forth in the said Contract Agreement. After issuance of the Work Order and the execution of the Contract Agreement, the petitioner proceeded to execute the Project, Ponglefo Hydro Electric Project in a remote area in Kiphire District which does not have proper road connectivity and other infrastructure.

    2.2. It is the further case of the petitioner that despite the hardships and difficulties faced by it apart from unprecedented monsoon rains and natural calamities, the petitioner was able to complete the Project, Ponglefo Hydro Electric Project. The petitioner has asserted that the Ponglefo Hydro Electric Project was successfully erected, tested and technically commissioned on 27.08.2020. After completion of the Project, the petitioner had intimated the respondent authorities regarding completion of the Project vide a Letter dated 30.11.2022 with a request to make payment of its outstanding bill amount against the Project.

    2.3. When the respondent authorities failed to pay the outstanding bill amount, the petitioner stated to have sent reminders on 03.04.2023 and 19.05.2023 for payment of the outstanding bill amount. When despite the reminders, the respondent authorities failed to make the payment, the petitioner sent a Legal Notice on 30.10.2023 to the respondent authorities demanding payment of the outstanding bill amount within thirty days from the date of receipt of the notice.

    2.3. In response to the Legal Notice, the petitioner was furnished a copy of the Letter dated 22.11.2023 sent by the respondent no. 4 to the Commissioner & Secretary to the Government of Nagaland, Department of Power [the respondent no. 2] inviting attention of the respondent no. 2 that a proposal was already submitted for provisionin

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top