SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2022 Supreme(Ker) 987

IN THE HIGH COURT OF KERALA AT ERNAKULAM
V.G. ARUN, J.
M/s. PGCCPL and Aryacon Consortium – Petitioner
Versus
Kerala State Electricity Board Limited – Respondent
W.P. (C) No. 32855 of 2022
Decided On : 09-11-2022

Advocates:
Advocate Appeared:
For the Petitioners: Joseph Kodianthara, Isaac Thomas, Sharad Joseph Kodanthara, Alexander Joseph Markos.
For the Respondents: G. Keerthivas, T.K. Sreekala, Vineeth Komalachandran, S. Parvathi, Kalliyani Krishna B., Uthara Asokan, V.V. Asokan, Harishankar, Mayankutty Mather K.I.

Headnote:

Constitution of India – Article 226 - Probable Amount of Contract – Tender - Petitioners had serious doubts about the third respondent's qualification, the materials submitted by the third respondent in support of its bid was downloaded from the website - Third respondent had failed to comply with Clause of the instructions to the bidders forming part of Notice Inviting Tender - Whether the public interest is affected – Held, In the light of certificates issued by the Chartered Accountant, the award in favour of the third respondent cannot be termed as a decision which no responsible authority, acting reasonably and in accordance with relevant laws, could have reached - Public interest is also in favour of the award - Petition dismissed.

JUDGMENT :

V.G. ARUN, J.

1. The Kerala State Electricity Board Limited/second respondent, invited tenders for the execution of Civil and Hydro Mechanical works of Upper Sengulam Hydro Electric Project vide Ext.P1 e-tender notice dated 3.5.2022, with the Probable Amount of Contract (PAC) fixed at Rs. 1,75,60,70,410/-. The first petitioner and respondents 3 and 4 were pre-qualified in the tender and Ext.P4 Note containing the details of the pre-qualified bidders was published on 7.10.2022. The price bids were opened on 10.10.2022 and the third respondent declared as the lowest bidder, as evidenced by Ext.P6, the BOQ summary details. As the petitioners had serious doubts about the third respondent's qualification, the materials submitted by the third respondent in support of its bid was downloaded from the website. A scrutiny of the documents proved the petitioners' suspicion to be correct. It came to light that the third respondent had failed to comply with Clause 26.2.1(c), Clause 3.1.6 and 27.1 of the instructions to the bidders forming part of Ext.P1 Notice Inviting Tender. Hence, this writ petition seeking the following reliefs:

    (a) Call for the records relating to Exhibit P4 Note No. CECCS)USHEP/Tender/ 2022-23 dated 7.10.2022 and Exhibit P5 Note No. CECCS)/USHEP/Tender/2022-23 dated 10.10.2022 both issued by the 2nd Respondent and to quash the same to the extent it has pre-qualified the 3rd Respondent and declare its bid as L1 by issue of a writ of certiorari, or such other appropriate writ, order or direction.

(b) Declare that the 2nd Respondent cannot entertain the bid submitted by the 3rd Respondent due to lack of pre-qualification and consequently declare the 1st Petitioner as L1 in E-Tender No. CECCS/01/2022-23 dated 03.05.2022 invited by the 2nd Respondent by a writ of mandamus or such other appropriate writ, order or direction.

(c) Stay all further proceedings pursuant to Exhibit P1 E-Tender No. CECCS/01/2022-23 dated 03.05.2022 invited by the 2nd Respondent and Exhibit P4 Note No. CECCS/USHEP/Tender/2022-23 dated 7.10.2022 and Exhibit P5 Note No. CECCS)USDHEP/Tender/2022-23 dated 10.10.2022.

2. Senior Advocate Joseph Kodianthara appearing for the petitioners contended that the third respondent having failed to satisfy the mandatory conditions for pre qualification, respondents 1 and 2 ought to have rejected its bid at the pre-qualification stage. As per Clauses 3.1.6 and 27.1.of Ext.P1, the lead bidder of a joint venture consortium should have a turnover of not less than 30% of the probable amount of contract for the last three years. The PAC being Rs. 1,75,60,70,410/- 30% of the same would come to Rs. 52,68,21,123/-. Going by the balance sheet and profit and loss accounts of M/s. Anchor Structural, Engineers and Contractors, the lead bidder of the third respondent consortium, its turnover for the three financial years preceding the tender is only Rs. 47,77,13,533/-.

3. In a patently illegal and fraudulent attempt to overcome this defect, the third respondent produced Ext.P8 Asset and Business Operation Transfer Agreement where under the lead member of the consortium agreed to acquire certain assets of a proprietorship concern. In an attempt to lend further support to its claim, the third respondent produced Ext.P9 Chartered Accountant's Certificate dated 17.6.2022, wherein the Chartered Accountant included the supposed outcome of Ext.P8 agreement to the turnover of the lead member, so as to make it appear that the lead member had the requisite turnover stipulated in Clause 3.1.6 and 27.1 of Ext.P1.

4. Learned Senior Counsel further contended that as per Clause 27.2, the assessment of the applicant's total turnover for the last three years should be based on the audited annual accounts submitted by the bidder. The Chartered Accountant should issue the certificate in the format prescribed as per Annexure 6 to Ext.P1. As such, there is no provision for producing and accepting a certificate like Ext.P9. Even otherwise, Ext.P8

        Click Here to Read the rest of this document
        1
        2
        3
        4
        5
        6
        7
        8
        9
        10
        11
        SupremeToday Portrait Ad
        supreme today icon
        logo-black

        An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

        Please visit our Training & Support
        Center or Contact Us for assistance

        qr

        Scan Me!

        India’s Legal research and Law Firm App, Download now!

        For Daily Legal Updates, Join us on :

        whatsapp-icon Back to top