SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Ker) 2487

IN THE HIGH COURT OF KERALA AT ERNAKULAM
M.A.ABDUL HAKHIM, J.
The Regional Director, ESI Corporation - Appellant 
Versus 
M/s. L & T Tech Park Ltd - Respondent 
Ins.App No. 3 of 2014
Decided on : 20-08-2025

Advocates Appeared:
For the Appellant : SHRI.T.V.AJAYAKUMAR, KUM.RIMJU P.H.
For the Respondent: SRI.V.ABRAHAM MARKOS, SHRI.ABRAHAM JOSEPH MARKOS, SHRI.BENNY P. THOMAS (SR.), SRI.BINU MATHEW, SRI.D.PREM KAMATH, SHRI.TERRY V.JAMES, SRI.TOM THOMAS (KAKKUZHIYIL)

The court ruled that workers engaged in pre-operative fit-out works are not covered employees under the ESI Act and ordered a refund of contributions based on prior incorrect payments.

Headnote:(A) Employees’ State Insurance Act, 1948 - Sections 2(9), 2(13), and 2(17), and Regulation 40 - Refund of contributions ordered by E.I. Court after determining workers engaged for pre-operative fit-out works are not covered employees under E.S.I. Act. The court noted that construction site workers are exempted from the Act, reaffirming their classification as unorganized workers. (Paras 2, 8, 30)

(B) Interpretation of terms - ‘Establishment’ and ‘employee’ under the ESI Act - E.I. Court addressed whether the workers engaged by the principal employer were covered employees. The Court underlined that workers engaged directly in a covered factory are considered under the Act (Paras 10, 14, 18).

(C) Employment status and liability - The court emphasized the necessity of determining if the new unit is an extension of an already existing establishment, thereby influencing the applicability of the ESI Act (Paras 19, 24).

Facts of the case:
The applicants sought a refund of ESI contributions remitted by the principal employer for workers engaged in fit-out work for an establishment not covered under the ESI Act. Controversy arose regarding worker classifications and contributions related to pre-operational activities.

Findings of Court:
The E.I. Court ruled that fit-out workers were exempt from contributions as they did not fall under the purview of the E.S.I. Act. The refund was ordered based on mistaken contributions paid under misunderstanding of applicability.

Issues: The substantial question addressed was whether the E.S.I. Act covered workers engaged in preparatory works for an establishment that was not operational at the time of work.

Ratio Decidendi: The court clarified that the lack of operational status for the establishment at the time of the fit-out works meant contributions were not applicable, alongside the broader principle that the legislation is meant to benefit workers and must be interpreted liberally.

Result: Appeal dismissed without costs.

Table of Content
1. establishment and contract details (Para 1 , 4)
2. substantial question of law identified (Para 2 , 3 , 14)
3. arguments on employer and esi contributions (Para 5 , 6 , 10 , 11)
4. legal interpretations of employment under esi act (Para 15 , 17 , 18)
5. court's decision rationale and judgment (Para 21 , 22 , 25 , 31)

JUDGMENT :

M.A.ABDUL HAKHIM, J.

1. Appellants are the Respondents Nos.1 and 2 before the E.I.Court, Alappuzha in I.C. No.67/2011 filed under Sections 75 and 77 of the Employees’ State Insurance Act, 1948 (E.S.I. Act, for short). They are the Regional Director and the Deputy Director of E.S.I. Corporation. The Respondents are the Applicant and the Respondent No.3 before the E.I. Court. The Appellants are challenging the Order by which the refund of the ESI contribution was ordered by the E.I. Court.

2. This Court formulated the following substantial question of law in this Appeal as per the Order dated 20.11.2024:

“Whether Section 2 (9) of the E.S.I. Act covers the workers engaged for pre-operative fit-out works by the employer requiring contribution to be paid as per the aforesaid Act?”

3. The parties are referred to according to their status before the E.I. Court.

4. The Corporate office of the Respondent No.3 at Mumbai was an establishment covered under the ESI Act during the relevant period. The Applicant was not an establishment covered under the ESI Act. The Applicant owns a building by the name, Thejomaya, constructed for I.T. business, I.T. enabled services and other related services and amenities pursuant to Sanction Order dated 05.04.2007 issued by the Development Commissioner, Infopark Special Economic Zone, Kochi. The building was constructed within the Special Economic Zone at Infopark, Kakkanad. The Respondent No.3 took lease of the 7th 8th & 9th floors of the said building from the Applicant for starting a new unit as per Ext.D1 Lease Deed dated 21.10.2007. As per Ext.D1 Lease Deed, the lease commencement date is 21.10.2007 or the date of actual handover of the premises by the Lessor to the Lessee to start the fit-out works. Even before the execution of the Ext.D1 Lease Deed, the Respondent No.3 awarded a contract in favour of the Applicant to do the interior fit-out works in the premises as per Exhibit A1 Contract/Work Order dated 08.10.2007. For the purpose of executing the pre- operative fit-out works, 90 days rent-free period was allowed to the Respondent No.3 by the Applicant. The interior fit-out works were completed on 11.01.2008, and the premises were entrusted to the Respondent No.3 on 11.03.2008. The Respondent No.3 started its operations of the new unit in the leased premises on 02.04.2008 by issuing Ext.A4 Letter of Intimation to the Development Commissioner (Sez-IT & ITES), Thiruvananthapuram. Since the burden to meet the ESI contribution was on the Applicant as per Ext.A1 Contract, the Respondent No.3 deducted an amount of Rs.23,68,366/- from the value of the contract payable to the Applicant and remitted the same to the E.S.I. Corporation on 29.03.2008. Ext.A1 Contract contained a clause that it is the Applicant who has to comply with all the labour laws such as E.S.I., P.F. and Contract Labour Act. The Applicant submitted Exhibit A5 Request dated 12.01.2010 to the Respondent No.1 seeking a refund of the amount remitted by the Respondent No.3 on the ground that, as per Exhibit A9 Instruction No.4/99 dated 14.06.1999 of the E.S.I. Corporation, New Delhi, the workers engaged in construction sites are exempted from the provisions of the ESI Act and that the contribution was paid by mistake and hence the Applicant is eligible to get a refund of the amounts paid by the Respondent No.3 with respect to Exhibits A1 & A2 Contracts. The Respondent No.3 also submitted Exhibit A8 Letter dated 11.03.2010 to the Respondent No.1 stating that since construction activity is exempted, the payment of contribution was made by mistake, and the Respondent No.3 had no objection to refunding the amou

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top