IN THE HIGH COURT OF KERALA AT ERNAKULAM
A.K. JAYASANKARAN NAMBIAR, SYAM KUMAR V.M., JJ.
Indian Space Research Organization (ISRO) – Appellant
Versus
M/s. Roopam Engineers and Contractors Private Limited – Respondent
W.A. No. 1262 of 2023
Decided On : 05-08-2024
| Table of Content |
|---|
| 1. details of contract execution and delays. (Para 2 , 3) |
| 2. claim for price escalation due to delays. (Para 4 , 5) |
| 3. arguments regarding contract applicability. (Para 7 , 8) |
| 4. court rejects appeal; affirms lower court's decision. (Para 9 , 10 , 11 , 12) |
JUDGMENT :
A.K. JAYASANKARAN NAMBIAR, J.
1. The respondents 1 to 4 in W.P.(C).No.17515 of 2022 are the appellants before us aggrieved by the judgment dated 09.12.2022 of the learned Single Judge in the writ petition.
2. The brief facts necessary for disposal of this Writ Appeal are as follows:
The 1st appellant is a Government of India organisation for promoting the development and application of Space Science and Technology. It had invited tenders for establishment of a Mechanical Testing Research Laboratory for Propulsion Systems – Liquid Propulsion Systems Centre [LPSC] at Valiyamala, Thiruvananthapuram. Ext.P1 notice of tender was issued on 04.05.2019 and the period of completion of the work was stipulated as 12 months. The minimum validity of the tender was 120 days from the last date of receipt of tender. On account of a delay in technical evaluation and approval for opening of a price bid, the respondent/writ petitioner was requested to extend the validity of the tender on various occassions, which was apparently agreed to by the respondent without any objections or demur. Eventually, the technical bid was opened on 17.06.2019, and the price bid was opened on 05.11.2019. The work order was issued to the petitioner on 16.03.2020, and the agreement for the work was executed with the petitioner on 19.03.2020.
3. It would appear that even before the work could commence pursuant to the issuance of the work order, the Government of India declared a complete lock-down in connection with the Covid-19 pandemic on 22.03.2020. The 1st appellant therefore intimated the respondent of the fact of lock-down. Thereafter, upon the partial lifting of the lock-down, there was a need to re-prioritize the works and therefore an administrative decision was taken by the 1st appellant to postpone the execution of work awarded to the respondent by six months. Accordingly, Ext.P11 letter dated 23.06.2020 was issued to the respondent seeking his willingness to execute the work at a later date strictly as per the work order and the agreement that was executed. Ext.P11 letter was accepted by the respondent unconditionally by issuing Ext.R1(a) communication dated 24.06.2020. Pending confirmation of budget availability due to the re-prioritization of works post lock-down, the 1st appellant once again wrote to the respondent by Ext.P13 letter dated 21.12.2020 seeking his willingness to execute the work at a later date after four months, again strictly in accordance with the work order and the agreement executed. The said letter was also unconditionally accepted by the respondent by Ext.R1(b) communication dated 07.01.2021. Thereafter Ext.P14 letter dated 10.03.2021 was issued by the 1st appellant to the respondent to commence the construction activities for the work awarded within 15 days, and the site was handed over to him on 24.03.2021.
4. While so, the respondent/writ petitioner, by Ext.P15 letter dated 12.03.2021, requested the appellants to consider the application of Clause 10C(ii) of the General Conditions of the Contract that dealt with price escalation to the contract awarded to him. The letter was issued in the phase of the express provisions of the contract which made it clear that the price escalation clause was applicable only to contracts where the stipulated period for completion of the contract was beyond 12 months. The appellants considered the said request of the respondent along with another similar request dated 08.03.2022 and rejected the same by Ext.P17 communication dated 10.03.2022. A further reiteration of the request by the respondent on 17.03.2022 was also similarly rejected by Ext.P19 communication dated 19.04.2022. In the writ petition, the respondent/writ petitio
A contract's timelines affected by mutual agreements for delays allow claims for price escalation under applicable clauses, establishing equity in contractual relations with state entities.
The court emphasized the importance of contractual terms, specifically the price variation clause, in justifying the termination of a work order and rejected the petitioner's claim of the global incr....
The suit was within limitation as the cause of action accrued upon the non-payment of the final bill, and not completing the price escalation calculations per the contract terms invalidated the defen....
The existence of an arbitration clause in the agreement does not ipso facto render a writ petition not maintainable. The High Court may still exercise its writ jurisdiction in exceptional circumstanc....
The main legal point established in the judgment is the entitlement of the petitioner to escalation cost under the contractual provision of Clause-32(a)(b)(c) despite the submission of a 'no claim ce....
Termination of Contract - Execution/completion of project - Learned Single Judge has rightly come to conclusion that there is no arbitrariness on part of respondents in terminating contract as they h....
(1) Disputes arising out of purely contractual obligations cannot be entertained by High Court in exercise of extra-ordinary writ jurisdiction.(2) A wrong doer ought not to be permitted to make profi....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.