SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Ker) 289

IN THE HIGH COURT OF KERALA AT ERNAKULAM
SOUMEN SEN, C.J., SYAM KUMAR V.M., J.
M/S. RCC-ACC (JV), Represented By Its Authorised Representative, Mr. Rajeev Jain – Applicant
Versus
Board of Major Port Authority For Port Of Cochin Willingdon Island, Represented By The Chief Engineer – Respondent 
WA No. 834 of 2026
Decided On : 06-04-2026

Advocates Appeared:
For the Applicant : Sri. Ranjith Varghese, Sri. Rahul Varghese, Shri. Ralitzine Mendez, Smt. Akhila Sunil Nedungadi.

Show cause notice must specify all grounds and actions; writ jurisdiction limited where arbitration clause and efficacious remedies exist.

Headnote:The judgment involves a writ appeal against termination of an EPC contract for cruise terminal construction, citing delays, non-compliance with supplementary agreement, and inferior workmanship as per show cause notice under contract terms. Essential facts include contractor's reply highlighting lack of CRZ approval and ongoing arbitration on scope variations, with termination following despite invocation of Arbitration Clause. Court findings emphasize principles of natural justice requiring show cause notices to specify all grounds and proposed actions, referencing Arbitration and Conciliation Act, 1996, and Article 226 remedies. Key issues framed: Whether termination was illegal for introducing new grounds absent from show cause notice, bypassing arbitration, and if writ jurisdiction applies despite arbitration clause. Ratio decidendi holds that authorities cannot rely on grounds not in show cause notice, as affirmed in precedents; writ petitions are entertainable despite arbitration clauses where no efficacious remedy exists, but courts reluctant if alternative forums available; disputed facts better suited for arbitration. Writ appeal disposed of, directing joint measurements and no coercive steps for six weeks due to recess, without prejudice to rights; blacklisting to follow due procedure.

Table of Content
1. contract termination via show cause notice for delays. (Para 1 , 2)
2. arbitration invoked; new termination grounds challenged. (Para 3 , 4)
3. show cause must specify all grounds per natural justice. (Para 5 , 6 , 7)
4. writ court can address disputed facts despite arbitration. (Para 8 , 9)
5. writ declined; interim relief granted pending arbitration. (Para 10 , 11 , 12 , 13 , 14 , 15)

JUDGMENT :

SOUMEN SEN, C.J.

This writ appeal is filed at the instance of a contractor assigned with the work of construction of international and domestic cruise terminal and other allied facilities at Mormugao Port Authority through EPC contract, Tender No.T15-T-1946/2021-C.

2. The genesis of the dispute is the show cause notice dated 21.11.2025. In the show cause notice it was alleged by the Cochin Port Authority that the contract is liable to be terminated for wrongful delay or suspension of work or slow progress or inferior workmanship and in the event, no satisfactory reply is received within 10 days, the contract would stand terminated. The show cause notice was duly replied on 01.12.2025. One of the grounds was non availability of the valid CRZ approval and indemnity. The other contentions appears to be that arbitration proceedings are already underway concerning the major variations in scope and the consequential payments, which form the core of the contractual financial structure of the Cochin Port Authority as Employer and pending such arbitration proceeding, any threatened action to terminate the contract would be unfair, thereby bypassing the adjudicatory process. The Cochin Authority however proceeded with the matter and terminated the contract on 10.12.2025. The grounds for termination are as follows.

- Non compliance of the Supplementary Agreement executed on 13.08.2025 in order to enable you cash flow by releasing an amount of Rs.6 crores on your request and non progress and non completion of the work as per the timelines indicated

- In spite of show cause notice dated 21.11.2025, you have stopped all works at site on 30-11-2005 an intimated wide your letter No.RCC-ACC/CPT/T15/T-1945/1004 dated 01-12-2025.

- The reasons for the delay in Implementation of the project submitted vide your letter No.ROC-ACC/CPT/T15/T- 1945/1065 dated 01-12-2025 are not satisfactory.

- You have not submitted an action plan to complete the project within the stipulated time requested vide CoPA's letter No.Dy. CE-II/T-1946/Goa ICT/2022-C/2188(w) dated 21.11.2025.

- The JV partner M/s. Asian Construction Company has not executed any work at site even though as per the JV agreement executed between M/s.RCC Infraventures Ltd. and M/s. Asian Construction Company the parties shall execute works jointly in the ratio of 51% and 49% and this is clear breach of Contract Agreement executed in between CoPA and the Contractors M/s.RCC-ACC (JV).

- The rectification in painting of steel structures, fabrication & erection of steel structures, flooring works etc. intimated to the contractors vide CoPA's letter No.Dy. CE-II/T-1946/Goa ICT/2022-C/2008(w) dated 23.09.2025 has not been carried out to the satisfaction of CoPA till date.

- Your aforesaid actions amount to breach of contract as per the terms and conditions of contract.

3. Instantly, during the pendency of the said proceeding, the petitioner/appellant invoked the Arbitration Clause before the Commercial Court, Ernakulam. But for reasons best known to the petitioner, the said proceeding was abruptly withdrawn. In the said proceeding initiated under Section 9 of the Arbitration and Conciliation Act, 1996 (‘the Act’ for short), one of the prayers was to maintain status quo as on the date of the said application. It has now been contended that the said application was ultimately withdrawn by reason of the fact that by the time the said matter came up for consideration before the Commercial Court, the order of termination had been issued. It has also now been argued that notwithstanding the existence of the Arb

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top