IN THE HIGH COURT OF JUDICATURE FOR RAJASTHAN AT JAIPUR
SUDESH BANSAL, J.
M/s Larsen and Toubro – Petitioner
Versus
Rajasthan Urban Sector Development Project – Respondent
S.B. Arbitration Application No. 7 of 2024
Decided On : 13-08-2024
Arbitration - Dispute Resolution - Arbitration and Conciliation Act, 1996 - Sections 11(6), 20.8, 20.3, 20.4, 20.6, 29A - The court interpreted the arbitration agreement and the necessity of pre-arbitration steps, ultimately allowing the appointment of a sole arbitrator despite objections regarding the process and limitations.
Fact of the Case:
The applicant, a contractor, sought the appointment of arbitrators under the Arbitration and Conciliation Act due to a dispute over escalated costs for additional work performed beyond the original contract terms, which the respondent refused to honor.
Finding of the Court:
The court found that the applicant had made sufficient attempts to resolve the dispute through the Dispute Adjudication Board (DAB) and that the objections raised by the respondent regarding pre-arbitration steps and limitations were not valid, allowing the arbitration application.
Issues: Whether the arbitration application was premature due to failure to appoint a DAB, whether the claim was barred by limitation, and whether the claim exceeded the arbitrable limit as per the contract.
Ratio Decidendi: The court held that the applicant's attempts to constitute a DAB were rejected by the respondent, making the arbitration application valid. The claim was not barred by limitation, and the amount claimed did not exceed the contractual limit for arbitration.
Result: The court allowed the arbitration application and appointed a sole arbitrator to adjudicate the dispute.
ORDER :
1. Heard learned counsel for both parties and perused the record placed before this Court.
2. Instant application has been filed by and on behalf of applicant M/s Larsen and Toubro Limited (for short “L&T Company) under Section 11(6) of the Arbitration and Conciliation Act, 1996 (for short “A&C Act) for appointment of Arbitrators to adjudicate the dispute that has arisen with respondent- Rajasthan Urban Sector Development Project (for short “RUIDP”) in connection with claiming new rate of variation in terms of clause 13.3 of GCC for excess work carried out beyond the original BOQ (Bills of Quantity) agreed under the tender contract dated 24.09.2015, between applicant and respondent-RUIDP pursuant to tender bid dated 23.04.2015. For ready reference Clause 13.3, as reproduced in the letter of applicant dated 24.05.2023 (Ann-P3) is being extracted hereunder:
Variation will be dealt as follows:
(i) for items having weightage of each item upto 0.1% of the Accepted Contract Amount, quantity variations will be paid on BOQ rate. No new rate will be given.
(ii) for items having weightage of each item more than 0.1% of the Accepted Contract Amount, quantity variation (plus or minus) upto 20% of the BOQ quantity will be paid on the BOQ rates. Quantity variation will generally be limited to 20% of BOQ quantity.
New rate for BOQ item for quantities more than 20% of BOQ quantity and non BOQ items and items of Major Maintenance:
*Each new rate or price shall be derived from any relevant rates or prices in the Contract, with reasonable adjustments. The adjustment in rates shall be based on RUIDP Schedule of Rates (SOR) 2013.
*No rates or prices are relevant for the derivation of a new rate or price from BOQ items, it shall be derived from the reasonable cost of executing the work (rate analysis on current market rate), together with profit of 20%. The rate analysis method will be based on RUIDP SOR analysis.
Until such time as an appropriate rate or price is agreed of determined, the Engineer shall determine a provisional rate or price for the purposes of Interim Payment Certificates as soon as the concerned work commences.”
3. The Arbitration Clause 20.8 contained in documents of tender contract dated 24.09.2015, arrived at between parties is being extracted hereunder:
Place of arbitration: Jaipur, State of Rajasthan India [....]
(b) Dispute shall be settled by sole or three Arbitrators. Dispute to be arbitrated upon shall be referred to a sole Arbitrator where the total value of claims does not exceed to Rs.10 millions. Beyond the claim limit of Rs. 10 Million, there shall be three arbitrators. For this purpose the Employer will make out a panel of Engineers with the requisite qualifications and professional experience relevant to the field to which the Contract relates. This panel, will be for serving or retired Engineers Departments of Government or of Public Sector. The Arbitrator/Arbitrators shall be appointed within a period of 30 days from the date of receipt of written notice/demand of appointment of Arbitrator by either party. In case of a single arbitrator, the will be of three Engineers, out of which the
Citibank Vs. TLC Marketing PLC
Demerara Distilleries (P) Ltd. Vs. Demerara Distillers Ltd. (2015) 13 SCC 610
M/s Govind Rubber Limited Vs. M/s Louids Dreyfus Commodities Asia (P) Ltd. (2015) 13 SCC 477
The main legal point established is that once an application is filed under Section 11(6) of the Arbitration and Conciliation Act 1996, the right of the opposite party to appoint the arbitrator cease....
An arbitrator may award escalated costs due to employer delay despite prohibitory clauses, reinforcing that delays affecting contractor performance can lead to compensatory claims.
The appointment of an Arbitrator should proceed if there is doubt about the subsistence of the disputes, and objections regarding claims should be left to be determined by the Arbitrator.
Arbitration Agreement – Award -Scope of interference by the courts into the award is quite limited. A court considering an application under Section 30 of the Act neither sits in appeal over an award....
The main legal point established in the judgment is that the limitation for filing an application under Section 11 of the Arbitration Act arises upon the failure to make the appointment of the arbitr....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.