IN THE HIGH COURT AT CALCUTTA
Shekhar B. Saraf, J.
B.K. Consortium Engineers Private Limited – Petitioner
Versus
Indian Institute Of Management, Calcutta – Respondent
AP/237/2021
Decided On : 19-01-2023
Arbitration & Conciliation Act, 1996 - Section 11, 21, 43(1) - Limitation Act, 1963 - Article 18, 137 - Appointment of sole arbitrator - Adjudicate disputes between parties - Petitioner praying for appointment of a sole arbitrator to adjudicate disputes which have arisen between parties - Held, Limitation bars a legal remedy and not a legal right, legal policy being to ensure that legal remedies are not available endlessly but only up-to a certain point in time - Needless to add however, that if respondents are conceding petitioner's claim itself, and are ready and willing to pay-up, such payment would not be illegal and there could not be any legal impediment in doing so - A party may concede a claim at any time; but cannot concede availability of a legal remedy beyond prescribed period of limitation - Court would like to put on record appreciation of lawyers appearing for both parties for their assiduous efforts in trying to convince court on behalf of their clients - Arguments made during course of hearing were both invasive and thought-provoking and have resulted in substantial enhancement in ken of knowledge of Court on subject - Reference to arbitration is hereby declined - AP dismissed.
JUDGMENT :
Shekhar B. Saraf, J.
1. The petitioner B. K. Consortium Engineers Private Limited (hereinafter referred to as the ‘BKC’) has filed this application under Section 11 of the Arbitration & Conciliation Act, 1996 (hereinafter referred to as ‘the Act’) praying for appointment of a sole arbitrator to adjudicate the disputes which have arisen between the parties.
2. The petitioner has challenged the appointment procedure of the arbitrator, provided in its contract with the respondent Indian Institute of Management, Calcutta (hereinafter referred to as the ‘IIMC’), which empowers the IIMC director to appoint a sole arbitrator for dispute resolution between the parties.
Facts
3. The factual matrix of the case is delineated below –
b. During the course of execution of the work, the respondent, from time to time, introduced additions to the scope of work, and as a result, the value of the contract stood revised to INR 80,23,73,260/-(Rupees Eighty Crores Twenty-Three Lakhs Seventy-Three Thousand Two Hundred Sixty Only). The petitioner sought extension from the respondent on the following grounds –
i. Delay in handing over clear work site; the piling work being done by another contractor was not completed before September 2009, and hence the clear site area could not be handed over to the petitioner till September 2009;
ii. Additions and alterations incorporated during the contract period;
iii. Various changes in the specifications were introduced;
iv. The execution of the project was suspended for a considerable period. The work resumed only on March 14, 2011.
In view of the aforesaid, the time for completion of work was extended by the respondent from time to time. The last of such extensions was granted till August 31, 2014. The work was completed in all aspects by August 31, 2014.
c. The respondent issued the final bill on March 11, 2016 and the petitioner accepted the same by way of a letter dated March 15, 2016, under the signature of two directors of the petitioner, namely C. Mozumder and U.S. Mozumder. The acceptance stated that “we accept the final bill and final settlement of all demands against the contract and we will not prefer any claim in future in this regard”. By way of another letter dated March 17, 2016, bearing the signature of B.K. Mozumder, Chairman and Managing Director of the respondent, the acceptance of the final bill was reiterated but in addition to this, a request for price escalation was made. Pursuant to the acceptance of the final bill, the final completion certificate was issued by the respondent on May 5, 2016. It is to be noted here that this was not the first time price escalation requests were submitted to the respondent.
d. On May 16, 2016, the petitioner sent another letter claiming price escalation. It was acknowledged in the said letter that the final bill against work done has been settled, and the retention money against the contract has been refunded by the respondent. However, the petitioner also stated, in the said letter, that its escalation claim under Clause 10(CC) of the contract has not been settled yet. Surprisingly, it also sought permission from the petitioner to invoke arbitration in terms of clause 25 of the said contract.
e. After a brief lull, letter dated August 25, 2017 was sent by the petitioner with respect to the earlie
New India Assurance Company Limited vs. Genus Power Infrastructure Limited
Secunderabad Cantonment Board vs. B. Ramachandraiah and Sons
The main legal point established in the judgment is that the limitation period for filing an application seeking appointment of an arbitrator under Section 11(6) of the Arbitration and Conciliation A....
The main legal point established in the judgment is that the limitation for filing an application under Section 11 of the Arbitration Act arises upon the failure to make the appointment of the arbitr....
(1) Period of limitation to file application under Section 11 of Arbitration and Conciliation Act, 1996 is 3 years’ from date of refusal to appoint Arbitrator, or on expiry of 30 days’, whichever is ....
Claims withdrawn do not reset the limitation period; the original cause of action's date governs the timeliness of arbitration requests.
The main legal point established in the judgment is the application of limitation laws and the categorization of cases as dead wood in determining the eligibility for appointment of an arbitrator.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.