IN THE HIGH COURT OF JUDICATURE FOR RAJASTHAN AT JODHPUR
SHREE CHANDRASHEKHAR, NUPUR BHATI, JJ.
State of Rajasthan – Appellant
Versus
M/s. Leeladhar Devkinandan – Respondent
D.B. Civil Misc. Appeal No. 761 of 2024
Decided on : 16-12-2024
(A) Arbitration and Conciliation Act, 1996 - Section 34 - Arbitral award - Challenge to the award made by the Arbitral Tribunal regarding escalation claims under Clause 45 of the Agreement - The court affirmed the award, noting that the Tribunal's interpretation of the escalation clause was plausible and not perverse - The court emphasized the limited grounds for interference with an Arbitral award under Section 34, maintaining the sanctity of arbitration as an alternative dispute resolution mechanism. (Paras 4, 5, 6, 10, 12)
(B) Arbitral Tribunal - Powers and limitations - The court reiterated that it cannot re-examine facts or substitute its opinion for that of the Tribunal, emphasizing the supervisory role of the court in arbitration matters. (Paras 4, 6, 10)
Facts of the case:
The appeal was filed by the State of Rajasthan against the Arbitral award favoring the claimant for escalation claims under Clause 45 of the Agreement for construction work, which was upheld by the Commercial Court.
Findings of Court:
The court found no grounds to interfere with the Arbitral award, affirming the Tribunal's decision on escalation claims and interest.
Issues: The main issues included the applicability of the escalation clause and the authority of the Arbitral Tribunal to interpret the Agreement.
Ratio Decidendi: The court ruled that the Arbitral Tribunal's interpretation of the escalation clause was reasonable and within its jurisdiction, and the court's role was limited to supervisory functions without re-examining the facts.
Result: Appeal dismissed.
ORDER :
Per, Shree Chandrashekhar, J.
This Civil Miscellaneous Appeal has been filed by the State of Rajasthan through its Executive Engineer to challenge the decision of the Commercial Court passed in Civil Misc. Case No.04/2023 by which the challenge laid to the Arbitral award dated 27th October 2009 has been dismissed.
2. Pursuant to the Agreement No.61/1995-96 executed between the parties for construction of the Police-line at Hanumangarh Jn., the subject work was allotted to M/s. Lila Dhar Devki Nandan (in short, claimant). As per the Agreement, the total contract value was for Rs.2,88,04,833/- and the work under the Agreement was to be completed within two years from issue of the work order no.8024 on 21st March 1996. There were certain disputes that arose between the parties regarding admissibility of escalation as per the stipulation under Clause 45 of the Agreement which could not be resolved and the matter finally came to the High Court in S.B. Micellaneous Arbitration Application No.45/2002 seeking appointment of Arbitrator. By an order dated 21st August 2003, the application filed by the claimant was allowed and the Arbitral Tribunal entered the reference on 24th February 2004. The claimant made claims under three separate heads viz. (i) for escalation to the tune of Rs.31,54,223/- (ii) interest for the period between 14th April 2001 to 23rd February 2004 @ 18% per annum over the claim for Rs.31,54,223/- and (iii) interest pendente-lite and future upto the date of payment on Rs.31,54,223/- @ 18% per annum from 24th February 2004; alongwith the tentative cost of arbitration proceedings at Rs.15,000/-. The Arbitral Tribunal held that the claimant is entitled for the sum of Rs.31,54,223/-and granted interest @ 15% per annum both for the period between 14th April 2001 to 23rd February 2004 and interest pendente-lite.
3. The Arbitral Tribunal considered the claim pressed by the claimant for escalation in the following manner:-
In the written arguments the respondent has stated that according to the Circular no. D-209 dated 19.03.1998 of the Chief Engineer PWD, Rajasthan, Jaipur, the claimant is not entitled to receive from the respondent a sum of Rs. 31,54,223/ for price escalation because the said Circular is issued on 19.03.1998 whereas the agreement was executed in the year 1995-96.
In this regard I find that the claimant has not demanded the price escalation amount on the basis of the Circular dated 19.03.1998 (Ex.-C/9). On the other hand the price escalation is demanded by the claimant under clause 45 of the agreement, the calculation, formula, price index etc. of which are not disputed by the respondent.
Further I have also consulted the said Circular and I find that the Circular is only the guidelines for deciding the cases of interim/final extension in the completion period which is the internal matter of the department with a view to adopt a uniform policy and the amount of the price escalation should be paid as per the clause 45 of the agreement.
In the written arguments the respondent has further stated that escalation after the stipulated date of the completion is not admissible because the time extension up to the actual date of completion has been sanctioned with 1/2% compensation, vide letter no. F.1(1)PW/AS/96 dated 29.11.2000 of the Additional Secretary, PWD Rajasthan, Jaipur.
In the written arguments the respondent has further argued that the claimant cannot raise the contention that the Additional Secretary is not the authorised person to levy the compensation under clause 2 of the agreement and at the same relies upon the time extension made by the
Food Corporation of India v. Chandu Construction & Anr.: (2007) 4 SCC 697
U.P. SEB v. Searsole Chemicals Ltd.
McDermott International Inc. v. Burn Standard Co. Ltd.” (2006) 11 SCC 181
Delhi Airport Metro Express (P) Ltd. v. DMRC” (2022) 9 SCC 286
The court upheld the Arbitral Tribunal's award on escalation claims, affirming the limited grounds for judicial interference under Section 34 of the Arbitration and Conciliation Act, 1996.
An arbitrator may award escalated costs due to employer delay despite prohibitory clauses, reinforcing that delays affecting contractor performance can lead to compensatory claims.
A deleted contractual clause cannot be automatically revived upon extension of the contract; explicit agreement is required for revival.
The appellate jurisdiction under section 37 is limited to the grounds prescribed under section 34. Courts cannot re-appreciate evidence or substitute their views for that of the arbitrator, provided ....
The judgment emphasizes the limited scope of interference with arbitral awards and the principle that courts should not interfere with arbitral awards unless there is a patent illegality or violation....
An arbitrator cannot exceed jurisdiction by awarding claims not supported by written approval as mandated by the contract, rendering the award illegal.
An arbitrator cannot exceed contractual terms; applying external recommendation outside the agreed terms constitutes a jurisdictional error and is subject to judicial review under Sections 34 and 37 ....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.