IN THE HIGH COURT OF JHARKHAND AT RANCHI
ANUBHA RAWAT CHOUDHARY, J.
N.R. Construction Private Limited – Appellant
Versus
The State of Jharkhand – Respondent
Arbitration Appeal No. 17 of 2009
Decided On : 18-12-2023
JUDGMENT :
ANUBHA RAWAT CHOUDHARY, J.
1. Heard the learned counsels for the parties.
2. This appeal has been filed against the order dated 29.08.2009 passed under section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the Act of 1996) by learned Subordinate Judge-I at Ranchi in Misc. Case No. 57 of 2007 whereby an award dated 17.07.2007 made and published by the sole Arbitrator has been set-aside.
Foundational Facts.
3. The appellant herein was the claimant before the learned Arbitrator, who was allotted the work for construction of minor bridge on N.H. 23 in K.M. 49 pertaining to National Highway Road Construction Department, Dhanbad Division No. 2 for which an agreement was executed between the parties on 04.03.1992, containing an arbitration clause, for the total value of Rs. 34,92,803/- which was to be completed by 03.09.1993.
4. As per the appellant, additional work was done which was necessary for completion of the bridge and the inflow of traffic. The appellant, on the direction of the Engineer In-charge and assurance of extra payment, executed certain additional and extra work which was not provided in the item of work in the agreement. The work as per the agreement and also the additional work was completed on 31.08.2001 i.e. within the extended time.
5. The claim of the appellant was first placed before the Junior Engineer who prepared a report dated 16.06.2003. Thereafter, vide letter no. 7(A) dated 17.06.2003, the Executive Engineer recommended and placed the matter before the Superintending Engineer for his approval and payment. The Superintending Engineer sent a letter to the Chief Engineer on 22.09.2003 stating that the extra work done by the appellant was not included in the item of work in the agreement and made the recommendation for sanction of funds. However, no payment was made to the appellant.
6. When all attempts to persuade the authorities to make payment failed and having found no other alternative to recover the legitimate dues, the appellant filed a petition under section 11(6) of the Act of 1996 before this Court bearing Arbitration Application No. 28 of 2004 which was disposed of vide order dated 21.06.2006 wherein the arbitration was referred to the sole Arbitrator and direction was given to the learned Arbitrator to enter into reference and to pass an award within a period of four months from the date of receipt of the order, which was received on 25.07.2006. However, the award was pronounced on 17.07.2007.
7. There was a total of four claims and claim no. 1 was divided into 5 sub-claims. The summary of the award in connection with the claims is as under:
| Claim No. | Award |
| Claim No. 1. |
|
| Payment of the due amount of Rs. 55,69,577/- on account of additional work done beyond the agreement value. The total amount of Rs. 55,69,577/- was claimed under the following sub-heads: | Awarded in full Rs. 55,69,577/- |
| (I) Rs. 6,98,800/- Additional work actually done concerning deck slab casting: | |
| (a) Rs. 92,000/- for deck slab. | |
| (b) Rs. 6,06,799.92/- for RCC work in beams and superstructure. | |
| (II) Rs. 3,47,595/- Additional work actually done with respect to staging and shuttering of H.L. Bridge. | |
| (III) Rs. 3,49,280.00 - Overhead expenses due to prolongation of 9 years on account of departmental failure i.e. non availability of departmental cement and steel. Overhead expenses have been claimed @10% of the agreement value. | |
| (IV) Rs. 3,49,280.00 - Turnover loss due to delay - As the work continued for a much longer period than specified in the agreement, Turnover losses have been claimed @ 10% of the agreement value. | |
| (V) Rs. 38,24,621.14 - Escalation. Extra cost on procurement of materials by way of escalation on the increased value of inputs and labour as the agreement was continued up to 2001 whereas t | |
Chandigarh Construction Company Private Limited vs. State of Punjab and Another
DDA vs. R.S. Sharma and Co. (2008) 13 SCC 80
Jayesh H. Pandya and Another vs. Subhtex India Limited and Others
Kuldeep Singh vs. Commissioner of Police
K.N. Sathyapalan vs. State of Kerala and Another
Maharashtra State Electricity Distribution Company Limited vs. M/s. Datar Switchgear Ltd. and Others
NBCC Limited vs. J.G. Engineering Private Limited
ONGC Limited vs. Saw Pipes Limited
ONGC vs. Western Geco International Ltd. (2014) 9 SCC 263
Rajasthan State Mines and Minerals Limited vs. Eastern Engineering Enterprises and Another
Ssangyong Engineering and Construction Company Ltd. vs. National Highway Authority of India
Venkatesh Construction Company vs. Karnataka Vidyuth Karkhane Limited
An arbitrator cannot exceed jurisdiction by awarding claims not supported by written approval as mandated by the contract, rendering the award illegal.
An arbitrator may award escalated costs due to employer delay despite prohibitory clauses, reinforcing that delays affecting contractor performance can lead to compensatory claims.
An arbitrator's award may be upheld if it conforms to contract terms, despite challenges regarding procedural compliance or interpretation, provided it does not contravene public policy.
The court confirmed the validity of the Arbitrator's findings regarding excess work claims and the correct application of interest, highlighting that overlapping interest claims were erroneous.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.