IN THE HIGH COURT OF HIMACHAL PRADESH, SHIMLA
SANDEEP SHARMA, J.
State of Himachal Pradesh and another – Appellant
Versus
M/s SAB Industries Ltd. – Respondent
Arb. Cases Nos. 92 of 2011 & 6 of 2012
Decided on : 05-07-2023
Arbitration and Conciliation Act, 1996 – Section 34, 31(7), (7)(b) - Tender - No payment was made - Arbitral award - Challenge has been laid to Award passed by arbitral tribunal consisting of sole arbitrator Justice whereby learned Arbitrator, while allowing claim set up by M/s SAB Industries, petitioner in Arb. Case awarded Rs.1,40,36,158/- in its favour and against State of Himachal Pradesh – Post award interest could be awarded only on principal amount and not on post award interest, as such, claimant is entitled to compounding interest as claimed by it in objections. (Para 55)
Finding of the Court :
Impugned award clearly reveals that learned Arbitrator having taken note of judgment rendered by Hon'ble Apex Court in S.L. Arora supra, held that compounding interest can be awarded only if there is specific contract and authority under statute for compounding interest, however, in view of Hyder Consulting, supra, award to this extent is not sustainable - There is no dispute that Hon'ble Apex Court, while passing judgment in Hyder Consulting supra, held its finding in S.L. Arora, supra to effect that post award interest could be awarded only on principal amount and not on post award interest, to be incorrect, as such, claimant is entitled to compounding interest as claimed by it in objections - Impugned Award is modified to extent that claimant shall be entitled to interest at rate of 18% per annum.
Result: Arb allowed.
JUDGMENT :
Sandeep Sharma, J.
By way of above captioned arbitration cases filed under S.34 of Arbitration and Conciliation Act (hereinafter, ‘Act’), challenge has been laid to Award dated 19.8.2011 passed by arbitral tribunal consisting of sole arbitrator Justice Vijender Jain (retired), whereby learned Arbitrator, while allowing the claim set up by M/s SAB Industries, petitioner in Arb. Case No. 6 of 2012 (hereinafter referred to as, ‘claimant’) awarded Rs.1,40,36,158/- in its favour and against the State of Himachal Pradesh, petitioner in Arb. Case No. 92 of 2011 (hereinafter referred to as, ‘employer’).
2. For having bird’s eye view of the matter, facts shorn of unnecessary details, necessary for the adjudication of the case at hand are that an item rate tender for deposit work for construction of Himachal Pradesh Dental College, Shimla (Building portion Block-A & B including water supply and SI, external water supply, sewerage and development of site) was approved and awarded in favour of M/s SAB Industries Ltd. for total amount of Rs.4,94,85,169/- (which was 166.13% above total amount put to tender) with deviation limit of 30% as per Clause 2(e)(ii) of contract agreement i.e. amount of Rs.1,48,45,550/- and stipulated period of completion of work as per award letter dated 23.8.1996 was two years i.e. from 8.9.1996 to 7.9.1998. The contract period was admittedly extended by the petitioners on the requests made by claimant from time to time by granting six authorized time extensions. The work was completed on 30.6.2000. There was no dispute between the parties that upto 46th running bill, total amount to the tune of Rs.5,39,07,701/- stood paid to claimant by the department. Thereafter, in the 47th bill (final bill) an amount of Rs.32,54,503/- was claimed by the claimant for substituted and extra items from the employer. Since no payment was made by the employer, the claimant raised dispute in terms of Clause 25 of the agreement for Rs.2,72,90,155/- under following heads:
(b) In case these claims are not proved in their entirety, what claim amount the claimant can be held entitled which may be just and equitable?
(c) Whether the extension of contract period was due to default of the respondent on account of the acts of omission and commission on the part of the concerned employees and to what effect?
(d) Whether the claimant company is entitled to any amount of claim on account of deviations, escalations, substituted items and extra items and how much
(e) Whether the claimant is entitled to an interest and if so from which date and at what rate?
(f) Whether the claim of the petitioner company is time barred?
(g) Whether the claimant is stopped from making the claim in question.
3. Earlier Superintending Engineer (Arbitration Cell) was appointed as arbitrator on 13.3.2002 and he entered into reference on 16.2.2002, however, later said post was abolished and as such, this Court vide order dated 6.3.2003 appointed late Justice Roop Singh Thakur, as an Arbitrator but due to untimely death of said arbitrator, this court vide order dated 31.10.2008, appointed Justice Virender Jain, former Chief Justice, Punjab and Haryana High Court as an arbitrator. Since pleadings were completed during the tenure of late Justice Roop Singh Thakur, parties agreed to continue with arbitration proceedings, from the stage, left by earlier arbitrator, who entered into reference after being appointed as an arbitrator.
4. The claimant claimed following amounts in its claim filed before the Arbitrator:
B. Release of security Rs.50,000/-
C. Payment due against loss caused to the claimant by the Department by obstructing claimant from executing and completing the work of total estimated cost of Rs.4,94,85,169/- till original time limit i.e. u
Central Bank of India v. Ravindra and Others
Dyna Technologies (P) Ltd. v. Crompton Greaves Ltd. (2019) 20 SCC 1
Food Corporation of India & Ors. v. Vikas Majdoor Kamdar Sahkari Mangli Ltd. (2007) 13 SCC 544
G.J. Fernandez v. State of Karnataka & Ors 1990 (2) SCC 488
Hyder Consulting (UK) Limited v. Governor
McDermott International INC v. Burn Standard Co. Ltd. and Others
Nasiruddin v. Sita Ram Agarwal
Oil and Natural Gas Commission v. M.C. Clelland Engineers S.A.
ONGC Ltd. v. Saw Pipes Ltd. (2003) 5 SCC 705
Oil & Natural Gas Corporation Limited v. Western Geco International Limited (2014) 9 SCC 263
Pakala Narayana Swami v. Emperor
T.N. State Electricity Board v. Central Electricity Regulatory Commission
Uttar Pradesh Cooperative Federation Limited v. Three Circles
Uhl Power Company Limited v. State of Himachal Pradesh (2022) 4 SCC 116
Section 31(7)(a) of Act deals with grant of pre-award interest.
Point of Law : Award could also be set aside if it is so unfair and unreasonable that it shocks the conscience of the court. Such award is opposed to public policy and is required to be adjudged void....
The Court held that the learned Arbitrator had erred in decreeing the award with respect to the rate of interest, and hence, the Award qua issue no. 20 with regards to the rate of interest is liable ....
An arbitral award can only be set aside under Section 34 of the Arbitration and Conciliation Act, 1996 if the appellant establishes that the award is in conflict with the public policy of India, is p....
The main legal point established in the judgment is the limited scope for interference with arbitral awards under the Arbitration and Conciliation Act, 1996, and the discretion of the Arbitrator in a....
(1) Appeal against modified arbitral award – Merits of award are only to be gone into, if award is demonstrated to be contrary to public policy of India.(2) Arbitral proceedings are per se not compar....
The court confirmed the validity of the Arbitrator's findings regarding excess work claims and the correct application of interest, highlighting that overlapping interest claims were erroneous.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.