SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2024 Supreme(HP) 31

IN THE HIGH COURT OF HIMACHAL PRADESH AT SHIMLA
RAKESH KAINTHLA, J.
State of H.P. and Others – Petitioners
Versus
Ashok Kumar Thakur – Respondent
Arbitration Case No. 10 of 2013
Decided On : 10-05-2024

Advocates:
Advocate Appeared:
For the Petitioner: Seema Sharma.
For the Respondent: Sumeet Raj Sharma.

IMPORTANT POINT
The main legal point established in the judgment is that an award passed by the Arbitrator must be based on evidence and should not ignore vital documents. The court emphasized the importance of evidence and the need for the Arbitrator to consider all relevant documents in reaching a decision.

Headnote:

Arbitration - NH-88 Improvement/Up-gradation - Arbitration and Conciliation Act, Section 34 - The court discussed the legal framework under Section 34 of the Arbitration and Conciliation Act and emphasized that it will not sit in appeal over the decision of the Arbitrator unless the award shocks the conscience of the Court. The court analyzed the evidence presented and found that the award passed by the Arbitrator was based on no evidence and ignored vital documents, thus suffering from perversity as laid down by the Hon’ble Supreme Court. The court allowed the petition and set aside the award.

Fact of the Case:

The claimant was awarded a contract for the improvement/up-gradation of NH-88. Disputes arose regarding payment for additional work, correction of road undulation, and loss due to delayed payment. The matter was referred to arbitration, and the Arbitrator partly allowed the claimant's petition. The claimant filed a petition under Section 34 of the Arbitration and Conciliation Act, asserting that the award was against the Public Policy of India and not sustainable.

Finding of the Court:

The court found that the award passed by the Arbitrator was based on no evidence and ignored vital documents, thus suffering from perversity as laid down by the Hon’ble Supreme Court. The court allowed the petition and set aside the award.

Issues: The issues revolved around the payment for additional work, correction of road undulation, and loss due to delayed payment. The claimant sought payment for the final bill, correction of undulation, application of extra bitumen, loss due to idle machinery, and compensation for prolongation of work.

Ratio Decidendi: The court emphasized that the award passed by the Arbitrator must be based on evidence and should not ignore vital documents. It discussed the legal framework under Section 34 of the Arbitration and Conciliation Act and highlighted the parameters for adjudicating a petition under this section.

Final Decision: The court allowed the petition and set aside the award dated 11.9.2012 passed by the learned Arbitrator.

 

1. The present petition is directed against the award dated 11.9.2012 vide which the claim petition filed by the respondent (claimant before the learned Arbitrator) was partly allowed. (Parties shall hereinafter referred to in the same manner as they were arrayed before the learned Arbitrator for convenience).

2. Briefly stated, the facts giving rise to the present petition are that the work for improvement/up-gradation of NH-88 i.e. Shimla - Bilaspur - Hamirpur - Nadaun - Ranital - Kangra and termination near Bhawan National Highway-20, Km. 95/0 to 105/0 was awarded by the respondents to the claimant on 7.12.2001. The work was to be completed within six months from the 15th day of the issue of the work order. The parties entered into a standard form of contract. The total amount of the award was Rs. 1,27,75,363/- . The claimant found that bitumen at 2.50 kg for applying a thick coat of 50 mm was not given in the schedule of quantity. He requested the respondents to approve it and consider it an extra item in view of road width and the frequency of the usage of the road, which would not allow semi-dense bituminous concrete (SDBC) to settle down. He told the Executive Engineer that the slushy portion of the road required treatment before execution of the work and asked the respondents to lay Kharanja Soling before laying bitumen and SDBC and include it as an item. The respondents failed to pay for the work resulting in the loss to the claimant. The road was full of undulation and the claimant asked for its rectification. He sent the final bill but the payment was not made. This led to the dispute between the parties and the matter was referred to the learned Arbitrator.

3. The claimant filed a statement of claim seeking payment of the final bill, payment towards correction of undulation in the road, correction of slushy portion by laying tack coat and application of another layer of bitumen, application of one layer between bitumen and SDBC, loss for late payment resulting into idle machinery, payment for prolongation of the work, interest and the cost.

4. The respondents filed a reply admitting that the work was awarded to the claimant. The claimant asked for the release of his final payment after seven years of the completion of the work. The matter was processed and it was found that the payment of the final bill was not made and the amount of Rs. 1,05,440/- was yet to be paid. National Highway Division was created in the year 2004 and no record was transferred to the division. The respondents came to know of the liability after receiving a letter from the claimant. A meeting was held with the claimant to settle the dispute; however, the claimant approached this Court for the appointment of an Arbitrator. The cost of the work inflated from Rs. 1,27,75,363/- to Rs. 1,43,18,996/- which is required to be approved. The payment would be made after the approval of the competent authority. The statement of claim was denied. It was asserted that work was executed as per the terms and conditions of the agreement. The work was entered in the Measurement Book and the payment of Rs. 1,42,13,556/- was made. No entry was recorded regarding the rectification of undulation and the claimant was not entitled to the payment of this amount. As per the record, 28 to 30 Bitumen Macadam (BM) was laid on 24.10.2002 and SDBC was laid on 25.10.2002. The claimant has caused the delay. The payment was made immediately after the receipt of the bills. The claimant failed to start the work in time despite repeated requests. There was no provision for providing 24% interest or the cost of arbitration. A counterclaim for Rs. 2,000/- for non-requirement of technical staff, cost of arbitration and interest was made.

5. The parties filed various documents in support of their claim and defence. Learned Arbitrator held that the final payment of Rs. 95,845/- was to be made to the claimant which was accepted by him. The security deposit of Rs. 4,00,167/- was also pai

          Click Here to Read the rest of this document
          1
          2
          3
          4
          5
          6
          7
          8
          9
          10
          11
          SupremeToday Portrait Ad
          supreme today icon
          logo-black

          An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

          Please visit our Training & Support
          Center or Contact Us for assistance

          qr

          Scan Me!

          India’s Legal research and Law Firm App, Download now!

          For Daily Legal Updates, Join us on :

          whatsapp-icon Back to top