SUPREME COURT OF INDIA
S. RAVINDRA BHAT, DIPANKAR DATTA, JJ.
M/s Unibros - Appellant
Versus
All India Radio - Respondent
Civil Appeal No. 6895 of 2023 [Arising out of SLP (Civil) No. 8791 of 2020]
Decided On : 19-10-2023
(A) Arbitration and Conciliation Act, 1996 – Sections 34 and 37 – Setting aside arbitral award – Claim for damages, whether general or special, cannot as a matter of course result in an award without proof of claimant having suffered injury – Appellant's claim for loss of profit is primarily based on the grounds that appellant, having been retained longer than period stipulated in contract and its resources being blocked for execution of work relatable to contract in question, it could have taken up any other work order and earned profit elsewhere – Second Award fares no better than First Award, for, it is equally in conflict with public policy of India – Factors which weighed in Arbitrator’s mind in first round and second round are one and same – Judicial decision of a superior court, which is binding on an inferior court, has to be accepted with grace by inferior court notwithstanding that decision of superior court may not be palatable to inferior court – Any award of an Arbitrator or a Tribunal that seeks to overreach a binding judicial decision, does conflict with fundamental public policy and cannot sustain – Arbitral award in question, is patently illegal in that it is based on no evidence and is outrightly perverse – Appeal dismissed. (Paras 8, 13, 20 and 21)
(B) Judicial Discipline – Binding Precedent – Judicial decision of a superior court, which is binding on an inferior court, has to be accepted with grace by inferior court notwithstanding that decision of superior court may not be palatable to inferior court – This principle, ex proprio vigore, would be applicable to an Arbitrator and a multi-member arbitral tribunal as well, particularly when it is faced with a judicial decision (either under Section 34 or Section 37 of Arbitration and Conciliation Act, 1996) ordering a limited remand. (Para 14)
(C) Arbitration and Conciliation Act, 1996 – Sections 34 and 37 – Setting aside arbitral award – Hudson’s formula – For claims related to loss of profit, profitability or opportunities to succeed, one would be required to establish four conditions: first, there was delay in completion of contract; second, such delay is not attributable to claimant; third, claimant’s status as an established contractor, handling substantial projects; and fourth, credible evidence to substantiate claim of loss of profitability. (Paras 18 and 19)
Facts of the case:
Appeal is directed towards dismissal of appellant's claim for compensation relating to loss of profits (Claim No. 12). Appellant's claim for loss of profit stems from delay attributed to respondent in completing project. Loss of profit sought in present case is primarily based on the grounds that appellant, having been retained longer than period stipulated in contract and its resources being blocked for execution of work relatable to contract in question, it could have taken up any other work order and earned profit elsewhere.
Findings of Court:
Factors which weighed in Arbitrator’s mind in first round and second round are one and the same. To avoid any charge of being branded as a mirror image of First Award insofar as Claim No.12 is concerned, Second Award appears to have been expressed in language and form different from earlier one without, however, there being any change in substance.
Result : Appeal dismissed.
JUDGMENT :
Dipankar Datta, J.
1. Leave granted.
2. This appeal, at the instance of M/s Unibros (“appellant”, hereafter), registers a challenge to the judgment and order dated 9th December, 2019 in FAO (OS) 229/2010 passed by the High Court of Delhi (“High Court”, hereafter) dismissing an appeal carried by the appellant under section 37 of the Arbitration and Conciliation Act, 1996 (“the Act”, hereafter). Vide the impugned judgment, a Division Bench affirmed the judgment and order of a learned Single Judge dated 25th February, 2010 whereby an objection of the All India Radio (“respondent”, hereafter) under section 34 of the Act was allowed resulting in setting aside of an arbitral Award dated 15th July, 2002 to the extent it awarded loss of profit to the appellant.
3. The relevant facts, discerned from the records, reveal that the appellant was awarded a work contract by the respondent to carry out construction of Delhi Doordarshan Bhawan, Mandi House, Phase-II, New Delhi. The work was scheduled to commence on 12th April, 1990 and reach completion on 11th April, 1991; however, it suffered a delay of roughly 42½ months and was finally completed on 30th October, 1994. Disputes and differences emerged between the parties owing to such delay, which were subsequently referred to an Arbitrator (“Arbitrator”, hereafter) for resolution.
4. The trajectory of the case, leading to the present stage, is set out hereunder :
(a) Arbitration proceedings having been initiated, the Arbitrator vide award dated 11th February, 1999 (“First Award”, hereafter) decided various claims and counter-claims filed by the parties. Claim Nos. 10, 11, and 12 were collectively addressed under section 73 of the Indian Contract Act, 1872 (“Contract Act”), as they all centred around the issue of delay and the resultant losses. Vide Claim No. 10, the appellant claimed a sum of Rs. 50,00,000.00 (Rupees fifty lakh) owing to the marked escalation in prices/rates for the work executed beyond the stipulated contract period. Vide Claim No. 11, the appellant implored the Arbitrator to award Rs. 41,00,000.00 (Rupees forty-one lakh) to cover substantial expenses associated with the establishment, machinery, centring/shuttering, and other vital aspects of the project. Additionally, vide Claim No. 12, the appellant urged that a compensation of Rs. 2,00,00,000.00 (Rupees two crore) be granted as redress for the loss of profit endured due to the appellant’s protracted retention on the contract without any corresponding increase in monetary benefits earned. Despite the Arbitrator's rejection of Claim Nos. 10 and 11, the appellant was awarded a sum of Rs. 1,44,83,830 (Rupees one crore, forty-four lakh, eighty-three thousand, eight hundred and thirty) towards Claim No. 12, along with an interest of 18% per annum under Claim No. 13 from 12th May, 1997 to the date of actual payment. The Arbitrator supported this award based on the undisputed fact that the delay in completing the work beyond the stipulated contract period was caused by the respondent and against the stipulated contract period of 12 months, the appellant was retained by the respondent for the execution of the work for an additional period of 3½ years leading to loss of the appellant’s profit earning capacity during the said extended period. The loss of profit was worked out based on a profit allowance of 7½% per year, which the Arbitrator held to be reasonable in a civil works contract. Applying Hudson’s formula, the Arbitrator arrived at the final compensation for loss of profit, the computation of which is outlined below :
| Period of delay | 42.5 months |
| Contract value | Rs.5,45,27,386.00 |
| Contract period | 12 months |
| Contractor’s profit (7 ½ % per year) | Rs.40,89,554.00 |
| Contractor’s expected profit per month | Rs.3,40,796.00 |
| The total amount of loss of profit | The total period of delay x Cont |
Associated Builders vs. Delhi Development Authority
Bharat Cooking Coal Limited vs. L.K. Ahuja
M/s AT Brij Paul Singh & Ors. vs. State of Gujarat
McDermott International Inc. vs. Burn Standard Co. Ltd. and Ors.
(1) Setting aside arbitral award – Claim for damages, whether general or special, cannot as a matter of course result in an award without proof of claimant having suffered injury.(2) Binding Preceden....
An arbitrator's award can be set aside if it is based on a fundamental breach of contract that ignores material clauses of the agreement, leading to a finding that is perverse and constitutes a paten....
Clauses in contracts that prohibit claims for damages are against public policy and void under Section 23 of the Indian Contract Act, 1872, as they undermine the sanctity of contracts.
The court upheld the arbitral award for loss of profits, affirming that failure to notify a contract's termination constituted a material breach, justifying compensation under the Indian Contract Act....
The court set aside the arbitral award due to the arbitrator's arbitrary findings regarding contract termination and lack of evidence supporting claims, establishing grounds for patent illegality und....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.