SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(HP) 432

IN THE HIGH COURT OF HIMACHAL PRADESH, SHIMLA 
JYOTSNA REWAL DUA, J.
Union of India & Anr. - Appellants
Versus
M/s B.S. Ranbir and Co. - Respondent
Arbitration Appeal No.114 of 2024
Decided on : 06-05-2025

Advocates:
Advocate Appeared:
For the Appellants :Mr. Balram Sharma, Deputy Solicitor General of India with Mr. Rajiv Sharma, Advocate.
For the Respondent:Mr. Shubham Sood, Advocate.

The court upheld the arbitral award, affirming that contractual obligations prevail over departmental instructions, and emphasized the limited scope of appellate review under the Arbitration and Conciliation Act.

Headnote:

(A) Arbitration and Conciliation Act, 1996 - Sections 34 and 37 - Arbitral award upheld by District Judge - Objections against award dismissed - Appellants challenged the award claiming denial of escalation payment based on departmental instructions - Court affirmed that contractual obligations prevail over departmental instructions. (Paras 1, 2, 4(i)(a), 4(i)(b))

(B) Scope of Appellate Review - The jurisdiction under Sections 34 and 37 is narrow; courts should not interfere with arbitral awards unless there is a patent illegality or the award is perverse. (Paras 4(i)(a), 4(i)(b))

Facts of the case:
A contract for accommodation provision was executed for Rs.3,94,96,923.36/- with a stipulated completion of 18 months. Respondent No.1 claimed escalation payments which were denied based on departmental instructions. The Arbitrator ruled in favor of Respondent No.1, awarding the claimed amounts. (Paras 2(i), 2(v))

Findings of Court:
The Arbitrator's award was justified as the denial of payment was contrary to the contract. The court upheld the award and the interest on delayed payments. (Paras 4(ii))

Issues: Whether departmental instructions can override contractual obligations and the scope of appellate review under Sections 34 and 37 of the Act. (Paras 4(i)(a), 4(i)(b))

Ratio Decidendi: The court emphasized that contractual provisions must be adhered to, and the scope of interference with arbitral awards is limited, focusing on patent illegality. (Paras 4(i)(a), 4(i)(b))

Result: Appeal dismissed.

JUDGMENT :

Jyotsna Rewal Dua, J.

Arbitral award passed in favour of respondent No.1 on 15.10.2015 was upheld by the learned District Judge, Kangra at Dharamshala on 08.12.2023. Objections preferred against the award under Section of 34 of the Arbitration and Conciliation Act, 1996 (in short ‘the Act’) were dismissed. Feeling aggrieved, the appellants have now taken recourse to Section 37 of the Act and have assailed the order passed by the learned District Judge Kangra at Dharamshala dated08.12.2023 and Arbitral Award dated 15.10.2015, whereunder, claim preferred by respondent No.1 was allowed to the extent indicated therein.

2. The case

2(i) A Contract agreement was executed between the appellants and respondent No.1 for ‘Provision of OTM accommodation for Postal Unit at Palampur, District Kangra’ for an amount of Rs.3,94,96,923.36/-. Stipulated period of completion of work was 18 months with given date of completion as 16.07.2015. The work extended beyond the period of 18 months. Clause No.48 of the Contract Agreement provided mechanism of reimbursement/refund on variation in prices. Respondent No.1 claimed escalation amounting to Rs. 2,25,498.00/- in Running Account Receipt (RAR) dated 03.03.2014. Officials of the appellants submitted it to the Audit Branch. The concerned authority disallowed payment of escalation on the ground that stipulated period of completion of the contract was 18 months and as per the Government policy, provision for escalation is not to be included in the tenders having completion period of 24 months or less. The escalation was denied to respondent No.1. The dispute, ultimately reached the learned Arbitrator. Respondent No.1 submitted that both the parties were bound by the contract provisions and not by the departmental instructions; That it was obligatory on part of the appellants to make payment of escalation as per the provisions of the contract; That he had quoted rates considering contract provisions including provisions for escalation.

2(ii) Respondent No.1 also submitted that he had continued to claim escalation payment in subsequent RARs also. His legitimate payment of escalation was denied in the subsequent RARs as well. The Physical Date of Completion of the project was 36 months and hence, inclusion of escalation clause was in order. Despite respondent No.1’s representation, escalation was not paid to him. The claim filed by respondent No.1 gave details of different RARs for different amounts claimed by him, which were not paid to him on due dates on account of alleged departmental instructions.

2(iii) From the award, it appears that during hearing of the claim before the learned Arbitrator, appellants agreed to the contention of respondent No.1 that it was incumbent upon both the parties to abide by the contractual obligations and not the departmental instructions; That the departmental instructions would not override the contractual provisions agreed to between the parties. The appellants also furnished calculations in terms of Clause 48 for the escalation admissible to respondent No.1.

2(iv) Learned Arbitrator held that the contract had stipulated completion period of 18 months from the date of commencement. As per the contract, variations in price was to be reimbursed/refunded on quarterly bases, based on formula commencing from the date of receipt of quoted tenders and the claim preferred on account of work done by respondent No.1 at an interval of not less than 30 days. Condition No.64, pertaining to advances on account, was also considered, which stipulated that RARs payment so made shall be regarded as payments by way of advance for work done and material delivered at site. The advances were to be adjusted against the final bills submitted by respondent No.1 on completion of work.

2(v) Learned Arbitrator further held that contract is a legal document within the ambit of Indian Contract Act. It was obligatory on both the parties to follow it holistically without any deviation. Disallowanc

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top