SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Raj) 1973

HIGH COURT OF JUDICATURE FOR RAJASTHAN BENCH AT JAIPUR
MANEESH SHARMA, J.
 
State of Rajasthan through the Executive Engineer, Irrigation Department, Division Alwar, Alwar. - Appellant
Versus
M/s Devendra Pal Singh r/o 10, Poultry Estate, Agra Road, Jaipur. – Respondent 
S.B. Civil Miscellaneous Appeal No. 6760, 6763 of 2011
Decided on : 04-07-2025
 

Advocates:
Advocate Appeared:
For the Appellant : Mr. Gopal Krishan Sharma, AGC
For the Respondent: Mr. Devi Dutta Sharma Mr. Vishnu Kumar

Under the Arbitration and Conciliation Act, the scope for setting aside an arbitral award under Sections 34 and 37 is limited, emphasizing the need for substantial legal grounds and deference to arbitral decisions.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Sections 34 and 37 - Appeal against the dismissal of an application to set aside arbitral awards - The learned District and Sessions Judge, Alwar confirmed the arbitral awards, which the appellant challenged under Section 34 for alleged lack of reasoning by the arbitrator - Court clarified the limited scope of appeal under Section 37, prohibiting re-examination of factual issues unless substantial legal infirmities exist. (Paras 1 - 4, 12 - 24)

(B) Jurisdictional limits of courts under the Arbitration Act - The scope of interference under Section 37 is restricted, and arbitral awards can only be set aside on the grounds provided in Section 34. Appeals are subjected to narrow legal scrutiny and should uphold the finality of arbitral awards unless they contravene public policy or exhibit patent illegality. (Paras 22, 30, 31)

Facts of the case:
The appeals arise from the dismissal of the appellant's applications seeking to set aside arbitral awards of Rs. 2,63,137/- and Rs. 3,16,860/- made in favor of the respondent for construction disputes, where the arbitrator had made detailed findings in favor of the claimant. (Paras 5, 10, 14)

Findings of Court:
The court upheld the arbitrator's awards stating that the appellant failed to demonstrate any legal infirmities or reasons to contest the arbitrator's decisions and emphasized the narrow scope of judicial review in arbitration matters. (Paras 24, 32)

Issues: Whether the lower court rightly confirmed the arbitral awards and whether the appellant's claims of the awards being arbitrary and perverse were valid under the Arbitration Act. (Paras 4, 16, 24)

Ratio Decidendi: The court reiterated that an arbitral award must stand unless the appellant can show substantial legal grounds for setting it aside, confirming the principle that arbitration offers an efficient alternative dispute resolution mechanism, one to which courts should defer unless grave concerns arise. (Paras 25, 32)

Result: Appeals dismissed.

Table of Content
1. scope of appeal under section 37 (Para 1 , 2 , 3)
2. disputes arose under contracts leading to arbitration (Para 5 , 6 , 10 , 11)
3. arguments for and against arbitral awards (Para 12 , 13 , 16 , 17)
4. judicial review of arbitral awards is limited (Para 14 , 20 , 22)
5. limited grounds for setting aside awards (Para 24 , 26 , 29)
6. conclusion: appeals dismissed (Para 32 , 33)

Order :

MANEESH SHARMA, J.

1. The present miscellaneous appeals have been filed under Section 37 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as 'the Arbitration Act'), challenging the judgment dated 01.03.2011 passed by the Learned District and Sessions Judge, Alwar in Civil Misc. Nos. 141/2005 and 474/2005, whereby the challenge to the arbitral award(s) under Section 34 of the Arbitration Act filed by the non-claimant/appellant has been dismissed.

2. At the outset, it is required to be noted that by the impugned order, the learned District and Sessions Judge, Alwar in exercise of its powers under Section 34 of the Arbitration Act has confirmed the award(s) passed by the learned Arbitrator.

3. Nevertheless as regards to an order passed under Section 34 of the Arbitration Act (either setting aside the award or upholding the award) an appeal is provided under Section 37 of the Arbitration Act, however, the contours of the proceedings under Section 37 are more limited in terms of scope and ambit of challenge under Section 34 of the Arbitration Act.

4. Therefore the short question that is posed for consideration before this court is, whether in the facts and circumstances of the case, the learned District and Sessions Judge, Alwar is justified in confirming the award(s), while dismissing the application under Section 37 of the Arbitration Act.

5. The brief facts of the case are that Agreements Nos. 8/86-87 and 9/86-87 were executed between the Executive Engineer, Irrigation Department, Division Alwar, Rajasthan (present appellant) and M/s. Devendra Pal Singh (present respondent) for construction work of Jhiroli Canal from Chain zero to Chain 120 (Agreement No. 8/86-87) and Chain 120 to Chain Tail (Agreement No. 9/86-87), Minor Irrigation Project, Alwar. During the subsistence of the said agreements, certain disputes arose between the parties. Therefore, relying on Clause 23 of the contract, the claimant/respondent raised a dispute, therefore vide order no. F8(8) ASI/I/Cell/94/2701 dated 20.09.1998, Shri S.C. Saxena, Director (Dam), ID & R Irrigation Unit, Jaipur (Retired), was appointed as the sole Arbitrator.

6. Before the learned Arbitrator, the claimant/respondent filed its statement of claim of Rs.3,43,110/- and [(Rs.2,62,264/- + 73,597/-) (including Item No.9)] plus interest, mainly on the following grounds:

(i) Labour remainaing idle due to late issue of cement;

(ii) Cutlivators hinderances; (iii) Late compaction of E/W;

(iv) Shortage of budget;

(v) Mixer Machine and Vibrator charges; and

(vi) Escalation charges (excavated hard soil contrary to Schedule G, ordinary soil)

7. The non-claimant/appellant filed its statement of defence and counter-claim of Rs.2,58,812/- plus interest @ 18% and Rs.2,46,293/- plus interest @ 18% and Rs. 50,000/- towards cost of Arbitration. Thereafter, rejoinders were filed by the claimant/respondent. Subsequently, a reply to the said rejoinder was also filed by the non-claimant/appellant.

8. Thereafter, the claimant/respondent was examined himself as a witness, and three (3) witnesses were examined by the non-claimant/appellant.

9. On the basis of pleadings of the parties the learned Arbitrator framed three the following three (3) issues for consideration on 22.09.2003:

(i) Preliminary Objections;

(ii) Claim of the Claimant and interest; and

(iii) Counter-claim of the non-Claimant and interest on it.

10. Thereafter, the learned Arbitrator decided the issue No. (i) and (iii) against the non-claimant/appellant, whereas issue No. (ii) was partly decided in favour of the claimant/respondent, and a

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

AI

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top