SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Ori) 189

IN THE HIGH COURT OF ORISSA AT CUTTACK
S.K. PANIGRAHI, J.
M/s. National Aluminium Company Limited - Appellant
Versus
Indo Power Projects Limited - Respondent
ARBA No. 16 of 2023
Decided On : 24-07-2025

Advocates:
Advocate Appeared:
For the Appellants : Pami Rath, Guman Singh
For the Respondents: Dayananda Mohapatra, Subhasis Sarkar

The court reaffirmed that judicial intervention in arbitration under Sections 34 and 37 is limited to ensuring no substantial legal errors occurred, emphasizing the importance of respecting the arbitral award's findings.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 and Section 37 - Appeal against arbitral award - Non-compliance with contractual timelines - Contractual claims and counterclaims regarding delays and cost escalations due to alleged defaults - Powers of judicial review under Section 34 and 37 are restrictive and do not allow reappraisal of evidence or merits of arbitral award - The court upheld the arbitral award as it found no grounds of patent illegality or jurisdictional error. (Paras 11-12, 30-37)

(B) Contract Law - Fixed-price contract - The nature of the contract does not exempt from liability for delays caused by one party - Judicial interpretation affirms duty to act in good faith and fulfil contractual obligations without causing undue loss to the counterparty. (Paras 24-25, 40-46)

Facts of the case:
The Appellant filed an appeal under Section 37 against the dismissal of its Section 34 petition, concerning the arbitral award related to delays and claims arising out of electrical works contract. Multiple extensions were granted, and disputes arose over financial recoveries and cost escalations due to project delays attributed to both parties.

Findings of Court:
The court found the arbitrator's award to be well-reasoned and based on thorough consideration of evidence and contractual obligations, and that the delays were largely attributable to the Appellant.

Issues: The primary issue was whether the District Judge's decision was subject to interference given the limited scope of appellate powers under Section 37 of the Act.

Ratio Decidendi: The court held that the appellate jurisdiction is narrow under Sections 34 and 37 of the A&C Act, emphasizing that it does not permit re-evaluating the merits of the award unless substantial legal errors are demonstrated.

Result: Appeal dismissed.

Table of Content
1. describes the essential facts of the case and procedural history. (Para 1 , 2 , 3 , 4 , 5 , 6)
2. outlines the main arguments and positions of both the appellant and respondent. (Para 7 , 8 , 9 , 10 , 11)
3. defines the legal framework for arbitration and the limitation of court interference. (Para 12 , 13 , 14 , 15 , 16 , 17 , 18 , 19 , 20 , 21 , 22 , 23 , 24 , 25 , 26 , 27)
4. reiterates the stringent limits on court's power to interfere with arbitral awards. (Para 28 , 30 , 31 , 32)
5. discusses claims, counterclaims, and the reasoning provided by the arbitrator. (Para 33 , 34 , 35 , 36 , 37 , 38 , 39 , 40 , 41 , 42 , 43 , 44 , 45 , 46)
6. concludes the judgment affirming the arbitral award and dismissing the appeal. (Para 47 , 48 , 49 , 50)

JUDGMENT :

S.K. PANIGRAHI, J.

1. This Appeal under Section 37 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as “A&C Act”) has been filed against the judgment dated 18.05.2023 passed by the learned District Judge, Koraput at Jeypore in Arbitration Proceeding No.1 of 2020 wherein the learned District Judge has dismissed the petition filed under Section 34 of the A&C Act thereby confirming the award dated 17.12.2019 passed by the learned Sole Arbitrator in Arbitration Proceeding No.5 of 2017.

I. FACTUAL MATRIX OF THE CASE:

2. Pursuant to an invitation to tender floated by the present Appellant for execution and completion of the work of Electrical works for Phase-2 Expansion Project of Alumina Refinery at Damonjodi (Orissa). The present Respondent participated in the tender and was declared successful. Formal agreement between the parties was executed on 10.10.2007 with the stipulation that the work in question would be completed within a period of 12 months beginning from 15.9.2007.

3. However, the work could not be completed by the Respondent within the time stipulated i.e. 12 months. As many as 12 extensions were granted by the Appellant and the work was completed by the Respondent on 31.7.2012. The Designated Engineer- in-Charge issued a letter of completion on 1.7.2015 indicating that the work of the Respondent amounted to a total of Rs. 9,53,61,442/- The Engineer-in- Charge recommended payment of the 24th R.A. bill for an outstanding amount of Rs. 1,59,40,585 subject to statutory deductions and other legal recoveries to be decided by the present Appellant. Soon thereafter, the Appellant replied vide letter dated 30.9.2015 that this recommended amount was tentative and several deductions towards liquidated damages, cost of unreturned free issue materials and scraps, rebate items, cost of the items lost, etc. would be deducted from the Respondent. Upon calculation, the Appellant determined that the Respondent was liable to pay an amount of Rs. 89,63,093/- to the Respondent. And at this juncture, the dispute arose.

4. The Respondent questioned the proposed deductions terming them as illegal and beyond the terms of the contract. The Respondent issued a notice raising several claims and demanded reference of the matter for arbitration. As the Appellant did not respond to the notice, the Respondent approached the High Court of Orissa in ARBP No. 42 of 2016 u/s 11 of the Act. This Court was pleased to appoint former Judge of Orissa High Court Justice A.K. Parichha as the Sole Arbitrator in the matter.

5. Before the Sole Arbitrator both the parties, tendered oral and documentary evidence. Upon analysis and consideration of the evidence adduced by the parties, the Sole Arbitrator was pleased to pass an award in favour of the present Respondent vide award dated 17.12.2019.

6. Aggrieved, the present Appellant preferred an application u/s 34 of the A&C Act. Vide judgment dated 18.5.2023 in Arbitration Proceeding No.1 of 2020, the Ld. District Judge, Koraput at Jeypore was pleased to dismiss the said application on the ground that the Appellant has failed to point out any illegality in the Award. Hence, the present petition.

7. Now that the facts leading up to the ins

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top