SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(HP) 1669

IN THE HIGH COURT OF HIMACHAL PRADESH AT SHIMLA
SANDEEP SHARMA, J.
State of Himachal Pradesh and Another – Appellants
Versus 
M/s Tenzin Constructions Co. Pvt. Ltd. – Respondent
CARBC No. 72 of 2025
Decided On : 10-12-2025 

Advocates Appeared:
For the Appellants : Rupinder Singh Thakur, Ayushi Negi, Swati Draik
For the Respondents: J.S. Bhogal, Srishti Verma, Swati Verma, T.S. Bhogal

Under Section 34, courts cannot interfere with arbitral awards based on joint departmental reconciliations and admissions unless patent illegality apparent on award's face; limited to upholding finality and party autonomy.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - Petition to set aside arbitral award granting Rs. 4,97,49,382/- with 6% interest for claims including price escalation under Clause 10CC, GST reimbursement, extra substituted items, sales tax refund, security deposit - Award based on joint reconciliations (Ext. X1, X2, X3) and departmental admissions by divisional accountant and executive engineer - No patent illegality or violation of fundamental policy of Indian law, public policy, justice or morality - Scope of interference limited; court not to re-appreciate evidence or substitute alternative view unless perversity goes to root of matter. (Paras 1-33)

(B) Arbitration and Conciliation Act, 1996 - Sections 34(2)(b)(ii), 28(3) - Patent illegality must be apparent on face of award, not from re-analysis of pleadings/evidence - Award not to be set aside for mere disagreement with arbitrator's reasonable construction of contract terms or facts - Defer to arbitral tribunal's view on evidence quantity/quality. (Paras 8-20)

Facts of the case:
Construction contract for building portion including water supply, sanitation, rain water harvesting and septic tank awarded at Rs. 10,73,25,888/-, completion within two years from 15th day of letter of award - Delays due to non-provision of hindrance-free site, drawings/designs, materials, untimely payments, incomplete allied works by other contractor - Claims for escalation, GST, extra items etc. awarded by arbitrator; department challenged under Section 34 alleging non-appreciation of contract terms, lack of proof of delay attribution.

Findings of Court:
Claims A (Rs.71,71,098/-), B (Rs.93,24,007/- escalation), C (Rs.2,42,96,266/- GST), D (Rs.45,48,258/- extra items), E (Rs.6,54,270/- sales tax), H (Rs.37,55,483/- security deposit), I (6% interest), J (Rs.9,54,277/- costs) allowed based on joint verifications; F and G (prolongation, idling) rejected.

Issues: Whether award suffers from patent illegality, contravenes contract terms/public policy, or beyond arbitrator's jurisdiction; validity of claims absent formal acceptance despite recommendations/admissions.

Ratio Decidendi: Award upheld as founded on unchallenged joint reconciliations and repeated admissions by departmental witnesses; no perversity where arbitrator relies on verified documents over unilateral assertions; interference unwarranted absent facial violation of substantive law or contract.

Result: Petition dismissed.

Table of Content
1. petition challenges arbitral award under section 34. (Para 1 , 2 , 3 , 4)
2. petitioner alleges patent illegality; respondent cites admissions. (Para 5 , 6)
3. section 34 limits interference to patent illegality only. (Para 7 , 8 , 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16 , 17 , 18 , 19 , 20)
4. departmental admissions validate award claims; no perversity. (Para 21 , 22 , 23 , 24 , 25 , 26 , 27 , 28 , 29 , 30 , 31)
5. petition dismissed; arbitral award upheld. (Para 32 , 33)

JUDGMENT :

SANDEEP SHARMA, J.

1. Instant petition filed under Section 34 of Arbitration and Conciliation Act (herein after referred to as the “Act”), lays challenge to award dated 29.5.2023, passed by the learned Arbitrator, awarding therein sum of Rs. 4,97,49,382/- with interest @ 6% per annum w.e.f. 1.4.2022, till the date of payment.

2. Explicitly, facts of the case, relevant for adjudication of the case at hand, as emerge from pleadings adduced on record by the respective parties are that work of construction of Civil Hospital at Rohru (Sh: C/O Building Portion including WS and SI, rain water harvesting tank and septic tank) came to be awarded to the respondent/claimant vide letter dated 5.10.2016 amounting to Rs. 10,73,25,888/- which was to be completed within two years and time was to be reckoned from 15th day of the issuance of letter of award dated 5.10.2016. It is claimed by the respondent/claimant that work was commenced at the site well within time, but since petitioner-department failed to provide hindrance free site and required drawings/designs, delay was caused in completion of the work. Allegedly, petitioner-department failed to supply the requisite material required for the execution of the work, as a result thereof, machinery of the respondent-claimant as well as manpower brought on the site, rendered idle and the work was delayed.

3. Besides above, work of lifts and electrification, which was executed by another contractor, was not completed in time, rendering the infrastructure of the respondent-claimant idle for more than six months. Allegedly, petitioner-department failed to make the timely payments, as a result thereof, work on the site was delayed and prices of material and POL were increased under Clause 10CC of the Contract and respondent-claimant was entitled to price escalation. Since petitioner-department failed to pay price escalation admissible to the respondent-claimant under Clause 10CC, coupled with the fact that GST, which was liable to be reimbursed was not reimbursed, dispute arose inter-se parties, respondent filed Arbitration Case No. 48 of 2021, praying therein for appointment of the Arbitrator. Pursuant to directions issued by this Court in afore case, Mr. Justice Kuldeep Singh Kanwar (Retd.) Judge, came to be appointed as an Arbitrator.

4. Learned Arbitrator on the basis of pleadings as well as evidence adduced on record by the respective parties passed impugned award, thereby awarding amount of Rs. 4,97,49,382/-, along with interest @ 6% p.a. w.e.f. 1.4.2022 till payment in favour of respondent- claimant. Besides above, learned Arbitrator also awarded sum of Rs. 9,54,277/- in favour of the respondent-claimant on account of cost of proceedings. In the afore background, petitioner-department has approached this Court in the instant proceedings, praying therein to set-aside afore award on various grounds.

5. Precisely, the grouse of the petitioner, as has been highlighted in the petition and further canvassed by Mr. Rupinder Singh Thakur, learned Additional Advocate General, is that award passed by the learned Arbitrator is in conflict with basic notion of law and fundamental policy of Indian law and as such, deserves to be set- aside. While making this Court peruse record, learned Additional Advocate General attempted to argue that learned Arbitrator has not properly appreciated the pleadings of the parties and terms of agreement, as a result thereof, learned Arbitrator has wrongly allowed claims No. A, B, C, D
































Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top