IN THE HIGH COURT OF HIMACHAL PRADESH, SHIMLA
TARLOK SINGH CHAUHAN, ACJ, SATYEN VAIDYA, J.
M/s Patel-Gammon JV – Appellant
Versus
SJVN Limited - Respondent
FAO(OS) No. 23 of 2024
Decided on : 23-12-2024
| Table of Content |
|---|
| 1. appellant challenges dismissal of plaint rejection. (Para 1 , 2 , 3) |
| 2. plaintiff's claims regarding hydro allowance. (Para 4) |
| 3. defendant's objections to suit standing. (Para 5 , 6) |
| 4. court's rationale for cause of action. (Para 8 , 9 , 10) |
| 5. limitation argument analysis. (Para 11 , 12) |
| 6. parameters for cause of action determination. (Para 13 , 14 , 15 , 16 , 17) |
| 7. plaintiff's basis for hydro allowance claim. (Para 18 , 19 , 20 , 21) |
| 8. court's interpretation of contractual obligations. (Para 22 , 23 , 24 , 25) |
| 9. rejection of plaint based on lack of cause. (Para 26 , 27 , 28 , 29) |
| 10. ruling to set aside prior order. (Para 30) |
| 11. final disposition of the appeal. (Para 31) |
JUDGMENT :
Satyen Vaidya, J.
1. By way of this appeal, the appellant has assailed order dated 15.12.2023 passed by learned Single Judge in OMP No.189 of 2021 in Civil Suit No. 83 of 2019 whereby the application of the appellant under Order VII Rule 11 of the Code of Civil Procedure (for short “Code”) seeking rejection of the plaint has been dismissed.
2. The parties hereafter shall be referred to by the same status as they hold in Civil Suit No. 83 of 2019. The appellant is the defendant and the respondent herein is the plaintiff.
3. The plaintiff has filed a suit for recovery of Rs.129.51 crores along with interest pendent lite and future @ Rs.12% per annum against the defendant.
4. The premise of the suit as culled out from the contents of plaint is that the plaintiff had awarded major civil works being Package-I and Package-II relating to execution of 412 MW Rampur Hydro Electric Project (for short, “RHEP”) on 01.02.2007 to the defendant, after due evaluation by the Tender Evaluation Committee. It is averred that in pursuance to the notification dated 28.05.2008 issued by the Government of Himachal Pradesh, the labourers engaged in the construction of Hydro Electric Projects (for short, “HEPs”) being constructed in non-tribal areas of Himachal Pradesh were made entitled to additional 25% over and above prevalent minimum wages. Such allowance was popularly known as “Hydro Allowance”.
4.1 The labourers engaged in RHEP by the defendant staged dharna/strike in the project area on 28.09.2009 under the aegis of Labour Unions. The defendant had taken a stand that such allowance was not permissible to the labour employed in RHEP. Since, the labour strike continued, resulting in obstruction to the progress of the project work, plaintiff in order to resolve the issue, had constituted a committee on 05.03.2010. The Committee had submitted its recommendation on 19.03.2010. As a result, plaintiff issued an order for release of payment on account of additional component of 25% “Hydro Allowance”, subject to execution of an undertaking by the defendant that modality of the order would be agreeable to it and no claim would be raised on this account in any forum in future against the plaintiff. The said decision was said to have been made subject to further undertaking that actual payment on account of “Hydro Allowance” would not be less than the amount claimed by the defendant. In this way, a total sum of Rs.79.02 crore was released to the defendant.
4.2 It is further submitted that the Auditors vide annual report for the year 2016-2017, made observations with respect to the omission of defendant in passing on the benefit of “Hydro Allowance” to the labour in its totality and had found reimbursement of an amount of Rs.72,04,20,580/- due from the defendant.
4.3 As per the plaintiff, the Chief Vigilance Officer (for short, “CVO”) of plaintiff vide a communication dated 10.05.2018 addressed to the project authorities, required them to recover from the defendant the excess payment. To similar extents were the instructions imparted by the Deputy Chief Vigilance Officer (‘DCVO’) of the plaintiff on 31.07.2019.
4.4 The plaintiff also issued a communication to the defendant on 12.07.2018 claiming the entire amount of “Hydro Allowance” to the extent of Rs.74.00 crores includ
Sopan Sukhdeo Sable vs. Charity Commr.
Madanuri Sri Rama Chandra Murthy vs. Syed Jala
Dahiben vs. Arvindbhai Kalyanji Bhanusali (Gajra) dead through L.Rs and others
T. Arivandandam vs. T.V.Satyapal and another
I.T.C. Limited vs. Debts Recovery Appellate Tribunal and others
AI
A plaint must disclose a clear and enforceable cause of action; if it does not, it can be rejected under Order VII Rule 11 of the Code.
The court established that the starting point for limitation under the Limitation Act depends on when the right to sue accrues, not merely on the date of breach or completion of work.
The court clarified misapplications of the Limitation Act and confirmed entitlement to claims based on government notifications regarding minimum wage increases in a construction contract context.
A cause of action based on an approved bill resets limitation; rejection of plaint under Rule 11 is unwarranted where factual disputes exist.
Civil Courts have jurisdiction to hear claims under construction contracts barred from arbitration, provided they arise within the limitation period set by specific contract conditions.
The lack of privity of contract and failure to establish a cause of action were central to the court's decision.
Fraud allegations require specific pleadings with particulars under CPC Order VI Rule 4; vague pleas rejected. Limitation for work recovery runs from contract-specified final bill settlement date. Pr....
Defamation suit for libel time-barred beyond one year from publication; receipt of exoneration reports does not extend limitation. Plaint rejectable under Order VII Rule 11(d) if averments disclose l....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.