IN THE HIGH COURT OF HIMACHAL PRADESH, SHIMLA
G.S. Sandhawalia, C.J., Ranjan Sharma, J.
Himachal Pradesh Road and other Infrastructure Development Corp. Ltd - Appellant
Versus
M/s C & C Construction Ltd. - Respondent
Civil Arb. Appeal No. 01 of 2023
Decided On : 31-10-2025
| Table of Content |
|---|
| 1. contract delays led to arbitration on prolongation costs. (Para 1 , 2 , 3 , 4) |
| 2. award upheld absent arbitrator perversity. (Para 5 , 6 , 7 , 8 , 9 , 10) |
| 3. overhead claims need contemporaneous evidence proof. (Para 11 , 12 , 13 , 14) |
| 4. no re-appreciation of arbitral evidence. (Para 15 , 16) |
| 5. section 37 confines interference to patent illegality. (Para 17) |
| 6. head office expenses require witness-verified evidence. (Para 18 , 19 , 20 , 21 , 22 , 23 , 24 , 25 , 26 , 27 , 28) |
| 7. ca certificates alone insufficient without testimony. (Para 29 , 30 , 31 , 32 , 33 , 34 , 35 , 36) |
| 8. unproven claims violate public policy. (Para 37 , 38) |
| 9. supported claims immune from interference. (Para 39 , 40 , 41 , 42 , 43 , 44 , 45 , 46) |
| 10. appeal partly allowed setting aside unproven amounts. (Para 47 , 48 , 49) |
JUDGMENT :
G.S. Sandhawalia, C.J.
Challenge in the present Civil Arbitration Appeal is laid to the judgment dated 05.12.2022, passed by the learned Single Judge in Civil Arbitration Case No. 1 of 2020, titled Himachal Pradesh Road and other Infrastructure Development Corp. Ltd vs M/s C & C Construction Ltd. whereby the Award dated 17.08.2019, passed by the three Member Arbitral Tribunal in favour of the respondent herein has been upheld.
2. The appellant herein is a Infrastructure Corporation having its registered office at Nirman Bhawan Shimla and respondent on the other hand, is a construction company registered under The Companies Act, 1956 and having its registered office at Plot No. 79, Sector 32 Gurgaon, in the State of Haryana.
3. Apparently, appellant had awarded the Contract on 29.02.2008 to the respondent, whereby the respondent agreed to execute the works relating to widening and strengthening of Una-Barsar-Jahu-Kalkhar-Nerchowk Road, Section Una to Barsar from Km 45+000 to Km 90+800. The parties in terms of the aforesaid agreement inter se entered into a Contract on 6th of May, 2008 which was numbered as Contract No. PW -SRP/ RIDC/ Procurement-ICB-3/2008 for the execution of the aforesaid work. There was delay in execution of the work since the work was to be completed in 33 months from 07.05.2008 by March, 2011 however, the appellant decided to grant extension of time till the completion of the work which was on 31.10.2014. After making the entire payments with regard to the execution of the work to the respondent, the respondent invoked the arbitration agreement with respect to its claim for damages for prolongation of the Contract. The respondent nominated Shri Ashok Khurana, Director General (Retd.), CPWD, as its Arbitrator nominee. On receipt of such notice of invocation of the arbitration, the appellant also nominated Shri R.K. Sharma, Engineer-in-Chief (Retd.) IPH, Himachal Pradesh as its Arbitrator nominee and they both nominated Hon'ble Mr. Justice Devinder Gupta, former Chief Justice as the Presiding Arbitrator and the constitution of the Tribunal was completed on 24.02.2018.
4. The claimant/respondent herein put forth its all claims before the Tribunal and appellant herein replied to the said claim by taking objections with regard to maintainability of the claim petition, including the claim petition being hopelessly time barred as also the authority of the person who had filed the claim. Thereafter, the issues were framed by learned Tribunal and the parties led their respective evidence. The learned Arbitrator, after considering the pleadings of the parties and documents placed on record, has passed the award in favour of the claimant in the following terms.
"(i) An amount of Rs.11.70 Crore under claim No. 1.
(ii) An amount of Rs. 13.60 Crore under claim No.2
iii) Under Claim No.3, the Claimant is held entitled to Rs.6.07 Crore towards simple interest 12% per annum from 07.04.2016, the date when cause of action arose to the Claimant till 07.04.2018 the date of filing of statement of claim on the awarded amount of Rs.25.30 Crore.
(iv) Claimant is also held entitled to Rs.4.12 Crore towards pendente lite intere



AC Chokshi Share Broker Pvt. Ltd. vs. Jatin Pratap Desai and another
Balakrishna Savalram Pujari Waghmare Vs. Shree Dhyaneshwar Maharaj Sansthan and Others
Batliboi Environmental Engineers Limited Vs. Hindustan Petroleum Corporation Limited and Another
Bharat Cooking Coal Limited vs. L.K. Ahuja
Dyna Technologies Pvt. Ltd vs. Crompton Greaves Ltd.
Haryana Tourism Limited vs. Kandhari Beverages Ltd.
K. Sugumar and another vs. Hindustan Petroleum Corporation Ltd. and another
Metal Box Co. Vs. Their Workmen
Oil & Natural Gas Corporation Ltd. Vs. Saw Pipes Ltd
Parsa Kente Collieries Ltd vs. Rajasthan Rajya Vidyut Utpada Nigam Ltd.
Reliance Infrastructure Ltd. Vs. State of Goa
Samruddhi Co-Operative Housing Society Ltd. Vs. Mumbai Mahalaxmi Construction Pvt. Ltd.
State of Gujarat Vs. Kothari Associates
State of Rajasthan and Another Vs. Ferro Concrete Construction Private Limited
UHL Power Company Ltd. vs. State of Himachal Pradesh
Union of India and Another Vs. IndusInd bank Limited and Another
Arbitral awards set aside partly for patent illegality where head office overhead claims lack evidentiary support like unverified CA certificates without witness testimony, despite upholding other pr....
Arbitral awards under Section 34 set aside in part for patent illegality where claims lack evidence of loss; sustained for plausible delay findings, scope changes; severability applies to separable p....
The judicial review under Section 34 of the Arbitration and Conciliation Act is restricted to issues of patent illegality, ensuring that arbitrator's findings are not disturbed unless they fundamenta....
The court emphasized that arbitral awards should not be interfered with solely based on disagreements with findings, affirming the limited grounds for appeal under Section 34 of the Arbitration Act.
The judgment emphasizes the limited scope of interference with arbitral awards and the principle that courts should not interfere with arbitral awards unless there is a patent illegality or violation....
The need for evidence to establish loss of profits and the court's discretion to modify the interest rate as agreed upon by the parties.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.