SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2021 Supreme(J&K) 49

IN THE HIGH COURT OF JAMMU AND KASHMIR AT JAMMU
JAVED IQBAL WANI, J.
Union of India and Others – Appellants
Versus
Roshni Devi and Others – Respondents
M.A. No. 138 of 2007, I.A. No. 227 of 2007
Decided On : 21-04-2021

Advocates:
Advocate Appeared:
For the Appellant : Mr. Sandeep Gupta.
For the Respondent: Mr. Anil Mahajan.

Point of Law: Work Contract - Arbitration - We should make the law of arbitration simple, less technical and more responsible to the actual realities of the situation, but must be responsive to the canons of justie and fair play and make the Arbitrator adhere to such process and norms which will create confidence, not only by doing justice between the parties, but by creating a sense that justice appears to have been done.

Headnote:

Civil Procedure Code, 1908 - Order XVII Rule 2 - Arbitration Act - Section 20 and 41(a) - Contract - Appointment - Contract for providing the married accommodation to Officers was allotted to a contractor (deceased predecessor in interest of the respondents herein) by the appellants herein - It is being stated that the deceased signed the final bill with a declaration that he had no further claims and that subsequently said final bill was paid to the deceased contractor where after receiving same, deceased contractor intimated the department vide communication a statement of unpaid items of work with a claim appended to said communication which communication is stated to have been acknowledged by the appellants herein - It is being further state that the said claims were refused by appellants herein where upon deceased contractor is stated to have approached this Court while filing Arbitration Petition for appointment of an arbitrator under Section 20 of the Arbitration Act - Whether the arbitrator has misconducted himself and in the proceedings.

Finding of the Court:

Impugned Judgment and is of the considered opinion that the arbitrator has failed to provide a reasonable opportunity of hearing to claimants/respondents herein while conducting arbitration proceedings in question culminating into passing of award and in the process thus having misconducted himself and the proceedings - Court below having noticed all these facts has rightly drawn conclusions in the impugned Judgment that arbitrator has misconducted and has thus rightly set aside award and passed the impugned order within the parameters and principles of law occupying the field - Other grounds of challenge urged in the appeal in hand by the appellant in view of aforesaid analysis need not to be dealt with or deliberated upon, in that, same as such pales into insignificance - Viewed thus, what has been observed, analyzed and considered herein.

Result: Appeal dismissed.

ORDER :

1. The appellants herein through the medium of instant appeal challenge Judgment dated 31-05-2007 (for short impugned Judgment) passed by the Court of Additional District Judge, Jammu (for short court below) in case titled as Smt. Roshni Devi and Others vs. Union of India and Others.

Background facts:

2. The background facts those stem out from the memo of appeal as stated therein reveal that a contract bearing No. CEJK-11/83-84 for providing the married accommodation to Officers at Udhampur was allotted to a contractor namely “Vishnu Kumar Gupta” (deceased predecessor in interest of the respondents herein) by the appellants herein.

3. It is being stated that the deceased signed the final bill on 07-10-1986 with a declaration that he had no further claims and that subsequently the said final bill was paid to the deceased contractor on 03-04-1987, where after receiving the same, the deceased contractor intimated the department vide communication dated 14-07-1988, a statement of unpaid items of work with a claim appended to said communication which communication is stated to have been acknowledged by the appellants herein.

4. It is being further state that the said claims were refused by the appellants herein where upon the deceased contractor is stated to have approached this Court while filing Arbitration Petition No. 302/1989 for appointment of an arbitrator under Section 20 of the Arbitration Act (for short the Act) which is stated to have been dismissed by this Court vide Judgment dated 30-07-1990 on the ground of limitation. The said Judgment is stated to have been assailed by the deceased contractor in an appeal before the Division Bench which appeal is stated to have been allowed vide Judgment dated 31-03-1995 holding the Arbitration Petition filed by the deceased contractor under Section 20 to be within time.

5. It is being stated that as a consequence of the Judgment of the Division Bench dated 31-03-1995, the Arbitration Petition got revived and transferred subsequently to the Court of District Judge, Jammu for adjudication.

6. It is being further stated that the Arbitration Petition came to be allowed by the District Judge, Jammu vide order dated 17-03-1997 directing the Engineer-in-chief, Army HQ to appoint an arbitrator within one month who will enter upon the reference and make an award within the statutory period of four months.

7. It is being further stated that the respondents herein filed a petition for appointment of new arbitrator before the Court of Additional District Judge, Jammu which came to be resisted by the appellants herein on the ground that the arbitrator as per the directions of the District Judge, Jammu dated 17-03-1997 was appointed and delay was caused because of misrepresentation of claim by enhancing/modifying the claims from 7.89 lacs to 14.12 lacs by the deceased contractor.

8. It is being further stated that the Learned Additional District Judge, Jammu vide its Judgment dated 4-08-1997 disposed of the said petition directing the parties to cause appearance before the arbitrator on 16-08-1997 and that the arbitrator shall make and publish the award within the statutory period of four months.

9. It is being further stated that in pursuance to order dated 17-03-1997 passed by the District Judge, Jammu, the Engineer-in-chief vide letter dated 10-06-1997 appointed one Brig. G.R. Sud as an arbitrator who entered upon the reference and the parties submitted their claims and pleadings before him. The said Arbitrator is however stated to have resigned during the pendency of the arbitration proceedings vide his letter dated 28-11-1997 owing to his superannuation, whereafter it is being stated that one Brig. T.K. Mittal came to be appointed as a new arbitrator by the competent authority vide letter dated 10-03-1998.

10. It is being further stated that 21 claims were preferred by the deceased contractor totaling 7.89 lacs on 14-07-1988 which however, came to be subsequently enhanced by his alleged partn

          Click Here to Read the rest of this document
          1
          2
          3
          4
          5
          6
          7
          8
          9
          10
          11
          SupremeToday Portrait Ad
          supreme today icon
          logo-black

          An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

          Please visit our Training & Support
          Center or Contact Us for assistance

          qr

          Scan Me!

          India’s Legal research and Law Firm App, Download now!

          For Daily Legal Updates, Join us on :

          whatsapp-icon Back to top