IN THE HIGH COURT OF JHARKHAND AT RANCHI
SHREE CHANDRASHEKHAR, RATNAKER BHENGRA, JJ.
The State of Jharkhand through the Secretary, Industries Department & Ors. - Appellants
Versus
M/s Satyam Ferro-Tech(P) Ltd & Ors. - Respondents
L.P.A. No. 65 of 2011 with C.O. No. 5 of 2011
Decided On : 22-02-2022
Interest Subsidy - Jharkhand Industrial Incentive Rules - Rule 4.3(Gha) - 4.3 lwn vuqnku - Time limit - 1. The interested units must submit their claim along with entire required documents, complete in all respects, within six months of the financial year. 2. The power to relax the time period beyond more than six (6) months shall be vested in the Director of Industries. The power to relax the time limit beyond more than that shall be vested in the Secretary-Industries. - The court held that there are good grounds for condoning the delay in submission of the application for interest subsidy for the financial years 2006-07 and 2007-08. The delay for the year 2003-04 was not condoned due to unsatisfactory explanation. The respondents were directed to process the claims for interest subsidy of the petitioners (except for the year 2003-04) and disburse the legally payable claims as early as possible and preferably within two months from the date of receipt/production of a copy of this order.
Fact of the Case:
M/s Satyam Ferro-Tech (P) Ltd. filed a petition for payment of interest subsidy for the financial years 2006-07, 2007-08 and 2008-09 with interest at the rate of 18% per annum. The company also challenged the validity of Rule 4.3(Gha) of the Jharkhand Industrial Incentive Rules, 2003. The court found good grounds for condoning the delay in submission of the application for interest subsidy for the financial years 2006-07 and 2007-08, but not for the year 2003-04. The respondents were directed to process and disburse the legally payable claims.
Finding of the Court:
The court found good grounds for condoning the delay in submission of the application for interest subsidy for the financial years 2006-07 and 2007-08, but not for the year 2003-04. The respondents were directed to process and disburse the legally payable claims.
Issues: The main issue was the condonation of delay in submission of the application for interest subsidy for the financial years 2006-07, 2007-08, and 2008-09, and the challenge to the validity of Rule 4.3(Gha) of the Jharkhand Industrial Incentive Rules, 2003.
Ratio Decidendi: The court held that there are good grounds for condoning the delay in submission of the application for interest subsidy for the financial years 2006-07 and 2007-08. The delay for the year 2003-04 was not condoned due to unsatisfactory explanation.
Final Decision: The court allowed the appeal, dismissed the cross-objection, and directed the respondents to process and disburse the legally payable claims for interest subsidy of the petitioners (except for the year 2003-04) as early as possible and preferably within two months from the date of receipt/production of a copy of this order.
ORDER :
Shree Chandrashekhar, J.
W.P.(C) No.2129 of 2010 was filed by M/s Satyam Ferro-Tech (P) Ltd. (hereinafter referred to as “the Company”) for payment of interest subsidy for the financial years 2006-07, 2007-08 and 2008-09 with interest at the rate of 18% per annum on the accumulated amount of interest subsidy from due date.
2. By filing an interlocutory application for amendment vide I.A No.4090 of 2010 further prayer touching upon validity of Rule 4.3(Gha) of the Jharkhand Industrial Incentive Rules, 2003 was sought to be challenged, the averments in respect of which are contained in paragraph nos.36A to 36E of the said application.
3. Rule 4.3(Gha) of the Jharkhand Industrial Incentive Rules, 2003 is extracted below :
?k & le; lhek
1- bPNqd bdkbZ;ksa dks lHkh n`f"Vdks.k ls iw.kZ okafNr dkxtkrks ds lkFk vius nkos fdlh foRrh; lky dh lekfIr ds N% ekg ds Hkhrj lefiZr djuk vfuok;Z gksxkA
2- 6 ¼N%½ ekg ls vf/kd dh vof/k dks {kkUr djus dh 'kfDr m|ksx funs'kd esa fufgr gksxhA blls vf/kd ds le; lhek dks {kkUr djus dh 'kfDr lfpo m|ksx esa fufgr gksxhA**
English Translation:
“4.3 Interest Subsidy:
Gha - Time limit
1. The interested units must submit their claim along with entire required documents, complete in all respects, within six months of the financial year.
2. The power to relax the time period beyond more than six (6) months shall be vested in the Director of Industries. The power to relax the time limit beyond more than that shall be vested in the Secretary-Industries.”
4. By a common order dated 19th January 2011 W.P.(C) No.2129 of 2010 with W.P.(C) No.2141 of 2010 were disposed of in the following terms :
8. However, I am not inclined to condone the delay for the year 2003-04 in WPC No.2141/2010 as the explanation of the delay of 16 months is not satisfactory.
9. In the result, the impugned orders are set aside and the respondents are directed to process the claims for interest subsidy of the petitioners (except for the year 2003-04 in WPC No.2141 of 2010) and disburse the legally payable claims as early as possible and preferably within two months from the date of receipt/production of a copy of this order.
With these observations and directions, both the writ petitions stand disposed of.”
5. The proceedings in C.O. No.5 of 2011 would disclose that by an order dated 12th April 2018, L.P.A. No.211 of 2012 hearing in which by that time was complete was detagged and it was ordered that other matters shall be listed after the judgment in L.P.A. No.211 of 2012. The judgment in L.P.A. No.211 of 2012 was rendered by the Division Bench on 13th June 2018 upholding vires of the Jharkhand Industrial Incentive Rules, particularly Rule 4.3(Gha).
6. The State of Jharkhand has filed L.P.A. No.65 of 2011 against the common order passed in W.P.(C) No.2129 of 2010 by which the learned writ Court held that there are good grounds for condoning the delay in submission of the application for interest subsidy for the financial years 2006-07 and 2007-08.
7. L.P.A No.63 of 2011 has been filed against the common order dated 19th January 2011 passed in respect of W.P.(C) No.2141 of 2
City and Industrial Development Corpn. v. Dosu Aardeshir Bhiwandiwala
The main legal point established in the judgment is the court's discretion to condone the delay in submission of the application for interest subsidy based on the sufficiency of cause shown by the pe....
The main legal point established in the judgment is the necessity for determining the real questions in controversy between the parties and the consideration of prejudice or injustice to the other pa....
The main legal point established in the judgment is that the court upheld the rejection of the petitioner's claim for Capital Investment Subsidy as the application was filed after the stipulated peri....
The absence of a cut-off date in the Special Mega Package allows entitlement to incentives regardless of the commercial production start date relative to the previous policy's expiry.
The court affirmed that companies meeting criteria under the Bihar Industrial Incentive policies are entitled to interest subsidies from the commencement of commercial production, irrespective of pri....
The main legal point established in the judgment is that the Commissioner should consider the sufficient cause for the delay in preferring the application under Section 264 of the Income Tax Act, esp....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.