IN THE HIGH COURT OF JHARKHAND AT RANCHI
SUJIT NARAYAN PRASAD, J.
Usha Martin Limited - Petitioner
Versus
State of Jharkhand, through the Secretary, Department of Industries, Government of Jharkhand & Ors. - Respondents
W.P. (C) No. 3352 of 2013
Decided On : 27-06-2022
Industrial Policy - Jharkhand Udyogik Protsahan Niyamawali, 2003 - Jharkhand Mega Project Incentive Rule, 2005 - Jharkhand Industrial Policy Act, 2001 - [Clause 5 of Jharkhand Mega Project Incentive Rule, 2005] - The court rejected the petitioner's claim for Capital Investment Subsidy as the application was filed after the stipulated period of six months, as per the relevant policy decisions of the State Government. The court cited legal principles of approbate and reprobate, and the limitations of the writ of certiorari in correcting errors of jurisdiction committed by inferior courts or tribunals.
Fact of the Case:
The petitioner sought to quash the order rejecting their application for Capital Investment Subsidy under the Jharkhand Industrial Policy Act, 2001, as it was filed after the stipulated period of six months. The court found that the application was indeed filed after eight years from the date of commencement of commercial production, and therefore, rejected the claim.
Finding of the Court:
The court found that the application for Capital Investment Subsidy was filed beyond the stipulated period of six months, as per the relevant policy decisions of the State Government, and therefore, rejected the petitioner's claim.
Issues: The main issue was whether the rejection of the petitioner's application for Capital Investment Subsidy under the Jharkhand Industrial Policy Act, 2001, was justified due to the application being filed after the stipulated period of six months.
Ratio Decidendi: The court held that the petitioner's application for Capital Investment Subsidy was rightly rejected as it was filed beyond the stipulated period of six months, as per the relevant policy decisions of the State Government. The court also cited legal principles of approbate and reprobate, and the limitations of the writ of certiorari in correcting errors of jurisdiction committed by inferior courts or tribunals.
Final Decision: The writ petition lacked merit and was dismissed by the court.
JUDGMENT :
The instant writ petition, under Article 226 of the Constitution of India, has been filed seeking following reliefs :
(b) For a direction upon the concerned Respondent to immediately grant aforesaid Capital Investment Subsidies as applied by the Petitioner before the Competent Authority of the Respondent Department for grant of Capital Subsidy as provided under the “Jharkhand Industrial Policy Act, 2001" and in “Jharkhand Udyogik Protsahan Niyamawali, 2003”.
2. The brief facts of the case, as per the pleadings made in the writ petition, is that the State of Jharkhand came out with an Industrial Policy known as “Jharkhand Industrial Policy Act, 2001” vide Notification No. 1888 dated 25.08.2001 making therein, inter alia, the provisions for encouraging the existing Industrial Units, who have expanded/modernized/diversified their units on 15.11.2000 or thereafter. After promulgation of the aforesaid Industrial Policy, the State in order to implement the aforesaid policies notified a rule known as “Jharkhand Udyogik Protsahan Niyamawali, 2003”.
It is the case of the petitioner that the writ petitioner submitted application seeking benefit under the said Industrial Policy for Capital Investment Subsidy but the same was rejected vide order dated 25.07.2012 as contained in Memo No. 2302 on the ground that the Screening Committee constituted under the Chairmanship of Chief Secretary vide its meeting dated 31.05.2012 has found that the application for capital investment subsidy filed by the petitioner after 8 (eight) years from the date of commencement of commercial production and 19 months from the date of issuance of certificate.
3. Mr. Shreenu Garapati, learned S.C. III appearing for the respondents-State of Jharkhand has submitted that the issue has already been decided by the Division Bench of this Court in L.P.A. No. 211 of 2012 vide order dated 13.06.2018, wherein this Court, after taking into consideration the period of limitation, i.e., filed after the period of six months, since the claim of the respondent/writ petitioner of the said Letters Patent Appeal has been rejected, herein also, the case of writ petitioner has been rejected since application for seeking the leave under the aforesaid policy decision has been filed after the period of six months.
4. Mr. Dipak Kumar, learned counsel for the petitioner has not disputed the fact about submission of application after the period of six months as also the order passed by the Division Bench of this Court in L.P.A. No. 211 of 2012.
5. This Court has heard learned counsel for the parties and perused the documents available on record and found therefrom that Clause 5 of the "Jharkhand Mega Project Incentive Rule, 2005" enumerates the methodology/procedure for "Capital Investment Subsidy" made by the Mega Industries, which prescribed the time period of six months for submitting such application. The Clause 5 thereof reads as under :
State of Punjab and Ors. vs. Krishan Niwas
Sawarn Singh & Anr. Vs. State of Punjab & Ors.
Pepsico India Holding Private Limited Vs. Krishna Kant Pandey
Chandavarkar Sita Ratna Rao Vs. Ashalata S. Guram
Joint Action Committee of Air Line Pilots' Assn. of India v. DGCA
Bathutmal Raichand Oswal v. Laxmibai R. Tarta
The main legal point established in the judgment is that the court upheld the rejection of the petitioner's claim for Capital Investment Subsidy as the application was filed after the stipulated peri....
The main legal point established in the judgment is the necessity for determining the real questions in controversy between the parties and the consideration of prejudice or injustice to the other pa....
The main legal point established in the judgment is the court's discretion to condone the delay in submission of the application for interest subsidy based on the sufficiency of cause shown by the pe....
When a period of time is prescribed "from" a specific date, the starting date is excluded from the computation. Consequently, an act performed on the anniversary of that starting date falls within th....
The absence of a cut-off date in the Special Mega Package allows entitlement to incentives regardless of the commercial production start date relative to the previous policy's expiry.
The government cannot retroactively change subsidy claims based on later communications that deviate from previously established entitlements, respecting the doctrines of promissory estoppel and legi....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.