SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2022 Supreme(Jhk) 990

IN THE HIGH COURT OF JHARKHAND AT RANCHI
RAVI RANJAN, SUJIT NARAYAN PRASAD, JJ.
Senbo Engineering Limited – Appellant
Versus
East Central Railway, Hajipur – Respondent
Commercial Appeal No. 4 of 2021
Decided On : 29-08-2022

Advocates:
Advocate Appeared:
For the Appellant : Nand Kishore Singh.
For the Respondent: Pratyush Kumar.

Headnote:

Commercial Courts Act, 2015 – Section 13 – Arbitration and Conciliation Act, 1996 – Section 34 – Ground for termination – Assailing the order – Instant appeal has been preferred under Section 13 of Commercial Courts Act, 2015 assailing order/judgment passed in Commercial Revocation Case, by which, an arbitral award passed by sole Arbitrator, has been set aside in entirety – Held, So far as argument advanced on behalf of learned counsel for appellant that issue may be decided on merit by this Court in appeal itself instead of remitting matter before concerned Court, Court is of view that since this Court is sitting in an appeal and since issue of consideration of factual aspects, which were raised before learned Arbitrator, have been placed before Court dealing with issue under Section 34 of Act, 1996, that Court is required to deliberate upon same considering relevant documents or evidence for its proper appreciation, it would not be proper for this Court to exercise such power under appellate jurisdiction rather this Court deems it fit and proper to remit matter before concerned Court –Appeal allowed.

JUDGMENT :

RAVI RANJAN, J.

1. The instant appeal has been preferred under Section 13 of the Commercial Courts Act, 2015 assailing the order/judgment dated 06.01.2021 passed in Commercial Revocation Case No. 07 of 2019, by which, an arbitral award dated 23.02.2019 passed by the sole Arbitrator, has been set aside in entirety.

2. The brief facts of the case, required to be considered in this appeal, stand enumerated as under:

    A notice inviting tender was issued by the East Central Railway through its General Manager for construction of seven bridges between Tori to Shivpuri (Km 23.00 to Km 44.00) in connection with construction of Tori Shivpur new BG Rail line project in Latehar district of Jharkhand State and the work was awarded to the respondent vide LOA No. ECR/CAO/Con/WT/S/165/13616 dated 03.06.2014. The value of the work was estimated to the tune of Rs. 82,80,54,283.78 and the work was to be completed within 24 months from the date of issuance of acceptance letter i.e. till 02.06.2016. A formal contract/agreement was entered into in between the parties on 31.10.2014. However, the work could not have been completed within the stipulated time. Thereafter, the East Central Railway vide its letter dated 11.07.2016 issued letter for termination of contract. Thus, the dispute arose between the parties and the claimant-respondent-appellant filed an application before this Court for appointment of an Arbitrator to adjudicate upon the dispute and this Court vide order dated 28.07.2017 passed in Arbitration Application No. 16 of 2017 has appointed Hon’ble Mr. Justice D.G.R. Patnaik, a Former Judge of this Court as Arbitrator and the dispute was referred for arbitration.

The award was passed in favour of the appellant holding the termination of the contract to be illegal and has passed the order allowing the claim to the extent of Rs. 28,45,90,777.56 under different heads as under:

S. No.

Description

Amount Allowed

1.

Item No. I: Refund of encashed Bank Guarantees

Rs. 8,59,08,325/-

2.

Item No. 2: Compensation for loss of on going work

Rs. 2,44,85,062/-

3.

Item No. 3: Compensation for loss suffered on Batching Plant

Rs. 36,00,000/-

4.

Item No. 7: Loss of profit

Rs. 9,63,19,088.13/-

5.

Item No. 11 and 12: Compensation for expenses incurred in purchase, supply and cutting, bending, fixing TMT Bars and for procurement, fabrication of structural steel as per relevant clause of the contract

Rs. 1,83,38,701.96/-

6.

Item No. 10: Costs

Rs. 10,00,000/-

7.

Item No. 9: Payment of interest

Rs. 5,49,39,600.47/-

(i) Interest on Item No. 1 = Rs. 4,12,35,996/-

(ii) Interest on item nos. 2, 10 and 11 = Rs. 1,37,03,604.47/-

(iii) Interest on item No. 7: It shall be calculated @ 12 % per annum from the date of award till the date of actual payment made on the amount of loss of profit to the tune of Rs. 9,63,19,088.13

To be calculated

 

Total

Rs. 28,45,90,777.56/-

    The respondent East Central Railway, being aggrieved with the award, assailed the same by invoking the jurisdiction conferred under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the ‘Act’) 1996.

The Court below, after hearing the application filed under Section 34 of the Act, 1996 has considered the aforesaid award to be incorrect, as would appear from paragraphs-26, 27 and 28 of the order passed by the concerned Court. The finding recorded by the concerned court dealing with the application under Section 34 of the Act, 1996 as referred under paragraphs-26, 27 and 28 read as under:

“26. In the present case award to the extent of Rs. 8,59,08,325.00 has been made towards refund of encashed bank guarantee and security deposit vide item no 1 and further vide item no. 9 (I) award has been made towards interest on item no. 1. In this regar

      Click Here to Read the rest of this document
      1
      2
      3
      4
      5
      6
      7
      8
      9
      10
      11
      SupremeToday Portrait Ad
      supreme today icon
      logo-black

      An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

      Please visit our Training & Support
      Center or Contact Us for assistance

      qr

      Scan Me!

      India’s Legal research and Law Firm App, Download now!

      For Daily Legal Updates, Join us on :

      whatsapp-icon Back to top