IN THE HIGH COURT OF JHARKHAND AT RANCHI
ANUBHA RAWAT CHOUDHARY, J.
State of Jharkhand through the Secretary, Department of Information Technology - Petitioner
Versus
Webel Technology Limited - Respondent
Arbitration Appeal No. 6 of 2009
Decided On : 02-03-2023
Arbitration and Conciliation Act, 1996 – Section 34, 37 – Indian Contract Act, 1872 – Sections 53, 73, 74, 62 – Termination of agreement – Arbitration appeal has been filed under Section 37 of Arbitration and Conciliation Act, 1996 against order passed by learned Subordinate Judge I, Ranchi in Misc – Case, whereby learned court below has refused to interfere with award passed by learned sole Arbitrator under Section 34 of Arbitration and Conciliation Act, 1996 – Held, Court finds that learned court below has in its findings, inter alia, mentioned about case of respective parties and as to what the learned Arbitrator had done and mentioned about principles of law, but has not specifically dealt with and considered various grounds which were raised in the petition filed under Section 34 of Arbitration and Conciliation Act – Judgment passed by the learned court below is non-speaking on many aspects of matter and suffers from non-consideration of many points which were raised by appellant before learned court below in its petition under Section 34 of Aforesaid Act of 1996 – However, before this Court, counsel for parties have made elaborate arguments and the arguments were also recorded and uploaded earlier and thereafter, this judgment is being pronounced today – Arbitration appeal disposed of.
JUDGMENT :
[Anubha Rawat Choudhary, J.]
1. Heard the learned counsel for the parties.
2. This arbitration appeal has been filed under Section 37 of Arbitration and Conciliation Act, 1996 against the order dated 16.06.2009 passed by learned Subordinate Judge I, Ranchi in Misc. Case No. 54 of 2007, whereby the learned court below has refused to interfere with the award dated 23.07.2007 passed by the learned sole Arbitrator under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the Act of 1996). The learned Arbitrator has directed the appellant to pay Rs. 17,05,00,000/- to the claimant/respondent with interest @ 12 percent per annum from April, 2004 till the date of the award and has directed that if the said amount is not paid within the period of 30 days from the date of the award, the appellant shall pay the same with interest @ 14% from the date of the award till the date of payment. The learned Arbitrator has also awarded the cost of arbitration amounting to Rs. 1,56,000/-. The learned Arbitrator, however, rejected the counter-claim of the appellant amounting to Rs. 7,61,25,000/- against claimant/respondent.
3. The case of appellant, in brief, is that the appellant (Department of Information and Technology, Govt. of Jharkhand) has decided to provide Computer Education in 500 Schools in Jharkhand. M/s. Webel Technology Ltd. (claimant-respondent) made an offer to the Department to undertake Computer Literacy Programme in association with IBM in 500 Schools in the State of Jharkhand under scheme Build, Own, Operate and Transfer (BOOT) basis. The parties entered into an agreement on 2nd April, 2003. The broad terms of the agreement are that the respondent shall provide Computer Education Services in 500 Schools selected by the I.T. Deptt. (appellant) at the cost of Rs. 105/- per month per student. Payment to be made by the School authorities or by any other nodal agency to be identified by the information Technology Ministry. The Duration for the contract shall be for 5 years commencing from the date of signing the contract or commencement of operation in Schools whichever is later. There is a clause which provides for termination of the contract.
4. It is the case of the appellant-state that the claimant-respondent made an offer in the month of September, 2002 to undertake Computer Literacy Programme in 500 schools in the State of Jharkhand under the scheme “Build, Own, Operate and Transfer (BOOT) basis”. As per the BOOT model of implementation of any project, the government accords permission to the concessionaire to undertake the work relating to the project normally on the site owned by the government and the state has no financial liability on the project. It is the concessionaire who was to build the project, operate it and recover its investment and profit through charging from the services and after an agreed period, transfer the project to the State. The claimant had submitted a draft of agreement for implementation of the aforesaid project approved by the Government of Jharkhand and agreement between the parties was executed on 02.04.2003. As per the agreement, the aforesaid work was to be done in 500 schools at the cost of Rs. 105/- per student for total of 500 students per school. On 30.04.2003, the claimant intimated the State that it was ready to start with the computer education in 100 school by 31.05.2003 and requested to furnish the list of schools. In response, vide letter dated 30.04.2003 the claimant was informed that the list of the schools will be given shortly. It is further case of the State that before issuance of letter dated 30.04.2003, no approval of the government was taken and the authority who had issued the letter dated 30.04.2003 was the Secretary of Department of Information and Technology of the State and he was not competent to make any commitment to reimburse co
Phulchand Exports Limited v. O.O.O. Patriot
Kailash Nath Associates v. Delhi Development Authority
Construction and Design Services v. Delhi Development Authority
Haryana Tourism Ltd. v. Kandhari Beverages Ltd.
Project Director, NHAI v. M. Hakeem
UHL Power Company Ltd. v. State of Himachal Pradesh
Patel Engineering Limited v. North Eastern Electric Power Corporation Ltd.
Associate Builders v. Delhi Development Authority
Ssangyong Engineering & Construction Co. Ltd. v. National Highways Authority of India
M.P. Power Generation Co. Ltd. v. ANSALDO Energia SpA
Ssangyong Engg. & Construction Co. Ltd. v. NHAI
Haryana Tourism Ltd. v. Kandhari Beverages Ltd.
Phulchand Exports Ltd. v. O.O.O. Patriot
Clauses in contracts that prohibit claims for damages are against public policy and void under Section 23 of the Indian Contract Act, 1872, as they undermine the sanctity of contracts.
An arbitral award can only be set aside under Section 34 of the Arbitration and Conciliation Act, 1996 if the appellant establishes that the award is in conflict with the public policy of India, is p....
The court upheld the validity of damages awarded to the respondent based on implied findings of invalid termination, interpretation of the liquidated damages clause, and quantification of damages.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.