IN THE HIGH COURT OF JHARKHAND AT RANCHI
SHREE CHANDRASHEKHAR, RATNAKER BHENGRA, JJ.
Central Coalfields Limited & Ors. - Appellants
Versus
M/s ARETPL-AT(JV) - Respondent
LPA No. 155 of 2018
Decided On : 04-07-2022
Cancellation of LOA - Performance Security - Clause 4.2 of NIT - Summary: The court analyzed the cancellation of a Letter of Acceptance (LOA) due to a 2-day delay in furnishing performance security. It discussed the interpretation of Clause 4.2 of the NIT, the discretionary powers of the employer, and the consequences of non-compliance. The court found the decision to cancel LOA illegal and arbitrary, emphasizing the need for fairplay and judicial restraint in contractual matters.
Fact of the Case:
M/s ARETPL-AT(JV) approached the writ Court against the cancellation of LOA due to a 2-day delay in furnishing performance security. The court held that the stipulation under Clause 4.2 of NIT for performance security was not mandatory and the order of blacklisting without a show cause notice was bad in law.
Finding of the Court:
The court found the decision to cancel LOA illegal and arbitrary, emphasizing the need for fairplay and judicial restraint in contractual matters.
Issues: The issues included the interpretation of Clause 4.2 of NIT, the legality of the cancellation of LOA, and the requirement for a show cause notice before blacklisting.
Ratio Decidendi: The court emphasized the need for fairplay and judicial restraint in contractual matters, and the requirement for a show cause notice before imposing blacklisting.
Final Decision: LPA No. 155 of 2018 was dismissed, but the natural consequence of the order did not lead to the award of the remaining contract to the respondent.
ORDER :
Shree Chandrashekhar, J.
M/s ARETPL-AT(JV) approached the writ Court against the order contained in letter dated 12th October 2017 by which Letter of Acceptance (in short 'LOA') with respect to the work of “Hiring of HEMM for removal of OB at outsourcing patch of Konar part of AKK OCP of B-K Area for a period of four years” was cancelled for 2 days' delay in furnishing performance security.
2. The writ Court held that the stipulation under Clause 4.2 of NIT for furnishing performance security of 5% of annualized value of contract amount to be deposited within 28 days of LOA by the successful bidder was not a mandatory condition. The writ Court further held that the order of blacklisting for 3 years issued under Clause 4.2 of General Terms and Conditions (in short 'GTC') without issuing a show cause notice was bad in law.
3. The aforesaid findings by the writ Court in WP(C) No. 6106 of 2017 have been challenged by Central Coalfields Limited (in short 'CCL') on the grounds that (i) there was no concluded contract between the parties (ii) CCL cancelled LOA and passed the order of forfeiture and debarment as provided under NIT and, (iii) writ Court exceeded its jurisdiction to interpret the clauses in NIT.
4. In support of the aforesaid submissions, Mr. A.K. Das, the learned counsel for the CCL has referred to the judgments in “Bharat Coking Coal Ltd. v. AMR Dev Prabha” (2020) 16 SCC 759, “South Eastern Coalfields Limited v. S. Kumar's Associates AKM (JV)” (2021) 9 SCC 166, “Central Coalfields Limited v. SLL-SML (Joint Venture Consortium)” (2016) 8 SCC 622,“South Delhi Municipal Corpn. v. Ravinder Kumar” (2015) 15 SCC 545, “Rajasthan State Industrial Development & Investment Corpn. v. Diamond & Gem Development Corpn. Ltd.” (2013) 5 SCC 470, “Satish Batra v. Sudhir Rawal” (2013) 1 SCC 345, “Kisan Sahkari Chini Mills Limited v. Vardan Linkers” (2008) 12 SCC 500 and “Global Energy Ltd. v. Adani Exports Ltd.” (2005) 4 SCC 435.
5. An e-Tender Notice was published on 15th May 2017 for engaging contractor for “Hiring of HEMM for removal of OB at outsourcing patch of Konar part of AKK OCP of B-K Area for a period of four years”. The work under e-Tender Notice pertained to blast hole drilling, blasting, excavation, loading and transportation of all kinds of soil, rocks, broken rocks, hard rocks and extraneous materials including mixed soil, mixed hard soil, clay soil, pebbles, stone etc. and dumping outside the working zone. M/s ARETPL-AT(JV) which is respondent before us was declared L-1 bidder on 15th August 2017 and pursuant thereto LOA was issued to it on 15th August 2017. Under LOA dated 15th August 2017, the respondent was required to furnish performance security of Rs.2,04,04,894/- and additional performance security of Rs.16,06,24,850/- within 28 days – that is, by 12th September 2017. In the meantime, the project site was handed over to the respondent on 18th August 2017 and work order was issued on 29th August 2017.
6. CCL issued letter dated 6th September 2017 reminding the respondent to furnish performance security by due date to avoid any adverse consequence. However, the respondent could furnish performance security of Rs.2,04,04,894/- through 4 BGs drawn on State Bank of India, SME Branch, Dhanbad, all dated 11th September 2017, through letter dated 14th September 2017. There is no dispute that the aforesaid bank guarantees furnished through letter dated 14th September 2017 were received by CCL on 15th September 2017.
7. As noticed above, by a communication dated 15th October 2017 the respondent was intimated cancellation of award of tender through LOA dated 15th August 2017.
8. Before the writ Court, the decisions in “Global Energy Ltd.”, “Kisan Sahkari Chini Mills Limited ”, “Verigamto Naveen v. Govt. of A.P.” (2001) 8 SCC 344 and “Noble Resources Ltd. v. State of Orissa” (2006) 10 SCC 236 were pressed by CCL to submit that the terms of NIT are not amenable to judicial scrutiny and the writ Court should not have interfered
Bharat Coking Coal Ltd. v. AMR Dev Prabha
South Eastern Coalfields Limited v. S. Kumar's Associates AKM (JV)
Central Coalfields Limited v. SLL-SML (Joint Venture Consortium)
South Delhi Municipal Corpn. v. Ravinder Kumar
Rajasthan State Industrial Development & Investment Corpn. v. Diamond & Gem Development Corpn. Ltd.
Kisan Sahkari Chini Mills Limited v. Vardan Linkers
Global Energy Ltd. v. Adani Exports Ltd.
Verigamto Naveen v. Govt. of A.P.
Noble Resources Ltd. v. State of Orissa
Joshi Technologies International Inc. v. Union of India
Blacklisting a contractor without a fair hearing violates principles of natural justice, rendering such actions invalid, while the termination of the contract for non-compliance with security require....
The cancellation of a Letter of Acceptance due to an 8-day delay in performance security submission was deemed unreasonable, emphasizing the need for fairness in public contract processes.
The main legal point established in the judgment is the validity of the Bank Guarantee submitted by the petitioner and the application of principles of natural justice by the respondents.
It is well settled that mere existence of an alternative remedy or an alternative forum does not stand as an impediment on Court to exercise its jurisdiction under Article 226 of Constitution of Indi....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.