SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2024 Supreme(Jhk) 304

IN THE HIGH COURT OF JHARKHAND AT RANCHI
RONGON MUKHOPADHYAY, DEEPAK ROSHAN, JJ.
Ambey Mining Private Limited – Appellant
Versus
Bharat Coking Coal Limited – Respondent
W.P.(C) No. 1576 of 2017
Decided on : 07-05-2024

Advocates:
Advocate Appeared:
For the Appellant :Mr. Sumeet Gadodia, Mrs. Shilpi Sandil Gadodia, Mr. Ranjit Kushwaha, Mr. Ritesh Kumar Gupta, Advocate.
For the Respondents:Mr. Anupam Lal Das, Mr. Anoop Kumar Mehta, Mr. Amit Sharma, Advocate.

IMPORTANT POINT
The court established that state actions must comply with legal and environmental regulations, and arbitrary actions that violate constitutional rights can be challenged through writ petitions, even in the context of contractual disputes.

Headnote:

[MANDAMUS] - [CONTRACTUAL DISPUTE] - [Article 14 of the Constitution of India, Section 56 of the Indian Contracts Act, 1872, Environment Protection Act, 1986] - The court addressed the legality of the tender issued by Bharat Coking Coal Limited (BCCL) for open cast mining without the requisite environmental clearance, which was only granted for underground mining. The court interpreted Article 14 as prohibiting arbitrary state action, emphasizing that BCCL's actions were illegal and arbitrary, leading to the conclusion that the contract was frustrated under Section 56 of the Indian Contracts Act due to the withdrawal of permission by the Directorate General of Mines Safety (DGMS). The court ordered the closure of the contract and the refund of bank guarantees to the petitioner, highlighting the importance of compliance with environmental regulations in state contracts.

Fact of the Case:

The petitioner, Ambey Mining Pvt. Ltd., sought a writ of mandamus against BCCL for the closure of a contract for mining operations due to the withdrawal of permission by DGMS and the lack of environmental clearance for open cast mining. The petitioner had faced local protests and work stoppages due to safety concerns related to blasting activities near residential areas.

Finding of the Court:

The court found that BCCL had acted arbitrarily by inviting tenders for open cast mining without the necessary environmental clearance, violating Article 14 of the Constitution. The court also noted that the contract had effectively ended due to the inability to perform the work legally, as the DGMS had withdrawn permission for blasting activities.

Issues: 1. Whether the issuance of the tender by BCCL was legal given the lack of environmental clearance for open cast mining? 2. Did the withdrawal of permission by DGMS frustrate the contract under Section 56 of the Indian Contracts Act? 3. Was the retention of bank guarantees by BCCL justified after the contract period expired?

Ratio Decidendi: The court held that the lack of environmental clearance rendered the tender illegal and arbitrary, violating Article 14. It concluded that the contract was frustrated due to the withdrawal of permission by DGMS, and thus, the petitioner was entitled to the refund of bank guarantees.

Final Decision: The writ petition was allowed, directing BCCL to issue a closure report for the contract and refund the original bank guarantees amounting to Rs. 3.20 crores to the petitioner.

JUDGMENT :

Deepak Roshan, J

Heard learned counsel for the parties.

2. The present writ application has been filed by petitioner primarily seeking following reliefs:-

    (a) Issue an appropriate writ, order or direction or a writ in the nature of Mandamus directing the Respondents to make a final decision for the closure of the contract in terms of the representation dated 05.07.2021 made by the Petitioner before the Respondents vis a vis its non-execution due to the restrictions imposed by the DGMS vide its Order dated 18.11.2015 (Annexure-9 of the Writ Petition) and also in light of the Respondents decision of issuance of the tender in complete violation and disregard of the environment clearance rules, and direct the Respondents to pay the dues of the Petitioner in accordance with the law.

“Issue an appropriate writ, order or direction or a writ in the nature of Mandamus restraining/injuncting the Respondents from taking any coercive steps against the Petitioner and be further pleased to direct the parties to resolve disputes and differences through a dispute resolution mechanism/Arbitration in accordance with the Circular dated07.04.2017, issued by Coal India Limited, Civil Engineering Division.”

(b) For issuance of appropriate writ/order/direction commanding upon the Respondents showing them cause as to how can they justify the work tendered vide Tender Notice No. 147 vide Ref. No. BCCL/GM(CMC)/F-HEMM-OS/2014/2375 dated 11.06.2014 in the facts and situations and also in the light of withdrawal of permission by the DGMC and upon receiving their reply pass appropriate orders for taking suitable actions against the concerned authorities of the Respondents who have been instrumental in notifying the tender works without ascertaining the factual and technical viability of the work in question;

AND/OR

(c) The Petitioner further prays for issuance of a writ, order or direction commanding upon the respondents to recall its Notices dated 7/9.5.2016 (Annexure-10) and 28.05.2016 (Annexure-13) which have been issued by the respondents without any application of mind and in teeth of the direction given by the DGMS, which is binding and also in complete ignorance of the facts and situations narrated by the petitioner ide its various letters and communications including the letters dated 17.11.2015 (Annexure-8) and 25.5.2016 (Annexure-12); whereby the petitioner has, on the basis of the facts and circumstances narrated in the said representations/letters, prayed for foreclosure of the aforesaid contract;

3. Brief facts of the case is that Respondent-Bharat Coking Coal Limited (for short ‘BCCL’), vide its Tender Notice No. 147 dated 11.06.2014, published a Notice Inviting Tender for its Maheshpur colliery of Govindpur Area for the following works:-

    (i) Removal of Overburden – 226.47 LM; and

(ii) Extraction of coal – 67.28 LMT for five years.

4. Petitioner participated in the aforesaid tender and was issued Letter of Acceptance for above-referred works on 18.12.2014 and, pursuant to which, Petitioner submitted three separate Bank Guarantees each amounting to Rs. 1.00 Crore i.e. total Bank Guarantees of Rs. 3.00 Crores on 19.03.2015 for due performance of the contract.

5. On 15.05.2015, Petitioner was handed over the site and mutual schedule of work was agreed between Petitioner and Respondent-BCCL vide letter dated 25.06.2015, wherein work was to start on 1st July, 2015. It is an undisputed fact that Petitioner started the work and continued to execute the work till 01.10.2015, but Petitioner was facing acute hindrances from local people due to problems of land acquisition and re-habilitation and re-settlement.

6. The case of the Petitioner is that Director General, Mines Safety, Dhanbad (for short “DGMS”) on 12.11.2013 granted permission to BCCL for Maheshpur Colliery permitting use of explosives for blasting work up-to a distance of beyond 100 mete

                    Click Here to Read the rest of this document
                    1
                    2
                    3
                    4
                    5
                    6
                    7
                    8
                    9
                    10
                    11
                    SupremeToday Portrait Ad
                    supreme today icon
                    logo-black

                    An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

                    Please visit our Training & Support
                    Center or Contact Us for assistance

                    qr

                    Scan Me!

                    India’s Legal research and Law Firm App, Download now!

                    For Daily Legal Updates, Join us on :

                    whatsapp-icon Back to top