IN THE HIGH COURT OF JHARKHAND AT RANCHI
RONGON MUKHOPADHYAY, DEEPAK ROSHAN, JJ.
Ambey Mining Private Limited – Appellant
Versus
Bharat Coking Coal Limited – Respondent
W.P.(C) No. 1576 of 2017
Decided on : 07-05-2024
[MANDAMUS] - [CONTRACTUAL DISPUTE] - [Article 14 of the Constitution of India, Section 56 of the Indian Contracts Act, 1872, Environment Protection Act, 1986] - The court addressed the legality of the tender issued by Bharat Coking Coal Limited (BCCL) for open cast mining without the requisite environmental clearance, which was only granted for underground mining. The court interpreted Article 14 as prohibiting arbitrary state action, emphasizing that BCCL's actions were illegal and arbitrary, leading to the conclusion that the contract was frustrated under Section 56 of the Indian Contracts Act due to the withdrawal of permission by the Directorate General of Mines Safety (DGMS). The court ordered the closure of the contract and the refund of bank guarantees to the petitioner, highlighting the importance of compliance with environmental regulations in state contracts.
Fact of the Case:
The petitioner, Ambey Mining Pvt. Ltd., sought a writ of mandamus against BCCL for the closure of a contract for mining operations due to the withdrawal of permission by DGMS and the lack of environmental clearance for open cast mining. The petitioner had faced local protests and work stoppages due to safety concerns related to blasting activities near residential areas.
Finding of the Court:
The court found that BCCL had acted arbitrarily by inviting tenders for open cast mining without the necessary environmental clearance, violating Article 14 of the Constitution. The court also noted that the contract had effectively ended due to the inability to perform the work legally, as the DGMS had withdrawn permission for blasting activities.
Issues: 1. Whether the issuance of the tender by BCCL was legal given the lack of environmental clearance for open cast mining? 2. Did the withdrawal of permission by DGMS frustrate the contract under Section 56 of the Indian Contracts Act? 3. Was the retention of bank guarantees by BCCL justified after the contract period expired?
Ratio Decidendi: The court held that the lack of environmental clearance rendered the tender illegal and arbitrary, violating Article 14. It concluded that the contract was frustrated due to the withdrawal of permission by DGMS, and thus, the petitioner was entitled to the refund of bank guarantees.
Final Decision: The writ petition was allowed, directing BCCL to issue a closure report for the contract and refund the original bank guarantees amounting to Rs. 3.20 crores to the petitioner.
JUDGMENT :
Deepak Roshan, J
Heard learned counsel for the parties.
2. The present writ application has been filed by petitioner primarily seeking following reliefs:-
“Issue an appropriate writ, order or direction or a writ in the nature of Mandamus restraining/injuncting the Respondents from taking any coercive steps against the Petitioner and be further pleased to direct the parties to resolve disputes and differences through a dispute resolution mechanism/Arbitration in accordance with the Circular dated07.04.2017, issued by Coal India Limited, Civil Engineering Division.”
(b) For issuance of appropriate writ/order/direction commanding upon the Respondents showing them cause as to how can they justify the work tendered vide Tender Notice No. 147 vide Ref. No. BCCL/GM(CMC)/F-HEMM-OS/2014/2375 dated 11.06.2014 in the facts and situations and also in the light of withdrawal of permission by the DGMC and upon receiving their reply pass appropriate orders for taking suitable actions against the concerned authorities of the Respondents who have been instrumental in notifying the tender works without ascertaining the factual and technical viability of the work in question;
AND/OR
(c) The Petitioner further prays for issuance of a writ, order or direction commanding upon the respondents to recall its Notices dated 7/9.5.2016 (Annexure-10) and 28.05.2016 (Annexure-13) which have been issued by the respondents without any application of mind and in teeth of the direction given by the DGMS, which is binding and also in complete ignorance of the facts and situations narrated by the petitioner ide its various letters and communications including the letters dated 17.11.2015 (Annexure-8) and 25.5.2016 (Annexure-12); whereby the petitioner has, on the basis of the facts and circumstances narrated in the said representations/letters, prayed for foreclosure of the aforesaid contract;
3. Brief facts of the case is that Respondent-Bharat Coking Coal Limited (for short ‘BCCL’), vide its Tender Notice No. 147 dated 11.06.2014, published a Notice Inviting Tender for its Maheshpur colliery of Govindpur Area for the following works:-
(ii) Extraction of coal – 67.28 LMT for five years.
4. Petitioner participated in the aforesaid tender and was issued Letter of Acceptance for above-referred works on 18.12.2014 and, pursuant to which, Petitioner submitted three separate Bank Guarantees each amounting to Rs. 1.00 Crore i.e. total Bank Guarantees of Rs. 3.00 Crores on 19.03.2015 for due performance of the contract.
5. On 15.05.2015, Petitioner was handed over the site and mutual schedule of work was agreed between Petitioner and Respondent-BCCL vide letter dated 25.06.2015, wherein work was to start on 1st July, 2015. It is an undisputed fact that Petitioner started the work and continued to execute the work till 01.10.2015, but Petitioner was facing acute hindrances from local people due to problems of land acquisition and re-habilitation and re-settlement.
6. The case of the Petitioner is that Director General, Mines Safety, Dhanbad (for short “DGMS”) on 12.11.2013 granted permission to BCCL for Maheshpur Colliery permitting use of explosives for blasting work up-to a distance of beyond 100 mete
Century Spg. And Mfg. Co. Ltd. v. Ulhasnagar Municipal Council
Gunwant Kaur v. Municipal committee, Bhatinda
Indian Explosives Limited and Anr. Vs. Coal India Limited and Ors.
The court established that state actions must comply with legal and environmental regulations, and arbitrary actions that violate constitutional rights can be challenged through writ petitions, even ....
Tender issuance without requisite environmental clearance violates Article 14, rendering state action arbitrary and warranting judicial intervention.
The power of judicial review is not normally exercised in contractual obligations, and parties may be relegated to adjudication of their rights by resorting to remedies provided for adjudication of p....
Non-commencement of work allows for cancellation of administrative approvals under Article 226, ensuring public fund utilization.
The main legal point established in the judgment is the validity of the Bank Guarantee submitted by the petitioner and the application of principles of natural justice by the respondents.
Environmental clearance for mining is project and site-specific. Legal entities are distinct, preventing the attribution of one entity's regulatory failures to another absent proof of fraudulent inco....
Public authorities must act fairly and cannot arbitrarily terminate contracts without justification, reinforcing the legitimacy of expectations within public-private partnerships.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.