SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Jhk) 199

IN THE HIGH COURT OF JHARKHAND AT RANCHI
M. S. Ramachandra Rao, C.J., Deepak Roshan, J.
The State Highways Authority of Jharkhand - Appellant
Versus
Intercontinental Consultants & Technocrats Pvt. Ltd - Respondent
Commercial Appeal No. 7 of 2024
Decided On : 28-02-2025

Advocates:
Advocate Appeared:
For the Appellant :Mr. Rajiv Ranjan, Advocate General Mr. Ashutosh Anand, AAG-III Mr. Sharad Kaushal, A.C. to A.A.G.-III Mr. Shray Mishra, A.C. to A.G., Ms. Bharti Kumari, A.C. to A.G.
For the Respondent:Mr. Ajit Kumar, Sr. Advocate Mr. Vikalp Gupta, Advocate

The court emphasized that a termination of contract deemed improper by an arbitral tribunal cannot be set aside without substantial justification, requiring detailed reasoning from a reviewing court.

Headnote:(A) Commercial Courts Act, 2015 - Section 13; Arbitration and Conciliation Act, 1996 - Section 34 - Appeal challenging judgment upholding arbitral award - The Commercial Court ruled that the application under Section 34 of the Act is not an appeal and reviewed limited grounds for setting aside an arbitral award. The Court emphasized that the termination of the contract by the appellant was illegal per the arbitrator's findings. (Paras 9, 12, 19, 21)

(B) The Commercial Court failed to adequately address claims 2 to 9 leading to a remand for re-evaluation by the Commercial Court. (Paras 20, 22)

Facts of the case:
The State Highway Authority of Jharkhand has appealed against a judgment maintaining an award favoring the respondent concerning the termination of a consultancy contract for a state road project initiated in 2016. The contract was terminated on grounds of breach, leading to arbitration.

Findings of Court:
Essential findings on claim 1 upheld the arbitrator's decision, classifying the termination as improper and illegal under the relevant contractual provisions.

Issues: Whether the grounds presented warrant interference under Section 34 of the Act and the adequacy of the Commercial Court's reasoning regarding claims 2 to 9.

Ratio Decidendi: The court holds that an unexpected termination cannot be justified under contract clauses and reiterates the Commercial Court's duty to provide detailed reasoning for its conclusions on all claims.

Result: Judgment set aside as to claims 2 to 9; matter remitted for fresh consideration.

Table of Content
1. background of contractual disputes (Para 1 , 2 , 3 , 4 , 5 , 6 , 7)
2. issues related to contract termination and performance (Para 8 , 10 , 11 , 12)
3. analysis of the commercial court's judgment (Para 9 , 13 , 14 , 15 , 16 , 17)
4. reasons for upholding partial findings of arbitral tribunal (Para 18 , 19)
5. remanding claims 2 to 9 for reconsideration and fresh judgment. (Para 21)
6. final orders and remittal of case for further consideration (Para 22 , 23 , 24)

JUDGMENT :

M.S. Ramachandra Rao, C.J.

1. This Commercial Appeal is preferred under Section 13 of the COMMERCIAL COURTS ACT , 2015 challenging the judgment dt. 16.03.2024 of Additional Judicial Commissioner-III-cum-Presiding Officer, Commercial Court, Ranchi (for short ‘the Commercial Court’) passed in Commercial Arbitration Case No. 04/2022.

2. By the said judgment the Commercial Court has upheld the Award dt. 14.12.2021 of the Arbitral Tribunal and dismissed the application under Section 34 of the Arbitration and Conciliation Act, 1996 (in short ‘the Act’) filed before the said Court by the appellant/applicant/State Highway Authority of Jharkhand.

3. Admittedly, the appellant had entered into an agreement with the respondent in collaboration with another for providing consultation services relating to the Second Jharkhand State Road Project (ABD Funded). This agreement called the ‘Time-Based Contract Agreement’ was initiated on 02.11.2016 and the contract stipulated a revised price of US$ 29,58,300.00 plus Indian Rs.30,60,60,750.00 for the execution, completion of works, and rectification of defects, inclusive of provisional sum and contingencies but exclusive of local indirect taxes.

4. Following the issuance of a notice to proceed on 16.11.2016, work officially commenced on 01.12.2016. The duration of the contract was set at 50 months including a two month pre-construction period and the subsequent 12 month defects and liabilities period starting from the effective date of the contract.

5. The appellant terminated the contract on 05.06.2018 allegedly due to breach of contract by the respondent.

6. The disputes were referred to an arbitrator. Before the learned arbitrator, the respondent raised 9 claims while the appellant raised counter claims.

7. The decision of the Arbitral Tribunal along with 10 claims passed in the Award is as under:

Claim No.Contractor’s claim AmountRespondent’s Assessment & Counter claimTribunal Assessment
INRUSDINRUSD
SOC 1----Claim RejectedClaimant’s Claim is upheld----
SOC 26,44,67,0314,66,205Claim Rejected6,44,67,0314,66,205
SOC 32,26,49,000Claim Rejected2,26,49,000
SOC 46,27,41,0946,39,208Claim Rejected6,27,41,0946,39,208
SOC 568,00,000Claim RejectedRejected----
SOC 61,03,42,66482,156Claim Rejected1,01,35,81080,500
SOC727,79,5169,11,386Claim Rejected40,68,680--
SOC865,22,00065,22,000
Sub Total16,95,01,30588,98,95517,05,83,61511,85,913
SOC912% interest on the above sum12% interest on the above sum 13Interest for INR=10 % Compounded and for USD=8% compounded per year2,42,04,1771,68,269
Counter claim of the respondentDisallowed
Total19,47,87,9213,54,182

8. The appellant questioned the same before the Commercial Court on several grounds and the respondent refuted the said grounds.

The judgment of the Commercial Court

9. The Commercial Court first considered the scope of Section 34 of the Act and referred to the judgments cited by both the parties on the said aspect. It took the view that an application under Section 34 of the Act is not an appeal and the evidence cannot be re-appreciated as in an appeal. It also recognized that there are limited grounds specified in Section 34 of the Act for setting aside an arbitral Award, and after quoting Section 34 of the Act, framed the question as to “whether the Award given by the Arbitrator is against the Public Policy of India with its explanation or it is hit by the grounds mentioned under Section 34 of the Act?”

10. While dealing with Claim 1 which related to setting aside the illegal termination of co

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top